Change Order No. 6 April 3, 1986 .
Contract No. 85-01 !:
Owner: City of Oshkosh
Contractor: Centennial Contractors Corporation
Engineer: Howard Needles Tamrnen & Bergendoff
Contract No. 85-01, SEWER INTERCEPTOR, is hereby amended and changed as
follows:
Additional cost to the Contract for removal of Rock necessary to install
sewer interceptor. Rock was encountered along 8th St. from immediately
west of the intersection of Iowa St. to the intersection of Oregon St.
This Change Order tabulates the the total costs for all extra work
associated with the rock. The amount of this Change Order is for the
difference between the total costs attributable to the rock and the rock
costs already approved and processed on Change Orders No. 2 and No. 5.
Centennial Contractors Inc. hereby agrees that all claims associated with
rock removal have been submitted and that no further claims associated
with the rock will be submitted.
Original Amount of Contract $2, 215, 195. 00
Total Amount of Previous Change Orders to Date 408, 683. 48
Previous Adjusted Contract Amount $2, 623, 878. 48
Change Order Na. 6 Amount $ 97, 600. 14
Total Amount of Current Contract Including C. O. No. 6 $2, 721, 478. 62
RECOMMENDED:
Director of Pu - is Works City Manager
( A-!Cam_.--LL612t ----
City Clerk
P rove and Accepted
Centennial Construction Corp.
I certify that provision has been made to pay the liability that will
accrue to the City of Oshkosh, Wisconsin, under the within Change Order.
Appr -,ved A T , For Comptroller
City Attorne.
Change Order No. 6
Contract No. 85-01 - Sewer Interceptor Page 2 of 2
Breakdown of Total Costs Attributable to Rock. This breakdown includes
the amounts previously included in Change Orders No. 2 and No. 5 which
have been processed reflecting partial rock costs.
Costs For a Drill Operator and Drill Rig
Furnished By Centennial Contractors $30, 038. 00
Costs For Drill Rigs, Drill Operators,
Blasters, and Blasting Equipment Furnished
By Subcontractor, Don Lind $109, 096. 73
Generator And Pumping Costs Furnished
By Centennial Contractor' s $33, 728. 72
Centennial Contractor' s Main Line Labor Costs $35, 828. 15
Centennial Contractor' s Main Line Equipment
Costs (does not include trucking costs,
generator or pump costs already tabulated) $103, 853. 67
Trucking Costs $51, 672. 07
Miscellaneous Costs $2, 078. 19
Extra Backfi l l Costs $65, 858. 09
Extra Bituminous Paving Costs due to increase
in trench width as a result of blasting rock $12, 078. 60
Cold Weather Delays for Lateral Crew due to rock
time extension $4, 833. 86
Cold Weather Delays for Mainline Crew due to rock
time extension $15, 530. 76
Total Rock Costs $464, 597. 04
All of above Costs
include OH&P
Change Order No. 2 Costs
Included In Above Amount $246, 406. '31
Change Order No. 5 Costs
Included In Above Amount $160, 589. 99
Total Nos. 2 & 5 $366, 996. 90
Change Order No. 6 Amount $97, 600. 14
•