NOVEMBER 27, 2012 12-572 RESOLUTION
(CARRIED___7-0____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT 12-13 WITH CARL BOWERS & SONS
CONSTRUCTION CO., INC. FOR ASPHALT PAVING & UTILITIES
(+$99,740.80)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
CARL BOWERS & SONS CONSTRUCTION CO.
N1844 Maloney Rd.
Kaukauna, WI 54130
Net Increase to contract: $99,740.80
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 311-0410-7480-00000 Sidewalk Construction Fund
315-0410-7480-00000 Street Improvement Fund Expenditures
317-0410-7480-03301 Special Assessments Fund – Streets
317-0410-7480-03302 Special Assessments Fund – Sewer
317-0410-7480-03303 Special Assessments Fund – Water
317-0410-7480-03304 Special Assessments Fund – Sidewalks
317-0410-7480-03305 Special Assessments Fund – Storm Water
541-1810-1799-00000 Water Utility Construction Work in Progress
551-1910-1799-00000 Sewer Utility Construction Work in Progress
561-2010-1799-00000 Storm Water Utility Construction Work in
Progress
323-1728-7216-06141 Property Improvement Fund – North End
Railroad Crossing Improvement
OIHKOH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works S�
DATE: November 22, 2012
RE: Change Order No. 1 for Public Works Contract No. 12-13
Asphalt Paving & Utilities—Ceape Avenue, Poplar Avenue &Various Alleys
Carl Bowers Construction Co., Inc. (+$99,740.80)
BACKGROUND
Change Order No. 1 for Contract 12-13 is scheduled for consideration by the Common Council at the November
27, 2012 meeting. The contract was originally awarded to Carl Bowers Construction Co., Inc. in August of 2012.
This change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Storm Sewer — Additional materials needed to match existing pipe sizes and additional work to repair
several manholes in poor condition.
• Sanitary Sewer— During construction, it was discovered the sanitary laterals under Ceape Avenue were
in very poor condition. The laterals were relayed.
• Water Main—Additional work to abandon unknown pipe in conflict with proposed water main.
FISCAL IMPACT
Contract Section Change Order Amount New Contract Total CIP Budget Amount
Street/Sidewalk $0.00 $349,810.40 $400,000.00
Storm Sewer $10,365.00 $60,820.00 N/A
Sanitary Sewer $80,161.80 $87,961.80 N/A
Water Main $2,110.00 $261,320.04 N/A
Traffic $7,154.00 $135,454.00 $100,557.00
Total $99,790.80 $895,366.24 $500,557.00
Funding for the resurfacing portions of the contract is available in the 2012 Capital Improvement Program (CIP)
and from reserve funds. Additional funding is available in the 2012 CIP for the sanitary and water portions of the
contract from other projects being completed under budget. The Storm Water Utility has adequate reserves to
fund their portion of the contract. Funding for the Railroad Quiet Zone Improvements is available in the traffic
sections of the 2011 and 2012 CIP. Additional unspent funds are available in the traffic section to cover the
remainder of the cost. Assessments will be levied to adjoining property owners per the assessment policy.
RECOMMENDATIONS
I recommend approval of Change Order No. 1 to Contact No. 12-13 in the amount of +$99,740.80 to Carl
Bowers Construction Co., Inc.
