HomeMy WebLinkAboutLunda/CH OR 2 River Walk CHANGE ORDER NO. 2
TO: LUNDA CONSTRUCTION Date: January 2, 2013
2000 Taylor St
Little Chute,WI 54140
Your present contract with the City of Oshkosh for construction of Riverwalk improvements/dock
installations for the City Center Riverwalk project is hereby amended and changed as follows:
INCREASE:
Bid Items Amount
H-3 Load/Transport Sediment/Impacted Soil $38,548.00
CO-2 Elimination of Electrical Boxes <$ 1,474.00>
CO-3 Light Electrical Components/Cabinet $30,711.75
CO-4 Add Security Fence Beckets to Plaza $ 385.00
CO-5 Eliminate redundant light grounding <$ 563.00>
CO-6 Change PVC Electrical Conduit to Aluminum $21,621.63
CO-7 Add Expansion Couplings to Conduit $ 3,753.75
CO-8R1 Redesign of Station 21+00 to 23+00(Hotel) $64,640.00
CO-9 Redesign of Station 13+50 to 14+50(City Center Plaza) $ 9,500.00
CO-10 Redesign of Station 14+50 to'15+57(East of Plaza) $ 8,000.00
CO-11 Redesign of Station 15+60 to 20+95(Parking Lot) $82,770.00
CO-12 Redesign of Station 10+00 to 15+60(Beckets) $47,250.00
NET INCREASE-CHANGE ORDER#2 $305,143.13
Original Base Bid Amount $2,874,590.70
Alternate Bid Amount(hotel section) $1,024,040.00
$3,898,630.70
INCREASE C.O.#1 $ 254,858.00
INCREASE C.O.#2 $ 305,143.13
Revised Contract Amount $4,458,631.83
RECD ED: CITY OF OSHKOSH
fv, ', BY: �"T6-i� Xef'-X7—
Community Development Director City M ::o
1 t
a1lit .fit! I_ _
City Clerk
I certify that provision has been made to
pay the liability that will accrue to the City
of Oshkosh,Wisconsin, under the within APPROVED AND ACCEPTED:
C Order.
— �4'� tii �r�
�lr
Finance Director Lunda Construction Inc.
Ap.rr ed as to form: n
►.. , :!i
• ,�__ It
enson, Ci ` rney - i`1 Oude ige,JE /_ D'iis'v,J
Maw
CITY OF
• DMIP) REQUEST FOR QUOTATION
ON W R
•
CHANGE ORDER NO.:
TO CONTRACTOR: Lunde Construction Inc.
PROJECT: City Center Riverwaik PROJECT NO: 80250485
OWNER: City Of Oshkosh Redevelopment Authority
ENGINEER: AECOM
The following modifications)to the Contract arc hereb■ ordered (use additional pages if required):
12/18/2012
Delete(2)Each SS Junction Boxes on the West Side of the Main Street Bridge:
Credit ($1,474.00)
Athichm,cnts (! ist Supporting Documents):
Contract Amount or Price I Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) (Add/Deduct) s Da
$ Y
This Chant e Order / This Change Order
/
'edu `' > (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
20
Owner Contractor Engineer Recommendation
By:
° By:
Date: Date: /2/0200/2 Date:
` i 1
OF
Y;.FITS; : T.1; REQUEST FOR QUOTATION
CHANGE ORDER NO.: 2A(voids RFQ 2)()
TO CONTRACTOR: Lundy Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: Cr Of Oshkosh Redevelopment Authority
ENGINEER: AECOM
As directed In RFI 1,Electrical Component and Cabinet Additions. Change plane and specifications to strike OWNER
PROVIDED and change to CONTRACTOR PROVIDE. Please note all labor for assembly has already been included in the
base bid. Please proved cost break down per item.
Add equipment include all supplies and labor for items listed below.
