MAY 9, 2012 12-223 RESOLUTION
(CARRIED___7-0____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: AWARD PARTIAL BID TO LUNDA CONSTRUCTION FOR CITY
CENTER HOTEL RIVERWALK IMPROVEMENTS ($1,024,040.10)
INITIATED BY: COMMUNITY DEVELOPMENT
WHEREAS, the City of Oshkosh has heretofore advertised for bids for
construction of a bike/pedestrian riverwalk and docks along the north side of the Fox
River, between Jackson Street and Main Street, adjacent to the City Center Office
Complex and City Center Hotel; and
WHEREAS, necessary lands have been donated and appropriate easements
obtained from the owners of the City Center Hotel for said improvements; and
WHEREAS, upon the opening and tabulation of bids it appears that the following
partial alternate bid for the City Center Hotel area is the most advantageous bid:
Lunda Construction
2000 Taylor Street
Little Chute, WI 54140
TOTAL BASE BID: $1,024,040.10
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Oshkosh that said partial alternate bid is hereby accepted and the proper City officials
are hereby authorized and directed to enter into an appropriate agreement for the
purpose of same, all according to plans, specifications, and bid on file. Money for this
purpose is hereby appropriated from:
Acct. No. 530-1040-7216-07278 TID #17 Fund – Land Improvements
CITY CENTER RIVERWALK
BIDS OPENED FEBRUARY 27, 2012
1:00 PM
NAME OF LUNDA CONSTRUCTION EDWARD KRAEMER&SONS MCMULLEN & PITZ CONSTRUCTION
BIDDER 2000 Taylor Street One Plainview Road 17 Maritime Drive
Little Chute,WI 54140 Plain, WI 53577 Manitowoc,WI 54221
BASE BID TOTAL
CITY CENTER OFFICE $2,874,590.70 $4,804,625.00 $4,325,480.00
COMPLEX
ALTERNATE BID TOTAL
CITY CENTER HOTEL $1,024,040.10 $1,176,320.00 $1,468,122.00
, City of Oshkosh
QXHKQfH
TO: Honorable Mayor and members of the Common Council
FROM: Allen Davis, Community Development Director
DATE: May 3, 2012
SUBJECT: Award Partial Bid to Lunda Construction for the City Center Hotel
riverwalk improvements -Northshore - Jackson to Main Riverwalk/docks
Bid Award
BACKGROUND
The City has designed and bid out the Jackson Street to Main Street portion of the
proposed riverwalk and dock project. The bid was split into two pieces; the first piece
was the base bid for the City Center office complex river frontage. The City Council
awarded the base bid on March 27, 2012. The second piece is an alternate bid that was
included for the hotel river frontage. The Council is taking action on the alternate bid at
this time.
The City Center office complex donated land and granted easements for their portion of
the riverwalk and docks. The new owners of the hotel are doing the same as part of this
City Council meeting.
ANALYSIS
The City has already obtained the following grants for the project:
• $644,952 for docks and riverwalk.
• $ 45,000 for riverwalk
In addition,the City has 2 existing Tax Increment Finance (TIF) districts that can pay for
riverwalk improvements and a future TIF district for the hotel to also pay for riverwalk
and dock improvements.
The City awarded Lunda the base bid for $2,874,590.70 and their bid was the lowest bid.
Lunda's alternate bid for the hotel portion was also lowest bid at$1,024,040.10. The
total for both bids is $3,898,630.80
RECOMMENDATION
The City Council awards the alternate bid of$1,024,040.10 to Lunda Construction.
♦1
FISCAL IMPACT
The City's CIP 2011 and 2012 budgeted $4,199,200 for the project. The portions of the
project costs that are not paid with grant funds will be paid by existing or future TIF
increment.
Approved,
City Manager