FEBRUARY 14, 2012 12-45 RESOLUTION
(CARRIED___7-0____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT NO. 11-07 WITH PTS CONTRACTORS, INC. FOR
VARIOUS CONCRETE PAVING & UTILITY PROJECTS – NORTH
SIDE AREA (+$77,413.00)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
PTS CONTRACTORS, INC.
4075 Eaton Road
Green Bay, WI 54311
Net Increase to Contract: $77,413.00
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 311-0410-7480-00000 Sidewalk Construction Fund
315-0410-7480-00000 Street Improvement Fund Expenditures
317-0410-7480-03301 Special Assessments Fund - Streets
317-0410-7480-03302 Special Assessments Fund - Sewer
317-0410-7480-03303 Special Assessments Fund - Water
317-0410-7480-03304 Special Assessments Fund - Sidewalks
317-0410-7480-03305 Special Assessments Fund - Storm Water
541-1810-1799-00000 Water Utility Construction Work in Progress
551-1910-1799-00000 Sewer Utility Construction Work in Progress
561-2010-1799-00000 Storm Water Utility Construction Work in Progress
OJHKOJH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: February 9, 2012
RE: Change Order No. 2 for Public Works Contract No. 11-07
Concrete Paving and Utilities—North Side Paving Project
PTS Contractors, Inc. (+$77,413.00)
BACKGROUND
Change Order No. 2 for Contract 11-07 is scheduled for consideration by the Common Council at the February
14, 2012 meeting. The contract was originally awarded to PTS Contractors, Inc. in May of 2011. This change
order is for the inclusion of the additional services needed to complete the vacated Blackhawk Street Outfall
Replacement (Contract 11-34). The vacated Blackhawk Street Outfall failed late in 2011 and required an
emergency replacement. The Department of Public Works solicited proposals from five utility contractors to
perform the repairs. PTS Contractors, Inc. was the low bidder, and was awarded the work as a change order
onto Contract 11-07.
ANALYSIS
• Storm Sewer— The work on this change order included the removal of the existing failed storm sewer
outfall, and replacing the outfall with a new sixty inch (60")concrete pipe outfall. The work also included
some dredging of sediment from the Fox River and placement of rip-rap.
• Sanitary Sewer—The work on this change order includes one chimney seal that was not included in the
previous change order.
FISCAL IMPACT
Contract Section Change Order Amount CIP Budget Amount New Contract Total
Concrete Paving $0.00 $1,835,433.00 $1,029,155.96
Storm Sewer $76,956.00 $835,000.00 $675,351.45
Sanitary Sewer $457.00 $573,200.00 $476,645.64
Water Main $0.00 $817,100.00 $478,195.01
Total $77,413.00 $4,060,733.00 $2,659,348.06
Adequate funds are available in the relating sections of the 2011 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 2 to Contact No. 11-07 in the amount of +$77,413.00 to PTS
Contractors, Inc.
Respectfully Submitted, Approved:
2,7),J4,14,
Steven M. Gohde, P.E. Mark A. Rohloff
Asst. Director of Public Works City Manager
SMG/tit
I:\Engineering\l 1-07 Concrete Paving and Utilities North\Project_Information\Correspondence\Memo\I 1-07 Memo for CO#2_2-9-12.doc
TO: PTS CONTRACTORS, INC CHANGE ORDER#2
4075 EATON ROAD DATED: February 6, 2012
GREEN BAY WI 54311
Your present contract with the City of Oshkosh, Contract No.11-07, awarded May 24, 2011, is hereby
amended and changed as follows:
NET INCREASE TO: SECTION I - PAVING $1,560.00
NET INCREASE TO: SECTION II - STORM SEWER $75,396.00
NET INCREASE TO: SECTION III - SANITARY SEWER $457.00
NET INCREASE TO: SECTION IV-WATER MAIN $0.00
NET INCREASE TO CONTRACT $77,413.00