City will not be providing equipment. State would like complete separate communication
eyeball
Att,, mit tf t sui)t,ortinci Dccume nt.t. RFI1 and items below with all costs for equipment and labor required
Communication Vaults add 8,Item C,detail 10-211,on Sheet E 2.1
Commundatln Pull Box at Bridges add 4,item.l,on Sheet E1.0
Contract Amount or Price Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(a) Previous Change Order(s)
(Add/Deduct) (Add/Deduct)
Days
Change Order 7f This Change Order
) $ 7/(- (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
,20
Owner Contractor Engineer Recommendation
Date: Date: J/i2/X/20/Z Date: :_ j/(i ,
g g REV 00107 FORM 273
LUNDA CONSTRUCTION COMPANY
SINCE 1938 1' 2000 TAYLOR STREET•P.O.BOX 228
� LITTLE CHUTE,WI 54140
Iii PH: (920)788-5238 FAX: (920) 788-0229
re1:r�c�r cry INDUSTRIAL DIVISION
LITTLE CHUTE,w► An Equal Employment Opportunity Employer • Constructing Safely
May 4, 2012
AECOM
558 North Main Street
Oshkosh, WI 54901
Attn: Paul Timm
Re: City of Oshkosh
City Center Riverwalk Project
Oshkosh,Wisconsin
Electrical Service Change Order Request
Mr. Timm,
Please see the Change Order Request below for the changes to the electric service for the
above mentioned project. After talking with the City of Oshkosh Electrical Inspector, he will let
us install the 30kVa transformer in a 24in deep cabinet but he said the cabinet has to be
Nema4X because it is outdoors. The cabinet is much larger than prior so there was additional
labor added to account for that. There will be approximately 18-20 inches of width left for any
future equipment. The panelboard will only have enough breakers for this project. We can
install spare breakers if the city provides them to us prior to installing the panel. Also the
contractors were not originally in the scope of work as the specifications stated to have
termination blocks on din rail.
Also, after speaking with AECOM, the correct quantity of added Communication Vaults is five.
Changes are as follows:
> Larger Concrete Pad (36"x72"x31") $ 390.60
Cabinet(24"x60"x72") $ 9,645.30
> Exhaust Fan with Thermostat $ 937.65
> Contractors $ 961.80
• Panelboard $ 845.25
• Communication Vaults (5) $11,270.70
➢ Communication Pull Boxes $ 7,863.45
➢ Deduct Channel Supports, Strut, Footings, Term Blocks ($ 1,203.00)
Total Change Order Request: $30,711.75
(Thirty Thousand Seven Hundred Eleven Dollars and Seventy-Five Cents)
2000 Taylor St. •P.Q. Box 228 •Little Chute, WI 54140-0228 •Phone: 920-788-5238•FAX: 920-788-0229
401 Alderson St. • P.O. Box 288 •Schofield, WI 54476-0288•Phone: 715-355-4848 •FAX: 715-355-7710
,
+ Alternate to trace out existing site lighting circuits: Add $2,184.00
If you should have any further questions or concerns regarding this change order request,
please feel free to contact me.
Respectfully Submitted,
Lunda Construction Company
Ind ial Division
1 4 eve. ,_s_________
-aul J. Gev-rs
Project Manager
PJG/clg
0.4)DY:;;len■ REQUEST FOR QUOTATION
CHANGE ORDER NO.: 4
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh Redevelopment Authority
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered (use additional pages if required):
Add fencing to all access from Beckets through the plaza until plaza construction starts.
Reason for Modification(s): Part of the Access Agreement with City Center,LLC.
Contract Amount or Price I Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $t? (Add/Deduct) Days
This Change Order This Change Order
(Add/ ) $385, 00 (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
,20
Owner Contractor Engineer mmendation
By: By: / • / By:
Date: Date: (/-2/7/ Date: 4-- 7/
8-3 REV 06/07 FORM 273
CITY OF
OJHKOJH REQUEST FOR QUOTATION
ON THE WATER j
CHANGE ORDER NO.: J�
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered (use additional pages if required):
Eliminate redundant grounding as requested by City of Oshkosh Electrical Department.
Base Bid Item F-1 $
Alternate(Hotel Area)Item F-1 $
Reason for Modification(s): Changes in Electrical Grounding Requirements
Attachments(List Supporting Documents):
Contract Amount or Price Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct) Days
This Change Order This Change Order
. Deduct) $<5C - (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
, 20
Owner Contractor Engineer Recommendation
By: 4 ° if By:
Date: Pate: /26//20/Z Date:
B-3 REV 06/07 FORM 273
rr • _
�{� = REQUEST FOR QUOTATION /�,
l!/
CHANGE ORDER NO.: /D
TO CONTRACTOR: Lunde Construction Inc.
P1tOJECT—CIVTO Riveiwalk PROJECT-NO:-60250465
OWNER: City Of Oshkosh Redevelopment Authority
ENGINEER: AECOM
Change 1-Inch PVC Conduit for Bollards to Rigid Aluminum 1-Inch for the Entire Project.
Base Bid
Deduct for Elimination of 1-Inch PVC, 1080 IF: ($1,650.54)
Adding 1-Inch Ridged Aluminum, 1080 LF: $18,551.16
Alternate Hotel
Deduct for Elimination of 1-Inch PVC,280 LF: ($395.20)
Add 1-Inch Ridged Aluminum,280 IF: $5,116.21
h: son f c ion( Change in materiel to account for location of conduit for wiring associated with the Bollards
long the riverwalk as compared to the high water level of the Fox River. Aluminum will
stand freezing,UV and floating debris better than PVC.
