SEPTEMBER 11, 2012 12-432 RESOLUTION
(CARRIED___6-0____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT 12-07 WITH VINTON CONSTRUCTION CO. FOR
VARIOUS CONCRETE PAVING & UTILITY PROJECTS – NORTH
SIDE AREA (+$27,212.17)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
VINTON CONSTRUCTION COMPANY
P.O. Box 1987
Manitowoc, WI 54221-1987
Net Increase to contract: $27,212.17
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 311-0410-7480-00000 Sidewalk Construction Fund
315-0410-7480-00000 Street Improvement Fund Expenditures
317-0410-7480-03301 Special Assessments Fund – Streets
317-0410-7480-03302 Special Assessments Fund – Sewer
317-0410-7480-03303 Special Assessments Fund – Water
317-0410-7480-03304 Special Assessments Fund – Sidewalks
317-0410-7480-03305 Special Assessments Fund – Storm Water
541-1810-1799-00000 Water Utility Construction Work in Progress
551-1910-1799-00000 Sewer Utility Construction Work in Progress
561-2010-1799-00000 Storm Water Utility Construction Work in Progress
(411111-1-)
OJHKOJH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: September 6, 2012
RE: Change Order No. 1 for Public Works Contract No. 12-07
Various Concrete Paving & Utility Projects—North Side
Vinton Construction Company (+$27,212.17)
BACKGROUND
Change Order No. 1 for Contract 12-07 is scheduled for consideration by the Common Council at the
September 11, 2012 meeting. The contract was originally awarded to Vinton Construction Company in April of
2012. This change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Storm Sewer—Additional work and materials required to match field conditions.
• Sanitary Sewer—Additional work and materials required to match field conditions.
• Water Main — Additional work and materials were needed for repairing existing water main breaks and
for construction crew down time due to failed water valve.
FISCAL IMPACT
Contract Section Change Order Amount New Contract Total CIP Budget Amount
Concrete Paving $0.00 $1,684,831.85 $2,204,834.00
Storm Sewer $3,000.93 $1,409,543.43 $1,659,000.00
Sanitary Sewer $17,277.26 $718,806.26 $1,040,300.00
Water Main $6,933.98 $1,090,017.48 $1,606,900.00
Traffic $0.00 $31,425.00 $41,700.00
Total $27,212.17 $4,934,624.02 $6,552,734.00
Adequate funds are available in the relating sections of the 2012 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 1 to Contact No. 12-07 in the amount of +$27,212.17 to Vinton
Construction Company.
Approved:
Mark A. Rohloff
City Manager
SMG/tlt
1:1Engineering112-07 Conc Paving&Util-North\Project_Information\Correspondence\Memo112-07 Memo for CO#1_9-6-12.docx
TO: Vinton Construction Co. CHANGE ORDER# 1
2705 N Rapids Road DATED: August 21, 2012
PO Box 1987
Manitowoc, WI 54221-1987
Your present contract with the City of Oshkosh, Contract 12-07, awarded April 10, 2012, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING 0.00
NET INCREASE TO: SECTION II - STORM SEWER 3,000.93
NET INCREASE TO: SECTION III - SANITARY SEWER 17,277.26
NET INCREASE TO: SECTION IV- WATER MAIN 6,933.98
NET INCREASE TO: SECTION V - ELECTRICAL 0.00
NET INCREASE TO CONTRACT $27,212.17
Section I Section II Section III Section IV Section V
(Paving) (Storm) (Sanitary) (Water) (Electrical) Totals
Bid Total $1,684,831.85 $1,406,542.50 $701,529.00 $1,083,083.50 $31,425.00 $4,907,411.85
C.O.#1 $3,000.93 $17,277.26 $6,933.98 $27,212.17
Contract Total $1,684,831.85 $1,409,543.43 $718,806.26 $1,090,017.48 $31,425.00 $4,934,624.02
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approve. -Id accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 12-07 CHANGE ORDER#1
SECTION II-STORM SEWER
ADDITIONAL WORK REQUIRED: C.O.#1 - SECTION II
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
20000 Additional labor, materials,
and equipment to lower the
inlet lead out of MH B11 to
get under the sanitary
sewer, per Invoice dated
6/12/12,complete as Lump
specified Sum 0.00 1.00 1.00 $2,072.18 $2,072.18
20001 Furnish and install 8"x 8"
tees,complete as specified
Each 0.00 2.00 2.00 $100.00 $200.00
20002 Additional labor, materials,
and equipment to reset
Inlet D-36,which was
installed to an incorrect
grade, per Invoice dated
7/24/12, complete as Lump
specified Sum 0.00 1.00 1.00 $728.75 $728.75
ADDITIONAL WORK:C.O.#1 -(ITEMS 20000-20002)-SUB-TOTAL $3,000.93 $0.00
NET INCREASE TO: SECTION II $3,000.93
SECTION III-SANITARY SEWER
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION III
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
30000 Additional labor, materials,
and equipment to cut in
and install a new additional
wye for 544 School Street.
