January 27, 2012
Brian Enders
Northeast Asphalt
W6380 Design Drive
Greenville, WI 54942
Re: Change Order No. 1
Contract 11-13
Dear Mr. Enders:
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and Northeast
Asphalt regarding the above-mentioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
• • iel) - L
)avid C. Patek
Director of Public Works
DCP/tlt
Enclosure: Change Order No. 1
cc: Pam Ubrig, City Clerk (w/original)
Lynn Lorenson, City Attorney (w/copy)
File (w/original)
I:\Engineering\I 1-13 High Ave Asphalt Mill&Overlay\Project_In formation\Contract Info\CHANGE ORDERS\11-13 Page 1 of 1
Executed CO#1 Letter I-27-12.doc
CHANGE ORDER# 1
DATED: December 20, 2011
TO: BRIAN ENDERS
NORTHEAST ASPHALT
W6380 DESIGN DRIVE
GREENVILLE WI 54942
Your present contract with the City of Oshkosh, Contract No. 11-13 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION I -ASPHALT PAVING $78,149.44
NET INCREASE TO: SECTION II -STORM SEWER $7,917.83
NET INCREASE TO: SECTION III -SANITARY SEWER $1,102.86
NET INCREASE TO CONTRACT: $87,170.13
CITY OF OSHKOSH
BY: ' w-- l 'r "4/6"-
Recommended: ity Manager -
C -44
Director of Public Works City Clerk
Approved and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
/e4qe-d-4e_io
Comptroller
Approved as to form: r
'.►�
1I~-3 J+I11111kaI7J -
City Attorney
ec
CONTRACT:11-13 CHANGE ORDER#1
SECTION I-ASPHALT PAVING
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
100 Pavement removal, Square
complete as specified Yards 9,800.00 13,731.20 3,931.20 $3.35 $13,169.52
Sidewalk and driveway Square
101 removal,complete as Feet
specified 6,100.00 5,052.50 -1,047.50 $0.75 ($785.63)
102 Excavation,complete as Cubic
specified Yards 1,200.00 2,506.60 1,306.60 $8.75 $11,432.75
103 Pavement milling,complete Square
as specified Yards 23,250.00 22,510.40 -739.60 $3.60 ($2,662.56)
HMA pavement type E-1,
104 complete as specified Tons 6,050.00 5,682.00 -368.00 $51.35 ($18,896.80)
Tack coat,complete as
105 specified Gallons 600.00 725.00 125.00 $7.50 $937.50
Curb and gutter removal Linear
106 and replacement,complete Feet
as specified 550.00 954.70 404.70 $22.75 $9,206.93
107 4"concrete sidewalk, Square
complete as specified Feet 4,700.00 4,237.00 -463.00 $3.25 ($1,504.75)
6"concrete sidewalk and Square
108 driveway,complete as Feet
specified 1,600.00 1,428.80 -171.20 $3.50 ($599.20)
Furnish and install metal Square
109 detectable warning fields, Feet
complete as specified 120.00 120.00 $27.75
Fumish and install crushed
110 stone base course, Tons
complete as specified
6,500.00 11,610.50 5,110.50 $9.75 $49,827.38
111 Sawing,complete as Linear
specified Feet 12,800.00 10,620.80 -2,179.20 $2.25 ($4,903.20)
Adjust manholes and inlets,
112 complete as specified Each
85.00 64.00 -21.00 $500.00 ($10,500.00)
Prepare foundation for Lump
113 asphaltic paving,complete
as specified Sum 1.00 1.00 $32,500.00
Terrace work on High Lump
114 Avenue,complete as
specified Sum 1.00 1.00 $28,250.00
Load and haul
115 contaminated material, Tons
complete as specified 200.00 329.00 129.00 $10.00 $1,290.00
Load and haul
116 contaminated material Tons
(special),complete as
specified 50.00 0.00 -50.00 $11.00 ($550.00)
SECTION I-(BID ITEMS 100-116)-SUB-TOTALS $85,864.08 ($40,402.14)
ADDITIONAL WORK REQUIRED: C.O.#1-SECTION I
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Excavate and remove top
section of existing water
valve&adjust.Install new
117 top section supplied by City Each
of Oshkosh Water
Distribution per Bill Genz 0.00 37.00 37.00 $275.00 $10,175.00
Page 1 of 4
CONTRACT:11-13 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Fine grade and pave a 2"
temporary asphalt
118 pavement on Osceola St. Square
from approximately 200 ft Yards
West of High Ave.to Pearl
Ave. 0.00 1,472.60 1,472.60 $12.50 $18,407.50
Adjust water valves on
119 Osceola St.in 2"temporary Each
asphalt pavement
0.00 8.00 8.00 $275.00 $2,200.00
Furnish&install manhole
120 riser in 2"asphalt Each
pavement on Osceola St. 0.00 1.00 1.00 $250.00 $250.00
Trenching excavation for 3"
