HomeMy WebLinkAboutPW CNT 11-06/CHG1 DEPARTMENT OF PUBLIC WORKS
215 Church Avenue
P.O.Box 1130
Oshkosh,Wisconsin 54903-1130
Ph.(920)236-5065 OJHKOJH
Fax(920)236-5068
ON THE WATER
f +
January 12, 2012
Bill Ulman
Fischer-Ulman Construction Inc.
1115 South Theodore Street
Appleton, WI 54915
Re: Change Order No. 1
Contract 11-06
Dear Mr. Ulman:
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and Fischer-Ulman
Construction Inc. regarding the above-mentioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
c P,Ocri-Ab
David C. Patek
Director of Public Works
DCP/tlt
Enclosure: Change Order No. 1
cc: Pam Ubrig, City Clerk(w/original)
Lynn Lorenson, City Attorney (w/copy) D E L II V 2
File (w/original) lI L
JAN 12 2012
CITY KS OFFICE
I:\Engineering\11-06 Concrete Sidewalk-Rehab&New\Project_Information\Contract Info\CHANGE ORDERS\11-06 Page 1 of 1
Executed Change Order#1 Letter_I-12-12.doc
CHANGE ORDER# 1
DATED: December 13, 2011
TO: Fischer-Ulman Construction Inc.
1115 S Theodore St
Appleton WI 54915
Your present contract with the City of Oshkosh, Contract No. 11-06 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION I - CONCRETE SIDEWALK $8,867.98
NET DECREASE TO: SECTION II -STORM SEWER ($17,480.00)
NET DECREASE TO CONTRACT: ($8,612.02)
CITY OF OSHKOSH
BY: D,--
Recommended: City Manager---)1 -) i `r
Director of Public Works City Clerk ✓'
l
A•proved and ac epted:
N '' ► f J& —
C ntractor
rschay- LWr co4ictracfio 1
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
" comptroller
App kved as to form:
M V�� 1
I CAL 11 #.
City Atto
CONTRACT 11-06 CHANGE ORDER#1
SECTION I-CONCRETE SIDEWALK
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
100 Mobilization&construction
of temporary access for W.
9th Avenue sidewalk
construction,complete as Lump
specified Sum 1 0.00 -1.00 $1,500.00 ($1,500.00)
101 Sidewalk removal&
driveway removal,
complete as specified Square
Feet 90,500 118,004.88 27,504.88 $0.43 $11,827.10
102 Concrete/asphalt sawing,
complete as specified Linear
Feet 5,500 5,334.10 -165.90 $2.00 ($331.80)
103 Construct 4"thick concrete
sidewalk in various
locations in the City of
Oshkosh,complete as Square
specified Feet 97,100 94,167.63 -2,932.37 $2.89 ($8,474.55)
104 Construct 6"thick concrete
sidewalk in various
locations in the City of
Oshkosh, complete as Square
specified Feet 14,500 18,046.81 3,546.81 $3.17 $11,243.39
105 Construct 7"thick
crosswalk areas,complete Square
as specified Feet 3,000 3,240.78 240.78 $3.30 $794.57
106 Provide and install metal
detectable warning plates, Square
complete as specified Feet 216 288.00 72.00 $25.00 $1,800.00
107 Three(3")inch asphalt
replacement,complete as Square
specified Feet 1,500 1,047.00 -453.00 $3.70 ($1,676.10)
108 Curb and gutter removal, Linear
complete as specified Feet 300 363.40 63.40 $3.00 $190.20
109 Construct 30"curb and
gutter,complete as Linear
specified Feet 300 396.80 96.80 $18.80 $1,819.84
110 Terrace restoration,
including seed,fertilizer,
and mulch, complete as Square
specified Yards 2,750 344.03 -2,405.97 $4.00 ($9,623.88)
111 Furnish and install
pavement ties,complete as
specified Each 100 105.00 5.00 $5.00 $25.00
112 Construct 4"thick concrete
sidewalk in Water Dept.
repair locations at approx.
60 sites, complete as
specified Square
Feet 1,500 1,473.38 -26.62 $4.15 ($110.47)
Page 1 of 5
CONTRACT 11-06 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
113 Construct 6"thick concrete
sidewalk in Water Dept.
repair locations at approx.