.1
Contract Amount or Price [ Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct)
Days
This Change Order , This Change Order
(Add/9sduet) $ ?/ 42L (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
,20
Owner Contractor neer - .•mmendatlgn
By:B y o By: v� .
Date: Date: 42//20/j Date: q_
•
CITY OF
�;' Of HKOf H REQUEST FOR QUOTATION
°;:',�.� ON THE WATER /1
CHANGE ORDER NO.:
• TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered (use additional pages if required):
Revision of Electrical Conduit Expansion Coupling
Reason for Modification(s): Code requires expansion coupling on conduit that is not buried.
Attachments (List Supporting Documents): See attached June 26,2012 Lunda Memo.
Contract Amount or Price I Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct)
Days
Y
This Change Order 3 This Change Order
(AddEDee et) $ 3 753 ? (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
,20
Owner Contractor Engineer Recommendation
By: `13y: 11.„..,e�
Date: Date: /.7/2//k`y Date:
B-3 REV 06/07 FORM 273
LUNDA CONSTRUCTION COMPANY
'� 2000 TAYLOR STREET•P.O. BOX 228
b` SINCE 1938 ' LITTLE CHUTE,WI 54140
I
PH: (920)788-5238 FAX: (920)788-0229
INDUSTRIAL DIVISION
N-TT-I-----�l
LITTLE CHUTE.VII An Equal Employment Opportunity Employer • Constructing Safely
June 26, 2012
AECOM :f
558 North Main Street ,
Oshkosh, WI 54901
I - }
Attn: Paul Timm
Re: City of Oshkosh
City Center Riverwalk Project
Oshkosh, Wisconsin s z
Change Order Request—PVC Expansion Couplings
Mr. Timm,
Please see the Change Order Request below for adding PVC expansion couplings as PVC will
be routed exposed under the slab. Code requires that we install expansion couplings to allow
for the expansion and contraction of the PVC pipe with the warming and cooling temperatures.
{ 55 ea 3"and 35 ea 1" PVC Expansion Couplings:
Total Change Order Request: $3,753.75
(Three Thousand Seven Hundred Fifty-Three Dollars and Seventy-Five Cents)
If you should have any further questions or concerns regarding this change order request,
please feel free to contact me.
Respectfully Submitted,
Lunda Construction Company
trial Division
ap,/,AS -14 e
Paul J. Ge rs
Project Manager
PJG/c!g C%
2000 Taylor St. •P.O. Box 228 •Little Chute,WI 54140-0228 •Phone: 920-788-5238 •FAX: 920-788-0229
401 Alderson St. • P.O.Box 288 •Schofield, WI 54476-0288 •Phone: 715-355-4848 •FAX: 715-355-7710
CITY OF
1:" REQUEST FOR QUOTATION
CHANGE ORDER NO.: 8R-1
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered(use additional pages if required):
This RFQ supersedes and eliminates RFQ 8.
Elimination of reconstruction of planter bed retaining walls from west half of Hotel Area station 21+10
to 22+05 Detail K, S3.5. Extension of 8-inch reinforced concrete walkway to building, Detail K, S3.5.
Redesign of east most planter wall as noted on the attached drawing. Item D-1, Alternate Bid Hotel
Area Revision of Hotel Portion concrete cap and of concrete slab reinforcement per the attached
sketches. Changes in ramp wall and addition of form liner.
Addition for changes as noted including labor and supplies $ 64,640
Reason for Requested change of elimination of planters by Hotel owners and Hotel Sea
Nloditication(s): all construction was not constructed as anticipated or designed as
•etermined by exploratory openings in the existing Riverwalk structure.
Structural fill previously placed to support the concrete decking has settled.
I'evision of the concrete deck and seawall cap beam rebar is required to
aintain design criteria. This work is considered part of the rock anchor
ystem
B-3 REV 06/07 FORM 273
•
Attachments (List Supporting The following is AECOM's clarification on the placement of
Documents): reinforcing bars in the 8-inch slab between Sta. 21+00 to
23+10 The#4 bars in the top and bottom mat shall be
staggered so they are not directly over each other. The
bottom#7 and top#5 bars shall be placed directly over each
other. Reinforcing placement Shop Drawings shall be noted
with clarification number for layout of these bars, as
necessary.
They are to be installed in this manner to provide at a
minimum of 1-inch clear between#4 bar and#5 or#7 bar for
3/4-inch aggregate (#67 Stone ASTM C-33)per the
approved concrete mix design. This is an ACI 318 code
requirement and has a minimum clear between bar of 3/4-
Resided Drawings to replace appropriate Construction drawing set drawings.
Please note that the change from 12'-3"to 11"-9 1/2"for the width of the boardwalk, the Pier Layout C
will also need to shift in 5.5"on Sheet S5.1 and S5.2.