Existing lateral currently
goes through neighbor's
yard and is connected to
the sanitary sewer on Bay
Street, per Invoice dated
6/6/12, complete as
specified Lump
Sum 0.00 1.00 1.00 $1,611.43 $1,611.43
Page 1 of 4
CONTRACT: 12-07 CHANGE ORDER#1
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
30001 Additional labor, materials,
and equipment to install an
8"x 8"wye for Church on
Bay Street. The existing
lateral changed from a 6"
to an 8"lateral at the
property line and
Contractor had to cap the
6"wye and install and 8"
wye with two inline
sleeves, per Invoice dated
6/7/12, compelte as Lump
specified Sum 0.00 1.00 1.00 $4,556.27 $4,556.27
30002 Additional labor and
equipment to investigate a
sanitary lateral blockage
reported by homeowner.
There was no blockage
and City agreed to spit the
time with the Contractor,
per Invoice dated 6/12/12, Lump
complete as specified Sum 0.00 0.50 0.50 $1,035.00 $517.50
30003 Additional labor, materials,
and equipment to remove
concrete encased drop on
MH 02-108,so Contractor
could connect to existing
drop at the proposed
grade, per Invoice dated
6/14/12, complete as Lump
specified Sum 0.00 1.00 1.00 $2,968.42 $2,968.42
30004 Additional labor,materials,
and equipment to remove
concrete encasement
around MH 11-621 to allow
for the proposed
connection into the existing
manhole, per Invoice dated
6/27/12, complete as Lump
specified Sum 0.00 1.00 1.00 $902.00 $902.00
30005 Additional labor, materials,
and equipment to bulkhead
an existing abandoned
sanitary wye, creating a
sink hole in the intersection
of Broad Street and School
Avenue, per Invoice dated
7/6/12, complete as Lump
specified Sum 0.00 1.00 1.00 $994.70 $994.70
Page 2 of 4
•
CONTRACT: 12-07 CHANGE ORDER#1
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
30006 Additional labor, materials,
and equipment to cap wye
for 538 Boyd Street at an
abandoned sanitary lateral
and install a new wye at
new location,
approximately 30 feet
south of original location,
per Invoice dated 7/23/12, Lump
complete as specified Sum 0.00 1.00 1.00 $3,175.05 $3,175.05
30007 Additional labor, materials,
and equipment to remove
concrete encasement
around existing City fiber
optic cable,which also
encased the sanitary
sewer. Contractor had to
temporary connect the
sanitary sewer until City
Electric Division could
review the situation. Once
clear Contractor removed
the concrete encasement,
and installed the proposed
sanitary sewer underneath
the City fiber, per Invoices
dated 7/30/12 and 8/1/12, Lump
complete as specified Sum 0.00 1.00 1.00 _ $2,551.89 $2,551.89
ADDITIONAL WORK: C.O.#1 -(ITEMS 30000-30007)-SUB-TOTAL $17,277.26 $0.00
NET INCREASE TO: SECTION III $17,277.26
SECTION IV-WATER MAIN
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION IV
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
40000 Additional labor, materials,
and equipment to repair an
existing broken water valve
on Bay Street, per Invoice
dated 5/22/12,complete as Lump
specified Sum 0.00 1.00 1.00 $880.00 $880.00
Page 3 of 4
CONTRACT: 12-07 CHANGE ORDER#1
INCREASE IN DECREASE
ITEM DESCRIPTION UNIT 81D INSTALLED NET NET UNIT CONTRACT IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT
PRICE
40001 Additional labor, materials,
and equipment to cut out
an existing main and install
a new 6"x 6"tee. Plans
called for a tapping tee, but
tapping could not be used
due to oversized main, per
Invoice dated 6/19/12,
complete as specified Lump
Sum 0.00 1.00 1.00 $2,454.00 $2,454.00
40002 Additional labor, materials,
and equipment to fix
broken existing water main
on Boyd Street, per Invoice
dated 7/3/12, complete as Lump
specified Sum 0.00 1.00 1.00 $2,039.23 $2,039.23
40003 Additional labor, materials,
and equipment to repair
existing 6"broken water
main on Boyd Street at
station 87+72, per Invoice
dated 7/9/12, complete as Lump
specified Sum 0.00 1.00 1.00 $832.00 $832.00
40004 Construction crew down
time for City not being able
to shut down the existing
water main for a valve
abandonment in the
Washington Avenue and
Boyd Street intersection.
Down time was approved
by the Water Inspector on
site, per Invoice dated
7/26/12, complete as
specified Hours 0.00 1.00 1.00 $728.75 $728.75
ADDITIONAL WORK: C.O.#1 (ITEMS 40000-40004)-SUB-TOTAL $6,933.98 $0.00
NET INCREASE TO: SECTION IV $6,933.98
NET INCREASE TO SECTIONS I, II, III, IV,V $27,212.17
NET DECREASE TO SECTIONS I, II, III, IV,V $0.00
NET INCREASE TO CONTRACT: $27,212.17
Page 4 of 4