HomeMy WebLinkAboutPW CNT 12-04/CNG OR 2 DEPARTMENT OF PUBLIC WORKS
215 Church Avenue
P.O.Box 1130
Oshkosh,Wisconsin 54903-1130
Ph.(920)236-5065 OlHKOlH
Fax(920)236-5068
ON THE WATER
September 13, 2012 0 EC
Mr. Mark Schleis SEP Y 212
PTS Contractors, Inc. C�Ty
4075 Eaton Road I c
Green Bay, WI 54311 ``�i{'o
OFFpc.
Re: Change Order No. 2
Contract 12-04
Dear Mr. Schleis:
Enclosed is an executed copy of Change Order No. 2 between the City of Oshkosh and PTS Contractors,
Inc. regarding the abovementioned project.
If you have any questions,please call our office at (920)236-5065.
Sincerely,
Dada j 01
qg-
David C. Patek
Director of Public Works
DCP/tlt
Enclosure: Change Order No. 2
cc: Pam Ubrig, City Clerk(w/original)
Lynn Lorenson, City Attorney (w/copy)
Peggy Steeno, Finance Director(w/copy)
File (w/original)
I:\Engineering\12-04 Conc Paving&Utili-SouthProject_Information\Contract Info\Change Orders\12-04 Executed CO Page 1 of 1
#2 Ltr 9-13-12.docx
TO: PTS CONTRACTORS, INC. CHANGE ORDER#2
4075 EATON ROAD DATED: August 21, 2012
GREEN BAY, WI 54311
Your present contract with the City of Oshkosh, Contract No.12-04, awarded February 28, 2012, is hereby
amended and changed as follows:
SECTION I - PAVING 0.00
NET DECREASE TO: SECTION II - STORM SEWER (3,910.00)
NET INCREASE TO: SECTION III - SANITARY SEWER $12,213.20
NET INCREASE TO: SECTION IV-WATER MAIN $8,051.03
NET INCREASE TO CONTRACT $16,354.23
Section I Section II Section III Section IV Totals
(Paving) (Storm) (Sanitary) (Water)
Bid Total $1,409,854.51 $1,750,238.75 $1,018,733.25 $1,208,354.00 $5,387,180.51
C.O. #1 $0.00 $0.00 $1,960.00 $33,061.56 $35,021.56
Prev.Contract Total $1,409,854.51 $1,750,238.75 $1,020,693.25 $1,241,415.56 $5,422,202.07
C.O. #2 $0.00 ($3,910.00) $12,213.20 $8,051.03 $16,354.23
Contract Total $1,409,854.51 $1,746,328.75 $1,032,906.45 $1,249,466.59 $5,438,556.30
CITY OF OSHKOSH
BY:
./ ei------ A! „ C..?"r"---1AX--
Recommended: c.,`
City Manage"
06_,_ci L, 01-44 iMP./ 1:.-AM' sLio,.- •
Director of Public Works City Clerk
Approved and accepted:
-1Z_C --C2-1-ZiaiL--
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
�t�ptroller
Approved as y; form:
Li iiL.Aa■a ��M 4 N-"
Cit MIA"" ey
CONTRACT: 12-04 CHANGE ORDER#2
SECTION II-STORM SEWER
INCREASE IN 'DECREASE IN I
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT I CON TRACT CON TRACT
NUMBER I I QUANTITY QUANTITIES INCREASE DECREASE PRICE
I I
2032 Furnish&install 8-inch
storm sewer,complete as Linear
_specified Foot 0.00 54.50 54.50 $60.00 $3,270.00
SECTION II-(BID ITEM 2032)-SUB-TOTAL $3,270.00 $0.00
ADDITIONAL WORK REQUIRED: C.O.#2 - SECTION II
INCREASE IN DECREASE IN
ITEM BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
20000 Credit given to City to allow
PTS Contractors to Cast-In-
Place, instead of using Pre-
Cast Structures for four
Junction Chambers,per
letter dated June 12,2012,
complete as specified
Each 0.00 -4.00 -4.00 $2,500.00 ($10,000.00)
20001 Additional labor,materials,
and equipment to modify
Junction Chamber 15-23 to
include a Type III Inlet,per
Invoice number 12-605
T&M-10,dated August 6,
2012,complete as Lump
specified Sum _ 0.00 1.00 1.00 $2,820.00 $2,820.00
ADDITIONAL WORK:C.O.#2 -(ITEMS 20000-20001)-SUB-TOTAL $2,820.00 ($10,000.00)
NET DECREASE TO: SECTION II ($3,910.00)
SECTION III-SANITARY SEWER
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
3416 Furnish and install 36-inch
open cut casing pipe, Linear
complete as specified Foot 0.00 20.00 _ 20.00 $336.00 $6,720.00
SECTION III-(BID ITEM 3416)-SUB-TOTAL $6,720.00 $0.00
ADDITIONAL WORK REQUIRED: C.O.#2-SECTION III
INCREASE IN DECREASE IN
ITEM BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
Page 1 of 3
CONTRACT: 12-04 CHANGE ORDER#2
BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
30000 Additional labor,materials,
and equipment to have
Great Lakes TV Seal
rehabilitate MH 03-31,with
a spray liner,complete as Lump
specified Sum 0.00 1.00 1.00 $2,850.00 $2,850.00
30001 Additional labor,materials,
and equipment to break out
concrete poured around
existing manhole in the
intersection of W. 15th
Avenue and Nebraska
Street and core into
existing man hole at a
lower elevation due to
utility conflicts per Invoice
12-605-T&M-7,dated June
13,2012,complete as Lump
specified Sum 0.00 1.00 1.00 _ $2,643.20 $2,643.20
ADDITIONAL WORK: C.O.#1-(ITEM 3006)SUB-TOTAL $5,493.20 $0.00
NET INCREASE TO: SECTION III $12,213.20
SECTION IV-WATER MAIN
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION IV
BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
Furnish&install 12-inch
trenchless casing pipe, Linear
40002 complete as specified Foot 0.00 20.00 20.00 $193.00 $3,860.00
40003 Additional labor,materials,
and equipment to cut out
existing 12"x 6"tapping
tee and replace with a 12"
repair sleeve, per Invoice
12-605-T&M-5,dated June
13,2012,complete as Lump
specified Sum 0.00 1.00 1.00 $1,393.67 $1,393.67
40004 Additional labor,materials,
and equipment to cap
existing 6"watermain by
old hydrant,due to leaky
valve that was shut off but
still leaking,per Invoice 12-
605-T&M-6,dated June 13,
2012,complete as Lump
specified Sum 0.00 1.00 1.00 $956.36 $956.36
Page 2 of 3
CONTRACT: 12-04 CHANGE ORDER#2
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
40005 Additional labor,materials,
and equipment to repair
water main break when
valve broke while trying to
shut it off,per Invoice 12-
605-T&M-9,dated July 13,
2012,complete as Lump
specified Sum 0.00 1.00 1.00 $1,841.00 $1,841.00
ADDITIONAL WORK: C.O.#1 (ITEMS 4037-40001)-SUB-TOTAL $8,051.03 $0.00
NET INCREASE TO: SECTION IV $8,051.03
NET INCREASE TO SECTIONS II,III,&IV $26,354.23
NET DECREASE TO SECTIONS II,III,&IV ($10,000.00)
NET INCREASE TO CONTRACT: $16,354.23
Page 3 of 3