NOVEMBER 27, 2012 12-571 RESOLUTION
(CARRIED___7-0____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT 12-03 WITH ADVANCE CONSTRUCTION, INC. FOR
SAWYER CREEK CHANNEL IMPROVEMENTS FROM KOELLER
STREET TO FOX RIVER (+$161,250.52)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
ADVANCE CONSTRUCTION, INC.
2141 Woodale Avenue
Green Bay, WI 54313
Net Increase to contract: $161,250.52
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 551-1910-1799-00000 Sewer Utility Work in Progress
561-2010-1799-00000 Storm Water Utility Construction Work in
Progress
•
OIHKOJH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works S"4:_ty
DATE: November 22, 2012
RE: Change Order No. 1 for Public Works Contract No. 12-03
Sawyer Creek Channel Improvements from Koeller Street to Fox River
Advance Construction, Inc. (+$161,250.52)
BACKGROUND
Change Order No. 1 for Contract 12-03 is scheduled for consideration by the Common Council at the November
27, 2012 meeting. The contract was originally awarded to Advance Construction, Inc. in May of 2012. This
change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to the project:
• Revise completion date to September 1, 2013, due to discovery of contaminated sediment between
Sawyer Street and the Fox River.
• Revisions to the Hawk Street fishing hole to reduce the scope and the change from mechanical to
hydraulic dredging.
• Add increased dredging on Evergreen Retirement Community side of creek at bend by Eagle Street.
• Adjust quantities of the work completed to date to match actual quantities.
FISCAL IMPACT
Contract Section Change Order Amount New Contract Total Utility Funds Available
Storm Sewer $161,250.52 $2,675,217.52 $2,820,000.00
Sanitary Sewer $0.00 $82,200.00 $92,064.00
Total $161,250.52 $2,757,417.52 $2,912,064.00
RECOMMENDATIONS
I recommend approval of Change Order No. 1 to Contact No. 12-03 in the amount of+$161,250.52 to Advance
Construction Inc.
Approved:1 ark A. Rohloff
City Manager
SMG/tIt
1:1Engineering112-03 Sawyer Creek Channel Improvements\Project_Information1 Correspondence\Memo 112-03 Memo for CO#1_11-22-12.docx
TO: Advance Construction CHANGE ORDER# 1
2141 Woodale Avenue DATED: November 15, 2012
Green Bay, WI 54313
Your present contract with the City of Oshkosh, Contract No.12-03, awarded May 22, 2012, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING 60,452.50
NET INCREASE TO: SECTION II - STORM SEWER 100,798.02
SECTION III - SANITARY SEWER 0.00
NET INCREASE TO CONTRACT $161,25032
Section I Section II Section III
(Paving) (Storm) (Sanitary) Totals
Bid Total $1,754,605.00 $759,362.00 $82,200.00 $2,596,167.00
C.O. #1 $60,452.50 $100,798.02 $0.00 $161,250.52
Contract Total $1,815,057.50 $860,160.02 $82,200.00 $2,757,417.52
The final completion date of the project, including landscaping, has been changed from November 21, 2012
to September 1, 2013.