20 sites,complete as
specified Square
Feet 500 914.14 414.14 $4.30 $1,780.80
114 7"non-reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 75 0.00 -75.00 $41.40
($3,105.00)
115 8"non-reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 1,750 182.89 -1,567.11 $42.15 ($66,053.69)
116 8"special High Early
Strength, non-reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb and grading,terracing
and traffic control, Square
complete as specified Yards 100 20.63 -79.37 $48.50 ($3,849.45)
117 Extra crushed stone base,
complete as specified Tons 300 27.00 -273.00 $13.00 ($3,549.00)
118 No.4 epoxy-coated
reinforcement rods,
installed as specified Linear
Feet 520 1,700.00 1,180.00 $1.50 $1,770.00
119 Construct 12"wide radius
curb head,complete as Linear
specified Feet 75 60.00 -15.00 $4.00 ($60.00)
120 Furnish, install,and
maintain erosion mat, Square
complete as specified Yards 2,500 0.00 -2,500.00 $1.10
($2,750.00)
121 Profile sawcut concrete
curb,complete as specified Linear
Feet 50 0.00 -50.00 $26.00 ($1,300.00)
122 Sidewalk curb,complete as Linear
specified Feet 40 0.00 -40.00 $40.00 ($1,600.00)
123 Adjust manholes and inlets,
complete as specified
Each 2 0.00 -2.00 $200.00 ($400.00)
124 Remove trees and stumps,
complete as specified Inch
Diameter 92 0.00 -92.00_ $12.00_ ($1,104.00)
SECTION I-(BID ITEMS 100-124)-SUB-TOTALS $31,250.90 ($105,487.94)
Page 2 of 5
CONTRACT 11-06 CHANGE ORDER#1
ADDITIONAL WORK REQUIRED: C.O.#1 -SECTION I
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
125 7"/7-bag non-reinforced
concrete removal&
replacement, including
sawing,pavement ties,
intregral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 74.23 74.23 $43.60 $3,236.43
126 7Y8-bag non-reinforced
concrete removal&
replacement, including
sawing, pavement ties,
intregral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 0.00 $45.80
127 8"/7-bag non-reinforced
concrete removal&
replacement, including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 1,222.96 1,222.96 $45.25 $55,338.94
128 8'/8-bag non-reinforced
concrete removal&
replacement, including
sawing, pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 125.23 125.23 $46.04 $5,765.59
129 9'/7-bag non-reinforced
concrete removal&
replacement, including
sawing, pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 157.30 157.30 $47.60 $7,487.48
130 9"/8-bag non-reinforced
concrete removal&
replacement, including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Yards 0.00 100.37 100.37 $49.82 $5,000.43
131 7"/6-bag non-reinforced
concrete removal&
replacement, including
sawing, pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Feet 0.00 533.61 533.61 $4.78 $2,550.66
Page 3 of 5
CONTRACT 11-06 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
132 8"19-bag non-reinforced
concrete removal&
replacement, including
sawing,pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Feet 0.00 84.00 84.00 $5.72 $480.48
133 Adjust Manhole,complete
as specified Each 0.00 1.00 1.00 $100.00 $100.00
134 Repair Water Patch,
complete as specified Each 0.00 1.00 1.00 $50.00 $50.00
135 5"/7-bag non-reinforced
concrete removal&
replacement, including
sawing, pavement ties,
integral curb&grading,
terracing&traffic control, Square
complete as specified Feet 0.00 226.24 226.24 $4.84 $1,095.00
136 Sign Usage for Jackson
Street bridge pavement
repair
Each 0.00 1.00 1.00 $2,000.00 $2,000.00
ADDITIONAL WORK: C.O.#1 -(ITEMS 125-136)-SUB-TOTAL $83,105.02 $0.00
NET INCREASE TO: SECTION I $8,867.98
SECTION II-STORM SEWER
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
2032 Furnish and install 8"Storm
Sewer,complete as
specified Linear
Feet 6.00 0.00 -6.00 $45.00 ($270.00)
2036 Furnish and install 12"
Storm Sewer with endwalls,
complete as specified Linear
Feet 60.00 0.00 -60.00 $48.00 ($2,880.00)
2042 Furnish and install 15"
Storm Sewer with endwalls,
complete as specified Linear
Feet 60.00 0.00 -60.00 $55.00 ($3,300.00)
2300 Furnish and install 12"RCP
Class Ill apron end walls
with joint ties,complete as
specified
Each 6.00 0.00 -6.00 $650.00 ($3,900.00)
2302 Furnish and install 15"RCP
Class Ill apron end walls
with joint ties,complete as
specified Each 4.00 0.00 -4.00 $700.00 ($2,800.00)
Page 4 of 5
CONTRACT 11-06 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
2532 Furnish and install Std.
Storm Manhole(4'inside
diameter)in one location
with casting,complete as
specified Each 1.00 0.00 -1.00 $1,750.00 ($1,750.00)
2610 Furnish and install Type I
Inlet/with sump in one
location with casting,
complete as specified Each 1.00 0.00 -1.00 $1,300.00 ($1,300.00)
2854 Furnish, install, and
maintain Type"C"inlet
protection,complete as
specified Each 5.00 0.00 -5.00 $40.00 ($200.00)
2856 Furnish, install, and
maintain Type"D"inlet
protection std.,complete as
specified Each 74.00 67.00 -7.00 $40.00 ($280.00)
2868 Furnish, install, and
maintain ditch checks,
complete as specified Each 8.00 0.00 -8.00 $100.00
($800.00)
SECTION II-(BID ITEMS 2032-2868)-SUB-TOTALS $0.00 ($17,480.00)
NET DECREASE TO: SECTION II ($17,480.00)
NET INCREASE TO SECTIONS I&II $114,355.92
NET DECREASE TO SECTIONS I&II ($122,967.94)
NET DECREASE TO CONTRACT: ($8,612.02)
Page 5 of 5