CHange, Order No. 5 March 20, 1986
Contract No. 85-01 '�
' �' / '
Owner: City of Oshkosh )
Contractor: Centennial Contractors Corporation
Engineer: Howard Needles Tammen & Bergendoff
Contract No. 85-01, SEWER INTERCEPTOR, is hereby amended and changed as
follows:
Additional cost to the Contract for removal of Rock necessary to install
sewer interceptor. Rock was encountered along 8th St. from immediately
west of the intersection of Iowa St. to the intersection of Oregon St.
This Change Order is for the additional costs encountered which are
attributable to the rock. These costs were incurred from the period
October 9, 1985 to January 10, 1986 and are in addition to the costs
previously tabulated under Change Order No. 2 for this Contract.
Original Amount of Contract $2, 215, 195. 00
Total Amount of Previous Change Orders to Date 288, 093. 49
Previous Adjusted Contract Amount $2, 503, 288. 49
Change Order No. 5 Amount $120, 589. 99
Total Amount of Current Contract Including C.O. N $2, 623, 878. 48
RECOMMENDED:
____ By: di,"
--. ---_ of . .~�~^ _~ ~= fk
Manager
����-����u�_���_����������__
City Clerk
'
-__-_ �___~�A
Approved and Accepted
Centennial Construction Corp.
I certify that provision has been made to pay the liability that will
accrue to the City of Oshkosh, Wisconsin, under the within Change Order.
' /]F or Comptroller-�• � � - -
�. ` _____
City Attorn=�
.
Change Order No. 5 Page 2 of 2
Contract No. 85-01 - Sewer Interceptor
Breakdown of Additional Costs Attributable to Rock for the period
from October 9, 1985 through January 10, 1986. (This change order is for
costs for which documentation is complete. One final rock associated
change order will be processed upon final submittal and documentation of
all rock associated costs. )
Costs For a Drill Operator and Drill Rig
Furnished By Centennial Contractors $30, 038. 00
Costs For Drill Rigs, Drill Operators,
Blasters, and Blasting Equipment Furnished
By Subcontractor, Don Lind $109, 096. 73
Generator And Pumping Costs Furnished
By Centennial Contractor' s $33, 728. 72
Centennial Contractor' s Main Line Labor Costs $35, 828. 15
Centennial Contractor' s Main Line Equipment
Costs (does not include trucking costs,
generator or pump costs already tabulated) $103, 853. 87
Trucking Costs $38, 9694. 77
078. 19
Miscellaneous Costs $2, 078. 19
Extra Backfill Costs for which tickets
have been furnished to date $13, 468. 47
Total $366, 996. 90
All of above Costs
include OH&P
Change Order No. 2 Costs
Included In Above Amount $246, 406. 91
Change Order No. 5 Amount $120, 589. 99
•