Attachments Revised Sheets S2.7A, S3.5, S4.5AS4.6
Contract Amount or Price I Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct) Days
This Change Order / `/�', ^ This Change Order
m
(Add/ et) $ c...7 c v_ (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
,20
Owner Contractor Q G " Engineer Recommendation
By: a /� �- �'By:
Date: Date: /?/.2/JZ /2■ Date:
B-3 REV 06/07 FORM 273
CRY QF
Y" REQUEST FOR QUOTATION
CHANGE ORDER NO.: 9
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered(use additional pages if required):
Station 13+50 to 14+50
Reconstruction of City Center Plaza per attached plan sheet C 5.0,C 5.0(A), S2.3A, S2.4A. S2.4B,S2.5. Provide and Install
approximately 105 CYD of topsoil for landscape area in planters
RFQ 9 $9,500
Reason for Modification(s): City Center Requested Change
Attachments(List Supporting Documents): Drawings C 5.0, C 5.0(A), S2.3A, S2.4A.S2.4B, S2.5.
Contract Amount or Price Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct)
Days
This Change Order This Change Order
(Add/IOW ) $ '5remr (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
Owner Contractor Engineer Recommendation
By: y: /C y1"G..'-" By:
Date: Date: 42/100/?i Date:
B-3 REV 06/07 FORM 273
CflY 0
L �
r REQUEST FOR QUOTATION
CHANGE ORDER NO.: 10
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered(use additional pages if required):
Station 14+50 to 15+57
Provide materials and labor per revised drawings S2.4, S2.4B S2.5
RFQ 10 $8,000
Reason for Modification(s): Exsisting Condtions were different than orginal design drawings. There were missing piles
per the design plans and exsisting piles were out of alignment.
Attachments(List Supporting Documents): Drawings S2.4, S2.4B S2.5
Contract Amount or Price Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct)
Days
This Change Order /- This Change Order
(Add/Bill. $ (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
Owner Contractor Engineer Recommendation
By: C 4or_ -2 By:
Date: Date: i,'L ,2//20,2---- Date:
B-3 REV 06/07 FORM 273
rrr OF
REQUEST FOR QUOTATION
CHANGE ORDER NO.: 11
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered(use additional pages if required):
Station 15+60 to 20+95
Addition of approximately 140 LF of 6X6X1/2 inch Galvanized Steel Channel $36,500
60"Storm Sewer Manhole Reconfiguration and Tie Back Grade Beam Repairs $14,000
Various Size Private Storm Sewer Outfall Repairs $2,270
Demolition and Replacement of Additional 4 inches of concrete $29,000
RFQ 11 Total $82,770
Plan set detail revision to include 6X6X1/2 inch steel channel to meet design standards for
ntilevered Riverwalk section.
Existing Conditions were different than original design drawings for the storm sewers and
ncrete.
Attachments(List Supporting Documents): Drawings S2.4, S2.4B S2.5
Contract Amount or Price Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct)
Days
This Change Order This Change Order
(Add/ ). $ `3'p2 72�—�- (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
Owner Contractor Engineer Recommendation
�
By: B Mt,t +/�
IC By:
Date: Date: /276,/S24l�---- Date:
B-3 REV 06/07 FORM 273
CRY t?F
1110410 REQUEST FOR QUOTATION
CHANGE ORDER NO.: 12
TO CONTRACTOR: Lunda Construction Inc.
PROJECT: City Center Riverwalk PROJECT NO: 60250465
OWNER: City Of Oshkosh
ENGINEER: AECOM
The following modification(s)to the Contract are hereby ordered (use additional pages if required):
Station 10+00 to 15+60(Beckets)
Adjustment of Wood Laging and Precast Panels including Panel Repair $17,950
Demoltion and Replacement of discovered loading dock slab $29,300
RFQ 12 Total $47,250
Exsisting conditions on sea wall varied from design plans and were not visible prior to
onstruction
A concrete slab was discovered and identified as part of a historical loading dock. The
oncrete slab is part of the seawall tie back system and required replacement with the cap
beam
Attachments(List Supporting Documents): Drawings S2.0A,S2.3A,S2.5, FSK 1A
Contract Amount or Price Contract Times(Calculate Days)
Original $ Original Duration Days
Previous Change Order(s) Previous Change Order(s)
(Add/Deduct) $ (Add/Deduct)
Days
Y
This Change Order This Change Order
(Addict) $ 7a, (Add/Deduct) Days
Revised Contract Amount $ Revised Contract Time Days
The Revised Contract Completion Date is:
Owner Contractor Engineer Recommendation
By: , 6 1 By:
Date: Date: 01 a2/ 1012 Date:
B-3 REV 06/07 FORM 273