Section I Section II Section III Section IV
(Paving) (Storm) (Sanitary) (Water) Totals
Bid Total $1,081,034.50 $627,720.50 $504,782.75 $468,751.00 $2,682,288.75
C.O. #1 ($51,878.54) ($29,325.05) ($28,594.11) $9,444.01 ($100,353.69)
Prev.Contract Totals $1,029,155.96 $598,395.45 $476,188.64 $478,195.01 $2,581,935.06
C.O. #2 Totals $1,560.00 $75,396.00 $457.00 $0.00 $77,413.00
Contract Total $1,030,715.96 $673,791.45 $476,645.64 $478,195.01 $2,659,348.06
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approved and accepted:
Con ractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT:11-07 CHANGE ORDER#2
SECTION I-CONCRETE PAVING(Original Contract 11-07)
ITEM CONTRACT INSTALLED NET NET _ UNIT INCREASE IN DECREASE IN
DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE
NUMBER CONTRACT CONTRACT
PRICE PRICE
100 Pavement removal, Square
2822.00 2,822.00 $3.25
complete as specified Yards
101 Sidewalk and driveway Square
removal,complete as Feet 36289.80 36,289.80 $0.40
specified
102 Excavation,complete as Cubic 11637.30 11,637.30 $8.60
specified Yards
103 7"non-reinforced concrete
pavement,including
integral curb,5'base Square 14571.39 14,571.39 $27.60
material and grading, Yards
complete as specified
104 8"non-reinforced concrete
pavement,including Square
integral curb,6"base Yards 7447.33 7,447.33 $31.50
material and grading,
complete as specified
105 8"concrete pavement,
HES,including integral Square
curb and 6"base material Yards 263.62 263.62 $36.00
and grading,complete as
specified
106 12"wide radius curb head, Linear
complete as specified Feet 613.60 613.60 $5.08
107 Standard 24"curb&gutter, Linear
7"(tie-in),complete as Feet 13.50 13.50 $25.40
specified
108 Standard 30"curb&gutter, Linear
7"(tie-in),complete as Feet 173.70 173.70 $21.35
specified
109 Sidewalk curb,complete as Linear
8.20 8.20 $17.30
specified Feet
110 4"concrete sidewalk, Square 19675.80 19,675.80 $3.34
complete as specified Feet
111 6"concrete sidewalk and Square
driveway,complete as Feet 18394.70 18,394.70 $3.66
specified
112 8"concrete sidewalk and Square
driveway,complete as Feet 3110.40 3,110.40 $4.07
specified
113 2"asphaltic concrete Square
transition,with base, Yards 159.93 159.93 $24.65
complete as specified
114 3'/i'asphaltic concrete Square
driveway/path,with base, Feet 344.70 344.70 $4.50
complete as specified
115 3'/z"asphaltic concrete Square
transition,with base, Yards 166.41 166.41 $46.00
complete as specified
116 5"asphaltic concrete Square
pavement,with base, Yards 274.97 274.97 $46.00
complete as specified
Page 1 of 10
CONTRACT:11-07 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
117 Furnish and install crushed
stone base course, Tons 1206.00 1,206.00 $7.90
complete as specified
118 Sawing,complete as Linear 1101.70 1,101.70 $1.50
specified Feet
119 Furnish and install
pavement ties(epoxy Each 295.00 295.00 $7.00
coated),complete as
specified
120 Adjust manholes and inlets,
complete as specified Each 112.00 112.00 $230.00
121 Furnish and install No.4
reinforcing bars(epoxy Linear 3530.00 3,530.00 $0.81
coated),complete as Feet
specified
122 Remove stumps,complete Inch
as specified Diameter 54.00 54.00 $20.00
123 Remove trees and stumps,
complete as specified Inch ed 87.00 $25.00
Diameter
124 Furnish and install trees, Each 1.00 1.00 $250.00
complete as specified
125 Furnish and install metal Square
detectable warning fields, Feet 344.00 344.00 $25.40
complete as specified
126 Terrace work on Broad
Street,complete as Sum 1.00 1.00 $5,191.00
specified
127 Terrace work on Custer
