Loading...
HomeMy WebLinkAboutPW CNT 85-01/CNG OR #5/Cetennial Contractors . CHange, Order No. 5 March 20, 1986 Contract No. 85-01 '� ' �' / ' Owner: City of Oshkosh ) Contractor: Centennial Contractors Corporation Engineer: Howard Needles Tammen & Bergendoff Contract No. 85-01, SEWER INTERCEPTOR, is hereby amended and changed as follows: Additional cost to the Contract for removal of Rock necessary to install sewer interceptor. Rock was encountered along 8th St. from immediately west of the intersection of Iowa St. to the intersection of Oregon St. This Change Order is for the additional costs encountered which are attributable to the rock. These costs were incurred from the period October 9, 1985 to January 10, 1986 and are in addition to the costs previously tabulated under Change Order No. 2 for this Contract. Original Amount of Contract $2, 215, 195. 00 Total Amount of Previous Change Orders to Date 288, 093. 49 Previous Adjusted Contract Amount $2, 503, 288. 49 Change Order No. 5 Amount $120, 589. 99 Total Amount of Current Contract Including C.O. N $2, 623, 878. 48 RECOMMENDED: ____ By: di," --. ---_ of . .~�~^ _~ ~= fk Manager ����-����u�_���_����������__ City Clerk ' -__-_ �___~�A Approved and Accepted Centennial Construction Corp. I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. ' /]F or Comptroller-�• � � - - �. ` _____ City Attorn=� . Change Order No. 5 Page 2 of 2 Contract No. 85-01 - Sewer Interceptor Breakdown of Additional Costs Attributable to Rock for the period from October 9, 1985 through January 10, 1986. (This change order is for costs for which documentation is complete. One final rock associated change order will be processed upon final submittal and documentation of all rock associated costs. ) Costs For a Drill Operator and Drill Rig Furnished By Centennial Contractors $30, 038. 00 Costs For Drill Rigs, Drill Operators, Blasters, and Blasting Equipment Furnished By Subcontractor, Don Lind $109, 096. 73 Generator And Pumping Costs Furnished By Centennial Contractor' s $33, 728. 72 Centennial Contractor' s Main Line Labor Costs $35, 828. 15 Centennial Contractor' s Main Line Equipment Costs (does not include trucking costs, generator or pump costs already tabulated) $103, 853. 87 Trucking Costs $38, 9694. 77 078. 19 Miscellaneous Costs $2, 078. 19 Extra Backfill Costs for which tickets have been furnished to date $13, 468. 47 Total $366, 996. 90 All of above Costs include OH&P Change Order No. 2 Costs Included In Above Amount $246, 406. 91 Change Order No. 5 Amount $120, 589. 99 •