HomeMy WebLinkAbout16. 13-419
SEPTEMBER 10, 2013 13-419 RESOLUTION
(CARRIED__6-0_____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT NO. 12-11 WITH PTS CONTRACTORS, INC. FOR
2012 SANITARY SEWER MANHOLE REHABILITATION PROGRAM
($107,202.96)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
PTS CONTRACTORS, INC.
4075 Eaton Road
Green Bay, WI 54311-9340
Net Increase to contract: $107,202.96
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 317-0410-7480-03305 Special Assessments Fund – Storm Water
551-1910-1799-00000 Sewer Utility – Construction Work in Progress
561-2010-1799-00000 Storm Water Utility - Construction Work in Progress
Ol-KOJH
ON THE WATER MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works 5 146 /Dc.p
DATE: September 5, 2013
RE: Change Order No. 2 for Public Works Contract No. 12-11
Sanitary Manhole Rehabilitation/ Infiltration/Inflow Reduction Program
PTS Contractors, Inc. (+$107,202.96)
BACKGROUND
Change Order No. 2 for Contract 12-11 is scheduled for consideration by the Common Council at the
September 10, 2013 meeting. The contract was originally awarded to PTS Contractors, Inc. in October of 2012.
This change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Sanitary Sewer — Contaminated soil was encountered during construction that needed to be removed
and hauled to Waste Management's facility in Berlin, Wisconsin, and additional work and materials were
required to match field conditions.
• Storm Sewer—Storm sewer construction for the Koeller Street sidewalk was added to this contract.
FISCAL IMPACT
Contract Section Change Order Amount New Contract Total CIP Budget Amount
Storm Sewer $33,083.25 $33,083.25 $33,083
Sanitary Sewer $74,119.71 $994,057.70 $900,000
Total $107,202.96 $1,027,140.95 $933,083
Another change order will be needed to reduce bid document quantities to the actual installed quantities.
Various manhole construction work was removed from the project in anticipation of the cost increases
completed as part of Change Order No. 2. This change order is being processed now to allow the contractor to
be paid for additional work that has been performed to date. The final project expenses for sanitary sewer
construction will be less than the original bid amount and will result in the final amount being less than the
$900,000 budgeted.
The majority of the storm sewer construction will be billed to the adjoining property owners on Koeller Street per
the Municipal Code as part of new sidewalk installation at that location.
RECOMMENDATIONS
I recommend approval of Change Order No. 2 to Contact No. 12-11 in the amount of +$107,202.96 to PTS
Contractors, Inc.
Approved:
Mark A. Rohloff
City Manager
SMG/tlt
I:\Engineering\12-11 San MH Rehab-181 Reduction Prog\Project Information\Correspondence\Memo112-11 Memo for CO#2 9-5-13.docx
TO: PTS Contractors, Inc. CHANGE ORDER#2
4075 Eaton Road DATED:August 21, 2013
Green Bay,WI 54311-9340
Your present contract with the City of Oshkosh, Contract No. 12-11, awarded October 23, 2012, is hereby amended and changed
as follows:
NET INCREASE TO: SECTION I REPLACE SANITARY MANHOLES,SECTIONS,FRAMES,&LIDS $3,538.12
NET INCREASE TO: SECTION II SANITARY MANHOLE GROUTING(CONES AND WALLS) $30,240.10
NET INCREASE TO: SECTION III SANITARY MANHOLE GROUTING(BASE SECTIONS) $0.00
NET INCREASE TO: SECTION IV SANITARY MANHOLE&SEWER ABANDONMENT $40,341.49
NET INCREASE TO: SECTION V SANITARY MANHOLE STRUCTURAL CEMENTITIOUS LINER $0.00
NET INCREASE TO: SECTION VI STORM SEWER WORK ON KOELLER STREET $33,083.25
NET INCREASE TO CONTRACT $107,202.96
SECTION I SECTION II SECTION III SECTION IV SECTION V SECTION VI Totals
Bid Total $790,037.42 $94,876.00 $12,512.50 $8,897.20 $4,882.50 $0.00 $911,205.62
C.O.#1 $5,293.62 $3,438.75 $0.00 $0.00 $0.00 $0.00 $8,732.37
Prev.Contract Total $795,331.04 $98,314.75 $12,512.50 $8,897.20 $4,882.50 $0.00 $919,937.99