Avenue,complete as
Lump 1.00 1.00 $4,653.00
specified
128 Terrace work on Eastman
Street,complete as
Lump 1.00 1.00 $3,936.00
specified
129 Terrace work on Lincoln
Avenue,complete as
Lump u 1.00 1.00 $857.00
specified
130 Terrace work on Monroe
Street,complete as Sump 1.00 1.00 $5,646.00
specified
131 Terrace work on East New
York Avenue,complete as
Lump 1.00 1.00 $1,028.00
specified
132 Terrace work on East
Tennessee Avenue, Sum 1.00 1.00 $3,385.00
complete as specified
133 Remove rails and ties, Lump 1.00 1.00 $1,525.00
complete as specified Sum
134 Excavation special, Tons 0.00 0.00 $10.00
complete as specified
135 Furnish and install cold
weather covering, 1-layer Square 0.00 0.00 $0.01
visquine,complete as Yards
specified
136 Furnish and install cold
weather covering,2-layer Square 0.00 0.00 $0.01
visquine,complete as Yards
specified
Page 2 of 10
CONTRACT:11-07 CHANGE ORDER#2
INCREASE IN DECREASE IN
ITEM CONTRACT INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
137 Furnish and install cold
weather covering,2-layer Square 0.00 0.00 $0.01
visquine and 6"hay, Yards
complete as specified
SECTION I-(ITEMS 100-137)-SUB-TOTALS $0.00 $0.00
SECTION I-CONCRETE PAVING(Original Contract 11-34)
INCREASE IN DECREASE IN
ITEM CONTRACT INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
100 Remove Asphalt Trail Square 0.00 15.00 15.00 $6.00
Yards $90.00
101 Temporary Cold Mix Square
Asphalt Trail Patch(include Feet 0.00 15.00 15.00 $45.00
6"CABC) $675.00
102 Hot mix Asphalt Trail Patch
(3"total depth,installed in Square 0.00 15.00 15.00 $45.00
2 lifts,E-0.3,9.5 mm) Yards
$675.00
103 Saw Cut Linear 0.00 20.00 20.00 $6.00
Feet _ $120.00
SECTION I-(ITEMS 100-103)-SUB-TOTALS $1,560.00 $0.00
NET INCREASE TO:SECTION I $1,560.00
SECTION II-STORM SEWER(Original Contract 11-07)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2014 Utility line opening, Each 5.00 5.00 $860.00
complete as specified
2030 Furnish and install 6"storm Linear
sewer,complete as Feet 10.00 10.00 $54.00
specified
2034 Furnish and install 10"
storm sewer,complete as Linear 20.00 20.00 $58.00
specified Feet
2036 Furnish and install 12" Linear
storm sewer,complete as Feet 1018.90 1,018.90 $43.50
specified
2042 Furnish and install 15"
storm sewer,complete as Linear 1892.30 1,892.30 $42.50
specified Feet
2048 Furnish and install 18"
storm sewer,complete as Linear 1206.40 1,206.40 $46.50
specified Feet
2054 Furnish and install 21"
storm sewer,complete as Linear 231.50 231.50 $53.00
specified Feet
2060 Furnish and install 24"
storm sewer,complete as Linear 524.10 524.10 $59.00
specified Feet
2072 Furnish and install 30"
storm sewer,complete as Linear 209.40 209.40 $69.50
specified Feet
Page 3 of 10
CONTRACT:11-07 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2074
Furnish and install 30"RCP Linear
29.00 29.00 $84.50
Class Ill storm sewer, Feet
complete as specified
2078 Furnish and install 36"
storm sewer,complete as Linear 440.80 440.80 $84.50
specified Feet
2128 Furnish and install 24"x
38"HERCP Class III storm Linear 384.70 384.70 $94.00
sewer,complete as Feet
specified
2280 Furnish and install 6"storm Linear
lateral,complete as Feet 2830.40 2,830.40 $37.50
specified
2284 Furnish and install storm
sewer marker balls, Each 204.00 204.00 $17.75
complete as specified
2286
Furnish&install clay dams, Each 106.00 106.00 $29.00
complete as specified
2532 Furnish and install standard
storm manhole(4' Vertical 131.68 131.68 $244.00
diameter),complete as Feet
specified
2534 Furnish and install standard
storm manhole(5' Vertical 32.78 32.78 $391.00
