HomeMy WebLinkAbout11-535
DECEMBER 13, 2011 11-535 RESOLUTION
(CARRIED__7-0_____ LOST _______ LAID OVER _______ WITHDRAWN _______)
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 09-21 WITH BUTEYN-PETERSON
CONSTRUCTION CO. INC. FOR THE OAKWOOD ROAD
STORMWATER FACILITIES (+$7,593.49)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
BUTEYN-PETERSON CONSTRUCTION CO. INC.
N7337 DAIRYLAND DR
SHEBOYGAN, WI 53083
Net Increase to Contract: $7,593.49
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 561-2010-1799-00000 Storm Water Utility Constr. Work in Progress
OfHKOJH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: December 8, 2011
RE: Change Order#1 for Public Works Contract No. 09-21
Buteyn-Peterson Construction Co., Inc. for Oakwood Road Storm Water Facilities ($7,593.49)
BACKGROUND
Change Order #1 for Contract 09-21 is scheduled for consideration by the Common Council at the December
13, 2011 meeting. The contract was originally awarded to Buteyn-Peterson Construction Co., Inc. in September
of 2009. This change order is for additional work required to complete the project and finalizes the quantities.
ANALYSIS
Through the course of constructing the project, additional pavement removal and replacement was required in
order to produce a quality finished project. This increase in pavement removal and replacement resulted in a
small increase in the paving costs of the project. The increase in storm sewer cost of the project was due to the
high ground water levels experienced during the wet construction season. The high ground water levels
required the construction of an additional dewatering well, and the replacement of a portion of the clay liner that
failed due to ground water pressure.
FISCAL IMPACT
Contract Section Change Order Amount CIP Budget Amount New Contract Total
Paving $2,259.38 $50,158.68
Storm Sewer $5,334.11 $344,251.52
Total $7,593.49 $394,410.20
The entire contract is being paid for by the Storm Water Utility. This project was funded with money available
due to several other project bids coming in well under budget in 2009. Therefore, the project did not appear in a
CIP budget. There is adequate funding available in the Capital Improvements Budget.
RECOMMENDATIONS
I recommend approval of the Change Order #1 to Contact No. 09-21 in the amount of $7,593.49 for Buteyn-
Peterson Construction Co., Inc.
Respectfully Submitted, Approved:
Steven M. Gohde Mark A. Rohioff
Asst. Director of Public Works City Manager
SMG/tIt
I:\Engineering\09-21 Oakwood Rd Storm Water Facility\Project_Information\Correspondence\Memo\09-21 CO#1 Council Memo_12-8-I I doc
CHANGE ORDER# 1
DATED: November 29, 2011
TO: BUTEYN-PETERSON CONSTRUCTION CO., INC.
N7337 DAIRYLAND DR
SHEBOYGAN WI 53083
Your present contract with the City of Oshkosh, Contract No. 09-21 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION I -CONCRETE PAVING $2,259.38
NET INCREASE TO: SECTION II -STORM SEWER $5,334.11
NET INCREASE TO CONTRACT: $7,593.49
CITY OF OSHKOSH
BY:
Recommended: City Manager
Director of Public Works City Clerk
Approved and accepted:
Cs'tractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
- CONTRACT:09-21 CHANGE ORDER#1
SECTION I-CONCRETE PAVING