C.O.#2 $3,538.12 $30,240.10 $0.00 $40,341.49 $0.00 $33,083.25 $107,202.96
Contract Total $798,869.16 $128,554.85 $12,512.50 $49,238.69 $4,882.50 $33,083.25 $1,027,140.95
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Ap roved and acce•ted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh Isconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT:12-11 CHANGE ORDER#2
SECTION I-Replace Sanitary Manholes,Sections,Frames and Lids
CHANGE ORDER#2: ADDITIONAL WORK REQUIRED
ITEM INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE_ PRICE
Contaminated soil
1004 encountered on Sterling. TONS 0.00 57.41 57.41 $18.25_ $1,047.73 _
Doweled pavement bars
1005 EA
on S. Main St. 0.00 70.00 70.00 $11.55 $808.50
1006 Detectable Warning Field SF 0.00 8.00 _ 8.00 $34.50 _ $276.00 -
Lateral Reconnect at MH
1007 T&M
03-491 0.00 1.00 1.00 $1,906.81 $1,906.81
1009 Credit for use of Infi-shield EA
External Chimney Seal 0.00 136.00 136.00 $10.00 $1,360.00
Excessive water in existing
1010 sanitary trench MH 14-139 T&M
0.00 1.00 1.00 $1,906.81 $1,906.81
SECTION I ADDITIONAL WORK SUB-TOTAL: $4,898.12 $1,360.00
NET INCREASE TO SECTION I: $3,538.12
SECTION II-Sanitary Manhole Grouting(Cones&Walls)
CHANGE ORDER#2: BID ITEM ADJUSTMENTS
ITEM INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
201 Sanitary manhole grout, l
complete as specified Gallons 2,900 6,615.00 3,715.00 $8.14 $30,240.10 1
SECTION II BID ITEMS SUB-TOTAL: $30,240.10 $0.00
NET INCREASE TO SECTION II: $30,240.10
Page 1 of 3
CONTRACT: 12-11 CHANGE ORDER#2
SECTION IV-Sanitary Manhole&Sewer Abandonment
CHANGE ORDER#2: BID ITEM ADJUSTMENTS
ITEM INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
3101 Furnish and install
standard sanitary manhole
(4'diameter)with sand Vertical
slurry backfill Feet 11 85.42 74.42 $410.00 $30,512.20
3800 Abandon sanitary
manhole, complete as
specified Each 2 8.00 _ 6.00 $780.00 $4,680.00
SECTION IV BID ITEMS SUB-TOTAL: $35,192.20 $0.00
CHANGE ORDER#2: ADDITIONAL WORK REQUIRED
ITEM INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
3815 Abandon 26"sanitary
sewer,complete as Linear
specified. Feet 0 463.90 463.90 $11.10 $5,149.29
SECTION IV ADDITIONAL WORK SUB-TOTAL: $5,149.29 $0.00
NET INCREASE TO SECTION IV: $40,341.49
Page 2 of 3
CONTRACT: 12-11 CHANGE ORDER#2
SECTION VI-Koeller Street Storm Sewer
CHANGE ORDER#2: ADDITIONAL WORK REQUIRED
ITEM INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
6000 Additional equipment,
labor,and materials to
install storm sewer on
Koeller Street per Invoice
13-621-Koeller-1,dated
5/31/13,complete as Lump
specified Sum 0.00 1.00 1.00 $6,269.16 $6,269.16
6001 Additional equipment,
labor,and materials to
install storm sewer on
Koeller Street per Invoice
13-621-Koeller-2,dated
5/31/13,complete as Lump
specified _ Sum 0.00 1.00 1.00 $7,766.42 $7,766.42
6002 Additional equipment,
labor,and materials to
install storm sewer on
Koeller Street per Invoice
13-621-Koeller-3,dated
5/31/13,complete as Lump
specified _ Sum 0.00 1.00 1.00 _ $2,963.07 $2,963.07
6003 Additional equipment,
labor, and materials to
install storm sewer on
Koeller Street per Invoice
13-621-Koeller-4,dated
5/31/13, complete as Lump
specified Sum 0.00 1.00 1.00 $6,682.93 $6,682.93
6004 Additional equipment,
labor, and materials to
install storm sewer on
Koeller Street per Invoice
13-621-Koeller-5,dated
5/31/13, complete as Lump
specified Sum 0.00 1.00 1.00 $4,413.62 $4,413.62
6005 Additional equipment,
labor, and materials to
install storm sewer on
Koeller Street per Invoice
13-621-Koeller-6,dated
5/31/13,complete as Lump
_specified Sum 0.00 1.00 1.00 $4,988.05 $4,988.05
SECTION VI ADDITIONAL WORK SUB-TOTAL: $33,083.25 $0.00
NET INCREASE TO SECTION VI: $33,083.25
NET INCREASE TO SECTIONS I,II,III,IV,V,&VI: $108,562.96
NET DECREASE TO SECTIONS I,II,III,IV,V,&VI: $1,360.00
NET INCREASE TO CONTRACT: $107,202.96