diameter),complete as Feet
specified
2536 Furnish and install standard
storm manhole(6' Vertical 4.20 4.20 $473.00
diameter),complete as Feet
specified
2612
Furnish and install Type 1 Each 4.00 4.00 $1,383.00
inlet,complete as specified
2614 Furnish and install Type 3
inlet(with 18"sump), Each 55.00 55.00 $1,476.00
complete as specified
2800 Connect to existing storm
sewer,complete as Each 7.00 7.00 $783.00
specified
2802 Connect to existing storm
lateral,complete as Each 1.00 1.00 $249.00
specified
2806 Connect to existing
manhole,complete as Each 9.00 9.00 $578.00
specified
2808 Connect to existing inlet, Each 2.00 2.00 $578.00
complete as specified
2820 Abandon 8"-12"storm Linear
sewer,complete as Feet 3640.20 3,640.20 $1.00
specified
2824 Abandon storm manholes
and inlets,complete as Each 30.00 30.00 $231.00
specified
Page 4 of 10
CONTRACT:11-07 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2856 Furnish,install,maintain,
and remove Type D inlet Each 117.00 117.00 $65.00
protection,complete as
specified
2862 Furnish,install,maintain,
and remove stone bag, Each 15.00 15.00 $10.00
complete as specified
SECTION II-(ITEMS 2014-2862)-SUB-TOTALS $0.00 $0.00
SECTION II-STORM SEWER(Original Contract 11-34)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2105 Furnish&Install 60"RCP
Class III with Joint Ties and Linear 0.00 32.00 32.00 $1,100.00 $35,200.00
Clay bedding and backfill Feet
2572 Furnish&Install Standard Vertical
Storm Inlet Manhole(6'x6' Feet 0.00 6.50 6.50 $1,485.00 $9,652.50
Box)
2574 Furnish and Install 60"
RCP Class III Apron Each 0.00 1.00 1.00 $5,750.00 $5,750.00
Endwall w/joint ties
2872 Furnish,Install,Maintain
and Remove Turbidity Each 0.00 1.00 1.00 $1,200.00 $1,200.00
Barrier
2910 Furnish&Install Native Square
Seeding(WISDOT Seed Yards 0.00 59.00 59.00 $10.00 $590.00
Mixture 70)
2932 Furnish&Install Class I, Square
Urban,Type A Erosion Yards 0.00 59.00 59.00 $3.50 $206.50
Control Mat
2945 Furnish&Install Medium Square 0.00 14.00 14.00 $45.00 $630.00
Rip-Rap Yards
2990 Furnish,Install,Maintain Each 0.00 1.00 1.00 $11,000.00 $11,000.00
and Remove Coffer Dam
2995 Stockpile,load,and haul
contaminated sediment to Ton 0.00 200.00 200.00 $0.01 $2.00
Waste Management
Landfill in Berlin,WI
SECTION II-(ITEMS 2105-2995)-SUB-TOTALS $64,231.00 $0.00
ADDITIONAL WORK REQUIRED: (Original Contract 11-07)C.O.#1 - SECTION II
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
20000 Additional labor,matreials,
and equipment to move
and reset storm inlet B-62, Lump
per Invoice 11-591-02, Sum 1.00 1.00 $1,054.65
dated 8/30/11,complete as
specified
ADDITIONAL WORK:C.O.#1 -(ITEM 20000)-SUB-TOTAL $0.00 $0.00
ADDITIONAL WORK REQUIRED: C.O.#2 - SECTION II
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2991 Additional coffer dam
length and excavation in Lump 0.00 1.00 1.00 $8,800.00 $8,800.00
Fox River based upon Sum
survey
Page 5 of 10
CONTRACT:11-07 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2996 Additional cost to haul
contaminated materials to Lump 0.00 1.00 1.00 $860.00 $860.00
Whitelaw instead of Berlin Sum
2997 Import clay material for
bedding and backfill of pipe Sump 0.00 1.00 1.00 $645.00 $645.00
2998 Remove unsuitable backfill Lump 0.00 1.00 1.00 $860.00 $860.00
materials Sum
ADDITIONAL WORK:C.O.#2 -(ITEMS 2991.2998)-SUB-TOTALS $11,165.00 $0.00
NET INCREASE TO: SECTION II $75,396.00
SECTION III-SANITARY SEWER(Orginal Contract 11-07)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIP710N UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