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approved d�/ ' ted:
•
A
C ntractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT:12-03 CHANGE ORDER#1
SECTION I-PAVING
i INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
1005 Excavation,Fishing Hole Lump
@ Hawk Street Sum 1.00 0.00 -1.00 $132,000.00 ($132,000.00)
1006 Excavation and Lump
Placement,Clay Liner Sum 1.00 0.00 -1.00 $11,650.00 ($11,650.00)
1007 Excavation, Special Dollars 20,000.00 40,000.00 20,000.00 $1.00 $20,000.00
1009 Linear
Cofferdam Feet 600.00 0.00 -600.00 $360.00 ($216,000.00)
1020 Remove 30-IN Curb and Linear
Gutter Feet 100.00 177.00 77.00 $5.00 $385.00
1021 Linear
30-IN Curb and Gutter Feet 100.00 177.00 77.00 $33.00 $2,541.00
1025 Salvage and Reinstall Linear
Guardrail Feet 40.00 65.00 25.00 $30.00 $750.00
SECTION t-(BID ITEMS 1005-1025)-SUB-TOTALS $23,676.00 ($359,650.00)
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
10001 Linear
Cofferdam Feet 0.00 390.00 390.00 $400.00 $156,000.00
10002 Hydraulic excavation of Lump
Hawk Street Fishing Hole Sum 0.00 1.00 1.00 $65,118.00 $65,118.00
Hydraulic excavation of
10003 "island"between stations Lump
38 and 44 Sum 0.00 1.00 1.00 $167,445.00 $167,445.00
10004 Lump
Tree removal at"island" Sum 0.00 1.00 1.00 $2,500.00 $2,500.00
10005 Lump
Abutment removal Sum 0.00 1.00 1.00 $2,000.00 $2,000.00
10006 Tree removal at 917 Lump .
Brookwood Court Sum 0.00 1.00 1.00 $3,363.50 $3,363.50
ADDITIONAL WORK: C.O.#1-(ITEMS 10001-100006)-SUB-TOTAL $396,426.50 $0.00
NET INCREASE TO: SECTION I $60,452.50
SECTION II-STORM SEWER
ITEM BID INSTAL t PD NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITES INCREASE DECREASE PRICE
PRICE PRICE
2004 Clear Trees,complete as Inch
specified Diameter 2,490.00 2,872.00 382.00 $15.00 $5,730.00
2010 Grub Stumps,complete as Inch
specified Diameter 2,000.00 2,208.00 208.00 $10.00 $2,080.00
Furnish and install 15"
2044 RCP Class III Storm Linear
Sewer,complete as Feet
specified 73.00 111.00 38.00 $67.00 $2,546.00
Page 1 of 3
CONTRACT: 12-03 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
Furnish and install 54"
2098 RCP Class Ill Storm Linear
Sewer,complete as Feet
specified 74.00 166.00 92.00 $167.00 $15,364.00
Furnish and install 24"x
2128 38"HERCP Class Ill Linear
Storm Sewer,complete as Feet
specified 21.00 25.00 4.00 $140.00 $560.00
Furnish and install
2532 Standard Storm Manhole Vertical
(4'diameter),complete as Feet
specified 6.00 7.80 1.80 $300.00 $540.00
Connect to Existing Storm
2800 Sewer,complete as Each
specified 10.00 17.00 7.00 $6,500.00 $45.500.00
Furnish,install,maintain
2856 and remove Type D Inlet Each
Protection,complete as
specified 30.00 33.00 3.00 $95.00 $285.00
Furnish, install,maintain
2876 and remove Turbidity Each
Barrier,complete as
specified 8.00 10.00 2.00 $750.00 $1,500.00
Furnish and install Heavy Square
2948 Rip-Rap w/Filter Fabric, Yards
complete as specified 150.00 186.96 36.96 $62.00 $2,291.52
Furnish and install
2971 Vegetated Boulder Linear
Revetment,complete as Feet
specified 750.00 803.00 53.00 $31.00 $1,643,00
SECTION II-(BID ITEMS 2004-2971)-SUB-TOTALS $78,039.52 $0.00
ADDITIONAL WORK REQUIRED: C.O.#1- SECTION II
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
20001 Additional turbidity Lump
monitoring Sum 0.00 1.00 1.00 $2,625.00 $2,625.00
20002 Tree grubbing and disposal Lump
at island" Sum 0.00 1.00 1.00 $5,212.50 $5,212.50
20003 Remove Miscellaneous Lump
Pilings Sum 0.00 1.00 1.00 $2,625.00 $2,625.00
20004 Remove and reinstall 54" Lump
endwall Sum 0.00 1.00 1.00 $1,700.00 $1,700.00
20005 Restoration at 903 Lump
Brookwood Court Sum 0.00 1.00 1.00 $6,500.00 $6,500.00
Page 2 of 3