conduit across High Ave.in Lump
121 front of new Sage Hall for a Sum
pedestrian crossing beacon
0.00 1.00 1.00 $900.00 $900.00
Repair sidewalk over UW-
122 O steam tunnel chamber in Lump
front of UW-0 parking Sum
ramp on High Ave. 0.00 1.00 1.00 $225.00 $225.00
• Additional traffic control for
four(4)no left tum(3-6 Lump
123 pm)custom signs on Sum
Congress Ave.at
Arboretum Dr. 0.00 1.00 1.00 $390.00 $390.00
Small load charge and
H.E.S.concrete pavement Lump
124 for sanitary lateral work at Sum
1227 High Ave.
0.00 1.00 1.00 $140.00 $140.00
ADDITIONAL WORK: C.O.#1-(ITEMS 117-124)-SUB-TOTAL $32,687.50 $0.00
NET INCREASE TO: SECTION I $78,149.44
SECTION II-STORM SEWER
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE _ PRICE
Utility line opening,
2014 complete as specified Each
5.00 6.00 1.00 $400.00 $400.00
Furnish and install 12"
2036 storm sewer,complete as Linear
specified Feet
35.00 79.50 44.50 $54.60 $2,429.70
Furnish and install 15"
2042 storm sewer,complete as Linear
specified Feet
90.00 92.50 2.50 $59.25 $148.13
Furnish and install Type 1
inlet with a Neenah R-3015
2612 frame and Type R gate, Each
complete as specified
10.00 10.00 10.00 $1,280.00
Reconstruct Type 1 inlet,
2635 complete as specified Each
3.00 7.00 4.00 $1,055.00 $4,220.00
Connect to existing storm
2800 sewer,complete as Each
specified
10.00 19.00 9.00 $250.00 $2,250.00
Page 2 of 4
CONTRACT:11-13 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Connect to existing
2806 manhole,complete as Each
specified
3.00 4.00 1.00 $300.00 $300.00
Furnish,install,maintain,
and remove Type D inlet
2856 protection,complete as Each
specified
68.00 51.00 -17.00 $90.00 ($1,530.00)
Furnish,install,maintain,
2862 and remove stone bag, Each
complete as specified
25.00 0.00 -25.00 $12.00 ($300.00)
SECTION II-(BID ITEMS 2014-2862)-SUB-TOTALS $9,747.83 ($1,830.00)
NET INCREASE TO: SECTION II $7,917.83
SECTION III-SANITARY SEWER
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Furnish and install 10"
3002 sanitary sewer relay, Linear
complete as specified Feet
65.00 102.00 37.00 $55.85 $2,066.45
Furnish and install 18"
3008 sanitary sewer relay, Linear
complete as specified Feet
25.00 20.00 -5.00 $433.00 ($2,165.00)
Furnish and install 21"
3010 sanitary sewer relay, Linear
complete as specified Feet
15.00 10.00 -5.00 $482.00 ($2,410.00)
Furnish and install external
manhole chimney seal,
3114 complete as specified Each
3.00 0.00 -3.00 $340.00 ($1,020.00)
Furnish and install internal
manhole chimney seal,
3118 complete as specified Each
25.00 23.00 -2.00 $270.00 ($540.00)
Furnish and install 10"x 6"
3212 factory wyes or tees, Each
complete as specified
4.00 1.00 -3.00 $152.00 ($456.00)
Furnish and install 18"x 6"
3218 factory wyes or tees, Each
complete as specified
1.00 0.00 -1.00 $560.00 ($560.00)
Furnish and install 21"x6"
3219 factory wyes or tees, Linear
complete as specified Feet
1.00 0.00 -1.00 $930.00 ($930.00)
Furnish and install"Insert-A
3222 Tee"or"Kor-N-Seal", Each
complete as specified
2.00 3.00 1.00 $160.00 $160.00
Furnish and install 416"
3234 sanitary lateral relay, Linear
complete as specified Feet
30.00 25.00 -5.00 $105.00 _ ($525.00)
Page 3 of 4
CONTRACT:11-13 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Furnish and install sanitary
lateral marker balls,
3236 complete as specified Each
6.00 6.00 $28.00
Furnish and install
connections to existing 10"
3302 mains,complete as Each
specified
2.00 3.00 1.00 $150.00 $150.00
Furnish and install
connections to existing 18"
3308 mains,complete as Each
specified
3.00 0.00 -3.00 $390.00 ($1,170.00)
Furnish and install
connections to existing 21"
3310 mains,complete as Each
specified
2.00 0.00 -2.00 $665.00 ($1,330.00)
Furnish and install concrete
3330 collars,complete as Each
specified 2.00 2.00 $700.00
Core into existing manhole,
3332 complete as specified Each
1.00 1.00 $400.00
Televise sanitary sewer, Linear
3700 complete as specified Feet
85.00 85.00 $4.35
SECTION III: (BID ITEMS 3002-3700)-SUB-TOTALS $2,376.45 ($11,106.00)
ADDITIONAL WORK REQUIRED: C.O.#1-SECTION III
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Furnish labor,materials,
and equipment to install
storm,sanitary,and water
30000 lateral to 1227 High
Avenue,to eliminate
sanitary sewer main in
back yard,complete as Limp
specified Sum 0.00 1.00 1.00 $9,832.41 $9,832.41
ADDITIONAL WORK: C.0.#1-(ITEM 30000)-SUB-TOTAL $9,832.41 $0.00
NET INCREASE TO: SECTION III $1,102.86
NET INCREASE TO SECTIONS I,II,III $140,508.27
NET DECREASE TO SECTIONS I,II,III ($53,338.14)
NET INCREASE TO CONTRACT: $87,170.13