3000 Furnish and install 8" Linear
sanitary sewer relay, Feet 3585.20 3,585.20 $52.00
complete as specified
3004 Furnish and install 12" Linear
sanitary sewer relay, Feet 225.50 225.50 $107.00
complete as specified
3064 Furnish and install 12-inch
sanitary sewer drop, Vertical 6.81 6.81 $446.00
complete as specified Feet
3100 Furnish and install standard
sanitary manhole(4' Vertical 131.31 131.31 $208.00
diameter),complete as Feet
specified
3114
Furnish and install external
manhole chimney seal, Each 15.00 16.00 1.00 $457.00 $457.00
complete as specified
3210 Furnish and install 8"x 6"
factory wyes or tees, Each 90.00 90.00 $85.00
complete as specified
3214 Furnish and install 12"x 6"
factory wyes or tees, Each 9.00 9.00 $183.00
complete as specified
3234 Furnish and install 4"16"
sanitary lateral relay, Linear 2703.10 2,703.10 $69.00
complete as specified Feet
3236
Furnish and install sanitary Each 202.00 202.00
lateral marker balls, $18.00
complete as specified
3238 Furnish and install clay
dams,complete as Each 99.00 99.00 $57.00
_specified
Page 6 of 10
CONTRACT:11-07 CHANGE ORDER#2
INCREASE IN DECREASE IN
ITEM CONTRACT INSTALLED NET NET UNIT
DESCRIPTION UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE
3300 Furnish and install
connections to existing 8" Each 1.00 1.00
mains,complete as $600.00
specified
3302 Furnish and install
connections to existing 10" Each 1.00 1.00
mains,complete as $612.00
specified
3304 Furnish and install
connections to existing 12" Each 3.00 3.00 $1,107.00
mains,complete as
specified
3330 Furnish and install concrete
collars,complete as Each 0.00 0.00 $568.00
specified
3332
Core into existing manhole, Each 0.00 0.00 $657.00
complete as specified
3700 Televise sanitary sewer, Linear 3810.70 3,810.70 $1.15
complete as specified Feet
3800 Abandon sanitary
manholes,complete as Each 27.00 27.00 $289.00
specified
3802 Linear
Abandon 8"sanitary sewer, Feet 2700.00 2,700.00 $0.60
complete as specified
3806 Abandon 12"sanitary
sewer,complete as Linear 2064.00 2,064.00 $1.20
specified Feet
SECTION III-(ITEMS 3000-3806)-SUB-TOTALS $457.00 $0.00
ADDITIONAL WORK REQUIRED: (Original Contract 11-07)C.O.#1-SECTION III
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
3116 Furnish and install external
chimney seal extension,
complete as specified Each 6.00 6.00 $420.00
ADDITIONAL WORK: C.O.#1-(ITEM 3116)-SUB-TOTALS $0.00 $0.00
NET INCREASE TO: SECTION III $457.00
SECTION IV-WATER MAIN(Original Contract 11-07)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
4000 Furnish and install 4"
ductile iron watermain with Linear 32.00 32.00 $73.50
poly wrap relay,complete Feet
as specified
Page 7 of 10
CONTRACT:11-07 CHANGE ORDER#2
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
4002 Furnish and install 6"
ductile iron watermain with Linear 161.00 161.00 $132.00
poly wrap relay,complete Feet
as specified
4004 Furnish and install 8"
ductile iron watermain with Linear 3305.00 3,305.00 $63.50
poly wrap relay,complete Feet
as specified
4006 Furnish&install 10'ductile
iron watermain with poly Linear 215.00 215.00 $85.00
wrap relay,complete as Feet
specified
4036 Furnish and install 1"water Linear
service relay,complete as Feet 2198.50 2,198.50 $43.50
specified
4038 Furnish and install 1 'h" Linear
water service relay, Feet 0.00 0.00 $62.00
complete as specified
4048 Furnish and install 1'
corporation and stop box, Each 99.00 99.00 $259.00
complete as specified
4050 Furnish and install 1''A"
corporation and stop box, Each 1.00 1.00 $518.00
complete as specified
4054 Furnish and install water
