Change', Order No. 3 March 20, 1986
Contract No. 85-01
` `
Owner: City of Oshkosh ~
Contractor: Centennial Contractors Corporation
Engineer: Howard Needles Tmmmen & Bergendoff
Contract No. 85-01, SEWER INTERCEPTOR, is hereby amended and changed as
follows:
47
Item NO. 1 - Delays to Water Main Break $466. 47
at 9th St. and Oregon Ave. on 1/23/86.
Item No. 2 - Addition of Drop to Manhole at $520. 69
5th St. and Michigan Ave.
Item No. 3 - Providing Electric Service $2, 378. 59
for Temporary Pumping @ Miles Kimball 75$3 365
Total , ,
215, 195. 00
Original Amount of Contract $2, 215, 195..00
Total Amount of Previous Change Orders to Date 275, 819. 74
Previous Adjusted Contract Amount $2, 491, 014. 74
�5 365.
Change Order No.. 3 Amount $3, 365. 75
Total Amount of Current Contract Including C. O. No. 3 $2, 494, 3869. 49
RECOMMENDED:
(Th
' By: w��
-�- - ' ' --- ity
k
irector of ublic Works ity Manager!
__A
axu) "2_,2LIA; )
��
/`
___
. Approved and Accepted
Centennial Construction Corp.
I certify that provision has been made to pay the liability that will
accrue to the City of Oshkosh, Wisconsin, under the within Change Order.
, l°_°- '14e---'
Appr ved o For l: Comptroller
fig,
Y. _
� �
^
City Attorne