HomeMy WebLinkAboutPW CNT 12-17/CH OR #1/sTRAND aSSOC CITY OF OSHKOSH
DEPARTMENT OF PUBLIC WORKS
215 CHURCH AVENUE, P.O. BOX 1130, OSHKOSH, WI 54903-1130
PHONE: (920)236-5065 FAX(920) 236-5068
LETTER OF TRANSMITTAL
To: Mr. Jeffrey Rau Date: January 29, 2013
Strand Associates, Inc. Subject: Executed Change Order No. 1
910 West Wingra Drive 2012 Consolidated Treatment Plant
Madison, WI 53715 and Pumping Station Improvement
Projects
Contract 12-17
Please find: ® Attached ❑ Under Separate Cover
El Copy of Letter ❑ Contracts ❑ Amendment ❑ Report El Agenda
❑ Meeting Notes El Photos El Mylars ® Change Order ❑ Plans
El Specifications El Estimates ❑ Diskette ❑ Zip Disk El Other
Quantity Description
2 Executed Change Order No. 1
These are being transmitted as indicated below:
❑ For Approval ® For Your Use El As Requested ❑ For Review& Comment
Remarks:
Enclosed are two copies of the executed Change Order No. 1 for J.F. Ahern Co. for the 2012
Consolidated Treatment Plant and Pumping Station Improvement Projects.
If you have any questions, please contact us.
Steve Brand — Copy
City Attorney's Office— Copy
City Clerk's Office— Original , �,
cc: _ File — Original Signed: >1 :)
Traci. aylor
C\Engineering112-17 WWTP Lift Slat&Plant ImprlProject_Information\Correspondence\LOTs112-17 Strand LOT-JF Ahe CO#1_1-29-13.d•�
Strand Associates, Inc.
6;41
STRAND
ASSOCIATES
December 14, 2012
CHANGE ORDER NO. 1
PROJECT: 2012 Consolidated Treatment Plant and Pumping Station
Improvement Projects
OWNER: City of Oshkosh, Wisconsin
CONTRACT: 12-17
CONTRACTOR: J.F. Ahern Co.
Description of Change
la Removal of SCADA electrical work associated with DEDUCT ($42,566)
the 28th Street and Northside pump stations as
outlined in Section 16940.
lb Agreed contract adjustment for project delay of DEDUCT ($15,000)
WWTP work on slide gates, baffle panels, and stop
logs.
Ic Removal of Milestone(s)No. 2 and No. 3 from DEDUCT ($ 0)
Contract.
ld Adjust Milestone No. 4 to February 15, 2013. DEDUCT ($ 0)
TOTAL VALUE OF THIS CHANGE ORDER: DEDUCT ($57,566)
Contract Price Adjustment
Original Contract Price $817,800
Previous Change Order Adjustments $ 0
Adjustment in Contract Price this Change Order ($ 57,566)
Current Contract Price including this Change Order $760,234
Contract Completion Date Adjustment
Original Contract Completion Date February 15, 2013
Contract Completion Date Adjustments due to previous Change Orders 0 days
Contract Completion Date Adjustments due to this Change Order 60 days
Current Contract Completion Dates including all Change Orders April 15, 2013
JSRclm\S.\MAD\1300--1399\I 382\057\Wrd\Change Orders\CO 41.doex
,A11 Of1z3_ I11IIII k,111 k;' i)11 `.1,1 t (;116111 wvw.strand.corn
Strand Associates, Inc."
City of Oshkosh—J.F. Ahern Co.
Contract 12-17, Change Order No. i
Page 2
December 14, 2012
This document shall become a supplement to the Contract and all provisions will apply hereto.
RECOMMENDED
J12/,4///Z
ENGINEER— trand Associates, Inc.® Date
APPROVED
12 ) 61 12
CONTRACTOR—J.F. Ahern Company Date
RECOMMENDED BY OWNER
OWNER—Director of Public Works, City of Oshkosh Date
APPROVED BY OWNER
-2-y1_ 2,313
OWNE —Mark A. Rohloff; City Manager, City of Oshkosh Date
CO , j0)(1-
OWNER- Pamela R. Librig, it)"Clerk, Cit o Oshkosh Date
I certify that provision has been made to pay the liability that will
accrue to the City of Oshkosh. Wisconsin, under this Change
Order.
//2,7//3
OWNER—Peggy Steeno, Director of Finance, City of Oshkosh Date
APP'OVED AS TO FO '
A
IA AA 41."- /� L• Et —Lynn Lorenson, ity Attorney, City of Oshkosh Date
JSR:clm1S.A MAD\I300--I 399'1382,057\Wrd\Change Orders\CO#1.doex
www.strand.com