service clay dams, Each 100.00 100.00 $29.00
complete as specified
4056 Furnish and install
connections to existing 4" Each 2.00 2.00 $1,283.00
watermain,complete as
specified
4058 Furnish and install
connections to existing 6" Each 10.00 10.00
watermain,complete as $1,332.00
specified
4060 Furnish and install
connections to existing 8" Each 6.00 6.00
watermain,complete as $1,385.00
specified
4062 Furnish&install
connections to existing 10" Each 1.00 1.00
watermain,complete as $1,490.00
specified
4109 Furnish and install 8"X 4"
tee,complete as specified Each 1.00 1.00 $299.00
4110 Furnish and install 8"X 6"
tee,complete as specified Each 8.00 8.00 $327.00
4111 Furnish and install 8"X 8"
tee,complete as specified Each 1.00 1.00 $390.00
4119 Furnish&install 10"X 6"
tee,complete as specified Each 1.00 1.00 $495.00
4189 Furnish and install 8"X 8"
cross,complete as Each 1.00 1.00 $553.00
specified
4235 Furnish and install 4-inch
45 degree bend,complete Each 4.00 4.00 $120.00
as specified
4236 Furnish and install 6-inch
45 degree bend,complete Each 28.00 28.00 $170.00
as specified
4237 Furnish and install 8-inch
45 degree bend,complete Each 9.00 9.00 $232.00
as specified
4263 Furnish and install 8"X 4"
reducer,complete as Each 1.00 1.00 $180.00
specified
Page 8 of 10
CONTRACT:11-07 CHANGE ORDER#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
4267 Furnish&install 10"X 8"
reducer,complete as Each 1.00 1.00 $251.00
specified
4400 Furnish and install 4"gate
valve,complete as Each 1.00 1.00 $882.00
specified
4401 Furnish and install 6"gate
valve,complete as Each 9.00 9.00 $1,032.00
specified
4402 Furnish and install 8"gate
valve,complete as Each 10.00 10.00 $1,426.00
specified
4403 Furnish&install 10"gate
valve,complete as Each 1.00 1.00 $2,007.00
specified
4500 Furnish and install hydrant,
complete as specified Each 9.00 9.00 $2,885.00
4502 Furnish and install gradelok
for hydrant branches, Each 0.00 0.00 $713.00
complete as specified
4900 Abandon watermain on
East Custer Avenue,
Harrison Street to Broad Sump 1.00 1.00 $2,300.00
Street,complete as
specified
4902 Abandon watermain on
Eastman Street,New York
Avenue to Custer Street, Sump 1.00 1.00 $2,300.00
complete as specified
4904 Abandon watermain on
Monroe Street,East Irving
Avenue to East Melvin
Lump u 1.00 1.00 $2,300.00
Avenue,complete as
specified
4906 Abandon watermain on
East Lincoln Avenue,
Monroe Street to CN
Lump 1.00 1.00 $1,500.00
Railroad tracks,complete
as specified
4908 Abandon watermain on
East New York Avenue,
North Main Street to Lump 1.00 1.00 $1,500.00
Jefferson Street,complete
as specified
SECTION IV-(ITEMS 4000-4908)-SUB-TOTALS $0.00 $0.00
ADDITIONAL WORK REQUIRED: (Original Contract 11-07)C.O.#1-SECTION IV
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
4264 Furnish and install 8"x 6"
reducer,complete as Each 1.00 1.00 $192.00
specified
4300 Furnish and install 8"
sleeve,complete as Each 1.00 1.00 $226.51
specified
Page 9 of 10
CONTRACT:11-07 CHANGE ORDER#2
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE 1N
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
40000 Additional labor,materials,
and equipment to fix a
leaking joint on existing 8"
water main in the
intersection of Custer Sump 1.00 1.00 $1,236.25
Avenue and Grand Street,
per Invoice 11-591-01,
dated 7/27/11,complete as
specified
ADDITIONAL WORK: C.O.#1 (ITEMS 4264-40000)-SUB-TOTAL $0.00 $0.00
NET INCREASE TO: SECTION IV $0.00
NET INCREASE TO SECTIONS I,II,III,IV $77,413.00
NET INCREASE TO SECTIONS I,II,III,IV $0.00
NET INCREASE TO CONTRACT: $77,413.00