Approved:
Mark A. Rohloff
City Manager
SMG/tlt
I:1Engineering112-13 2012 Hot Mix Asph Paving&Util\Project_Information\Correspondence\Memo112-13 Memo for CO#1_11-22-12.docx
TO: Carl Bowers & Sons Constr. Co., Inc. CHANGE ORDER# 1
N1844 Maloney Rd, DATED: November 13, 2012
Kaukauna, WI 54130
Your present contract with the City of Oshkosh, Contract 12-13, awarded August 14, 2012, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING $0.00
NET INCREASE TO: SECTION II - STORM SEWER $17,469.00
NET INCREASE TO: SECTION III - SANITARY SEWER $80,161.80
NET INCREASE TO: SECTION IV-WATER MAIN $2,110.00
NET INCREASE TO CONTRACT $99,740.80
Section! Section II Section III Section IV
(Paving) (Storm) (Sanitary) (Water) Totals
Bid Total $478,110.40 $50,455.00 $7,800.00 $259,210.04 $795,575.44
C.O.#1 $0.00 $17,469.00 $80,161.80 $2,110.00 $99,740.80
Contract Total $478,110.40 $67,924.00 $87,961.80 $261,320.04 $895,316.24
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approved and accepted:
CContractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 12-13 CHANGE ORDER#1
SECTION II-STORM SEWER
ADDITIONAL WORK REQUIRED: C.O.#1 - SECTION II
ITEM BID INSTALLED NET INCREASE IN DECREASE
NUMBER DESCRIPTION UNIT NET UNIT IN
QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE
PRICE
20000 Furnish and install 15"
CMP,complete as Linear
specified Feet 0.00 50.00 50.00 $47.00 $2,350.00
20001 Furnish and install 15"
CMP Endwalls,complete
as specified Each 0.00 2.00 2.00 $350.00 $700.00
20002 Furnish and install 24"
CMP,complete as Linear
specified Feet 0.00 56.00 56.00 $59.00
20003 Furnish and install 24" $3,304.00
CMP Endwalls,complete Linear
as specified Feet 0.00 2.00 2.00 $400.00 $800,00
20004 Abandon 36"strom sewer, Linear
complete as specified Feet 0.00 50.00 50.00 $18.00 $900.00
20005 Additional time for crew to
break out the concrete
encased pipe from
manhole In the Broad
Street&Poplar Ave nu
intersection, so they could
reconnect to manhole, for
work performed on
1012112,complete as
specified Hours 0.00 1.00 1.00 $1,055.00 $1,055.00
20006 Additional equipment,
labor,and materials to
replace cone with a flat
top an 8"adjustment ring, Lump
complete as specified Sum 0.00 1.00 1.00
20007 Additional equipment, $2,905.00 $2,905.00
labor,and materials to
rebuild 2 shallow storm
manholes that were in poor
condtion and discovered
during grading operations,
complete as specified Lump
Sum 0.00 _ 1.00 _ 1.00 _ $3,575.00 $3,575.00
Page 1 of 3
CONTRACT: 12-13 CHANGE ORDER#1
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT
PRICE PRICE
20008 Additional equipment,
labor, and materials to
rebuild 1 shallow storm
manhole that was in poor
condition and discovered
during grading operations, Lump
complete as specified Sum 0.00 1.00 1.00 $1,880.00 $1,880.00
ADDITIONAL WORK:C.O.#1 -(ITEMS 20000-20008)-SUB-TOTAL $17,469.00 $0.00
NET INCREASE TO: SECTION II $17,469.00
SECTION III-SANITARY SEWER
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION III
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
3234 Furnish and install 4"/S"
sanitary lateral
relay,complete as specified Linear
Feet 0.00 783.20 783.20 $67.75 $53,061.80
3236 Furnish and install sanitary
lateral marker balls,
complete as specified
Each 0.00 56.00 56.00 $20.00 $1,120.00
3238 Furnish and install clay
dams, complete as
specified Each 0.00 22.00 22.00 $65.00 $1,430.00
30000 Extra crew time to break
out concrete encased
sanitary laterals,complete Crew
as specified Hours 0.00 7.00 7.00 $1,055.00 $7,385.00
30001 Extra crew time to
excavate and cut and cap
sanitary lateral for 400
Cepae Avenue. Complete Crew
as specified Hours 0.00 1.00 1.00 $1,055.00 $1,055.00
30002 Extra crew time to
excavate sanitary lateral
for 505 Ceape Avenue and
verify it was not active, Crew
complete as specified Hours 0.00 2.00 2.00 $1,055.00 $2,110.00
Page 2 of 3
CONTRACT: 12-13 CHANGE ORDER#1
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
30003 Furnish and install
Bentonite slurry dams,
complete as specified ! Each 0.00 7.00 7.00 $2,000.00 $14,000.00
ADDITIONAL WORK: C.O.#1-(ITEMS 3234-30003)-SUB-TOTAL $80,161.80 $0.00
NET INCREASE TO: SECTION III $80,161.80
SECTION IV-WATER MAIN
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION IV
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
40000 Additional crew time to
determine and remove an •
abandoned unknown steel
casing pipe that was in
conflict with the proposed
water main, complete as
specified Hours 0.00 2.00 2.00 $1,055.00 $2,110.00
ADDITIONAL WORK: C.O.#1 (ITEM 40000)-SUB-TOTAL $2,110.00 $0.00
NET INCREASE TO: SECTION IV $2,110.00
NET INCREASE TO SECTIONS I,II,III,IV $99,740.80
NET DECREASE TO SECTIONS I,II,III,IV $0.00
NET INCREASE TO CONTRACT: $99,740.80
•
Page 3 of 3