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
100. Pavement Removal Square
Yards 925.00 922.50 -2.50 $6.22 ($15.55)
101. Driveway Removal Square
Yards 50.00 78.80 28.80 $16.42 $472.90
102. 8"Concrete Pavement Square
Including Integral Curb Yards 925.00 922.50 -2.50 $40.47 ($101.18)
103. Asphalt Driveway Square
Yards 50.00 78.80 28.80 $46.30 $1,333.44
104. Furnish&Install Terrace Square
Seed,Fertilizer,and Yards
Erosion Mat 545.00 742.15 197.15 $2.89 $569.76
SECTION I-(BID ITEMS 100-104)-SUB-TOTALS $2,376.10 ($116.73)
NET INCREASE TO: SECTION I $2,259.38
SECTION II-STORM SEWER
DESCRIPTION INCREASE IN DECREASE IN
ITEM UNIT BID INSTALLED NET NET UNIT CONTRACT CONTRACT
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Mobilization Lump
200. Sum 1.00 1.00 $18,683.00
Furnish,Install,Maintain, Linear
201. and Remove Silt Fence Feet 2,400.00 2,400.00 $2.13
Furnish, Install,Maintain,
202. and Remove Inlet Each . 11.00 11.00 $100.00
Protection
Furnish,Install,Maintain,
203. and Remove Tracking Pad Each 1.00 1.00 $986.00
Strip and Stockpile Topsoil Square
204. Yards 27,860.00 27,860.00 $0.32
Excavation of Detention
205. Basin Sump 1.00 1.00 $144,252.00
Import Clay Material Cubic
206. Yards 12,285.00 0.00 -12,285.00 $0.01 ($122.85)
Install Clay Liner Lump
207. Sum 1.00 1.00 $7,985.00
Furnish&Install Medium Square
208. Riprap and Filter Fabric Yards 260.00 285.00 25.00 $20.39 $509.75
Abandon Storm Sewer Linear
209. Feet 439.00 439.00 $33.35
Furnish&Install 29"x45" Linear
210. HERCP Class HE-III Storm Feet 652.00 631.00 -21.00 $82.98 ($1,742.58)
Sewer
Furnish&Install 29"x45"
211. HERCP Apron Endwall w! Each 1.00 1.00 $1,582.00
Grate
Page 1 of 2
CONTRACT:09-21 CHANGE ORDER#1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
Furnish&Install Outlet
212. Structure Each 1.00 1.00 $15,120.00
Furnish&Install Manholes Vertical
213. Feet 12.50 12.72 0.22 $435.20 $95.74
Furnish&Install Inlet Vertical
214. Maholes Feet 15.20 15.36 0.16 $431.98 $69.12
Furnish&Install Standard
215. Type 3 Inlet with 18"Sump Each 1.00 1.00 $1,200.00
Install Salvaged Topsoil- Square
216. 6"Depth Yards 14,020.00 14,020.00 $0.26
Install Salvaged Topsoil- Square
217. 12"Depth Yards 5,100.00 5,100.00 $0.52
Haul Excess Topsoil Cubic
218. Yards 4,220.00 4,220.00 $0.53
Furnish&Install Erosion Square
219. Mat Type 1,Class A Yards 7,125.00 7,054.40 -70.60 $0.85 ($60.01)
Furnish&Install Wetland Square
220. Plantings Yards 2,815.00 2,815.00 $7.50
Furnish&Install Native Square
221. Seeding and Mulch Yards 11,450.00 10,448.00 -1,002.00 $0.79 ($791.58)
Furnish&Install No-Mow Square
222. Fescue Seeding,Mulch, Yards 2,860.00 3,193.20 333.20 $1.07 $356.52
and Fertilizer
SECTION II-(BID ITEMS 200-222)-SUB-TOTALS $1,031.13 ($2,717.02)
ADDITIONAL WORK REQUIRED: C.O.#1 - SECTION II
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
223 Furnish&install Each
Permanent De-watering
Well,Re-compact failed
liner area due to
groundwater,Controlled fill
of detention basin. 0.00 1.00 1.00 $7,020.00 $7,020.00
ADDITIONAL WORK:C.O.#1 -(ITEM 223)-SUB-TOTAL $7,020.00 $0.00
NET INCREASE TO: SECTION II $5,334.11
NET INCREASE TO SECTIONS I,II $10,427.23
NET DECREASE TO SECTIONS I,II ($2,833.75)
NET INCREASE TO CONTRACT: $7,593.49
Page 2 of 2