HomeMy WebLinkAboutPW CNT 11-04/CNG 1 DEPARTMENT OF PUBLIC WORKS
215 Church Avenue
P.O. Box 1130
Oshkosh, Wisconsin 54903 -1130
Fa. (920) 236 -5065 OfHKOJ
Fax (920) 236-5068
ON THE WATER
September 29, 2011
Mr. Mike LaLonde
LaLonde Contractors, Inc.
P.O. Box 070420
Milwaukee, WI 54307 -0420
Re: Change Order No. 1
Contract 11 -04
Dear Mr. LaLonde:
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and LaLonde
Contractors, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920)236 -5065.
Sincerely,
David C. Patek
Director of Public Works
DCP /tlt
Enclosure: Change Order No. 1
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, Assistant City Attorney (w /copy)
File (w /original)
1:1Engineering \I I -04 Concrete Paving and Utilities Northeast \Project_Infonnalion \Contract Info \CHANGE ORDERS \I1 - Page 1 of 1
04 Executed Change Order #1 Letter_9 -29 -1 I.doc
CHANGE ORDER # 1
DATED: August 12, 2011
TO: Lalonde Contractors, Inc.
P.O. Box 070420
Milwaukee, WI 54307 -0420
Your present contract with the City of Oshkosh, Contract No. 11 -04 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION I - CONCRETE PAVING $11,824.56
NET INCREASE TO: SECTION II - STORM SEWER $38,430.97
NET INCREASE TO: SECTION III - SANITARY SEWER $31,135.99
NET INCREASE TO: SECTION IV - WATER MAIN $45,134.07
NET INCREASE TO CONTRACT: $126,525.59
CITY OF OSHKOSH �f
BY: r a� �%' - -Z�-?" �'"
Recommended: City Manager_-_
(.&
Director of Public Works City Clerk
Approved and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Pe-4 40— v
-CtSmptroller
Ap oved as to fort :
I
City Attorney
CONTRACT: 11 -04 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER
DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
10000 Additional labor, materials,
and equipment to furnish
and install cold mix patch
in the Pearl & Osceola
intersection, due to the
delay in storm sewer
construction, per Invoice
(004) dated 4/27/11, Lump
complete as specified Sum 0.00 1.00 1.00 $2,104.56 $2,104.56
10001 Additional price increase to
do hand work paving on
Osceola Street due to
change of width from UW-
O Fiber duct package in
conflict, per Invoice (030)
dated 7/11/11, complete as Square
specified Yards 0.00 1,215.00 1,215.00 $8.00 59,720.00
10002 Additional Days added to
the completion date due to
extra work and delays Days 0.00 21.00 21.00 $0.00 $0.00
ADDITIONAL WORK: C.O. # 1 - (ITEMS 10000 - 10001) - SUB -TOTAL $11,824.56 $0.00
NET INCREASE TO: SECTION I $11,824.56
SECTION II - STORM SEWER
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION II
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
2862 Furnish, install, maintain,
and remove stone bags
per Invoice (003) dated
4/18/11, complete as
specified Each 0.00 33.00 33.00 $65.05 $2,146.65
20000 Additional labor, materials,
and equipment to core two
12 -inch holes into MH P -10
to match field conditions,
per Invoice (002) dated
4/27/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,192.64 $1,192.64
20001 Additional labor, materials,
and equipment to remove
a poured in place concrete
structure and repair the
existing storm sewer
manhole on Osceola , per
Invoice (006) dated 5/9/11, Lump
complete as specified Sum 0.00 1.00 1.00 $1,989.50 $1,989.50
Page 1 of 6
CONTRACT: 11 -04 CHANGE ORDER # 1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
20002 Additional labor, materials,
and equipment to excavate
and re- connect to an
existing storm lateral.
Upon further investigation,
it was determined that the
lateral was never installed
and the hole was backfilled
with gravel, per Invoice
(006) dated 5/9/11,
complete as specified Lump
Sum 0.00 1.00 1.00 $2,155.35 $2,155.35
20003 Additional labor, materials,
and equipment to re- install
two storm inlets that were
staked incorrectly, per
Invoice (012) dated
5/24/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,925.57 $1,925.57
20004 Additional labor, materials,
and equipment to remove
an unknown buried
concrete foundation and
storm sewer on Osceola
Street, per Invoice (014)
dated 6/21/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,962.36 $1,962.36
20005 Additional labor, materials,
and equipment to
temporarily connect to
existing 42 -inch storm
sewer, after the storm
sewer installation was put
on hold due to UW-
Oshkosh fiber conflict, per
Invoice (015) dated
6/21/11, complete as Lump
specified Sum 0.00 1.00 1.00 $3,702.02 $3,702.02
20006 Additional labor, materials,
and equipment to raise the
proposed 3'x6' box culvert
over the UW- Oshkosh
steam tunnel that was in
conflict, per Invoice (019)
dated 6/21/11, complete as Lump
specified Sum 0.00 1.00 1.00 $5,564.85 $5,564.85
20007 Additional labor, materials,
and equipment to install 48-
inch storm sewer and inlets
on Osceola Street that
were in conflict with the
UW- Oshkosh fiber duct
package. Osceola was
ultimately narrowed to
allow inlets to be installed,
per Invoice (020) dated
6/21/11, complete as Lump
specified Sum 0.00 1.00 1.00 $6,684.38 $6,684.38
20008 Additional labor, materials,
and equipment to
permanently connect the 3'
x 6' box culvert to the
existing storm sewer after
the storm sewer box
culvert was eliminated from
the contract between
station 17 +25 and 20 +00,
per Invoice (022) dated
6/28/11, complete as Lump
specified Sum 0.00 1.00 1.00 $3,292.06 $3,292.06
Page 2 of 6
CONTRACT: 11 -04 CHANGE ORDER # 1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER
DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
20009 Additional labor, materials,
and equipment to remove
8- inches of mud from the
storm sewer due to the
water main break and
repair the storm sewer, per
Invoice (032) dated
7/15/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,614.49 $1,614.49
20010 Additional labor, materials,
and equipment to install a
storm lateral that was not
in the correct location
according to the plan.
Contractor had to re-
excavate in new location
and backfill original
location, per Invoice (034)
dated 7/19/11, complete as Lump
specified Sum 0.00 1.00 1.00 $820.20 $820.20
20011 Additional labor, materials,
and equipment to connect
the UW- Oshkosh Wellness
Center storm lateral to the
3'x6' box culvert. UW -O
told us that the lateral was
connected to an inlet
outside the building but it
was determined it was
connected to the
abandoned storm sewer
main. Contractor had to re-
mobilize to that area,
excavate, de- water, and re-
slurry the abandond storm
sewer, per Invoice (036)
dated 7/29/11, complete as
specified Lump
Sum 0.00 1.00 1.00 $5,380.90 $5,380.90
ADDITIONAL WORK: C.O. # 1 - (ITEMS 2862 - 20011) - SUB -TOTAL $38,430.97 $0.00
NET INCREASE TO: SECTION II $38,430.97
Page 3 of 6
CONTRACT: 11 -04 CHANGE ORDER # 1
SECTION 111 - SANITARY SEWER
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION III
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
PRICE PRICE
3815 Abandon 27 -inch sanitary
sewer, complete' as Linear
specified Feet 0.00 238.00 238.00 513.00 $3,094.00
30000 Additional labor, materials,
and equipment to move
and rebuild MH 0 -1, due to
existing 33 -inch sanitary
sewer being encased in
concrete, per lnvoice (001)
dated 4/27/11, complete as
specified Lump
Sum 0.00 1.00 1.00 $9,260.88 $9,260.88
30001 Additional labor, materials,
and equipment to core new
hole into MH 0 -2 to match
field conditions, and cap
new lateral that was shown
on plans, but was
abandoned, per Invoice
(005) dated 5/2/11, Lump
complete as specified Sum 0.00 1.00 1.00 $1,227.07 51,227.07
30002 Additional labor, materials,
and equipment to remove
concrete encased manhole
in front of Blackhawk
Commons, per Invoice
(007) dated 5/9/11, Lump
complete as specified Sum 0.00 1.00 1.00 $5,725.85 $5,725.85
30003 Additional labor, materials,
and equipment to break up
and dispose of concrete
encased sanitary/storm
manhole structure that was
excavated on 5/5/11, per
Invoice (010) dated
5/25/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,143.68 $1,143.68
30004 Additional labor, materials,
and equipment to remove
a poured in place sanitary
manhole on Algoma
Avenue, per Invoice (024)
dated 6/28/11, complete as Lump
specified Sum 0.00 1.00 1.00 $7,151.85 $7,151.85
30005 Construction crew down
time due to Gabe's
Construction air -
hammering the concrete
off AT &T's duct package
on Elmwood Avenue.
Sewer crew could not
install sanitary or storm
until Gabe's was complete
with their work, per Invoice
(027) dated 6/28/11, Lump
complete as specified Sum 0.00 1.00 1.00 $3,172.71 $3,172.71
30006 Additional labor, materials,
and equipment to use a
concrete buster to remove
encased concrete around
sanitary sewer manhole to
gain access, per Invoice
(028) dated 6/28/22, Lump
complete as specified Sum 0.00 1.00 1.00 $359.95 $359.95
ADDITIONAL WORK: C. 0. # 1 - (ITEMS 3815 - 30006) - SUB -TOTAL 531,135.99 $0.00
NET INCREASE TO: SECTION 111 $31,135.99
Page 4 of 6
CONTRACT: 11 -04 CHANGE ORDER # 1
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
40006 Additional labor, materials,
and equipment to install a
temporary water service to
the UW- Oshkosh Diversity
Center. Contractor was
told that the existing water
service was tapped off the
6 -inch fire protection lateral
and 4 -inch water lateral
was abandoned. It was
determined that the 2 -inch
service was connected to
the 4 -inch lateral, per
Invoice (025) dated
6/28/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,289.87 $1,289.87
40007 Additional labor, materials,
and equipment to repair a
watermain that was
improperly marked by the
utility locator, per Invoice
(031) dated 7/15/11, Lump
complete as specified Sum 0.00 1.00 1.00 $619.67 $619.67
40008 Additional labor, materials,
and equipment to repair a
unmarked watermain on
Irving Avenue, per Invoice
(026), dated 6/28/11, Lump
complete as specified Sum 0.00 1.00 1.00 $739.63 $739.63
40009 Additional labor, materials,
and equipment to repair a
watermain leak on
Elmwood Avenue, per
Invoice (033), dated
7/19/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,364.73 $1,364.73
ADDITIONAL WORK: C.O. # 1 (ITEMS 40000 - 40009) - SUB -TOTAL $45,134.07 $0.00
NET INCREASE TO: SECTION IV $45,134.07
NET INCREASE TO SECTIONS I, II, III, IV $126,525.59
NET DECREASE TO SECTIONS I, II, III, IV 50.00
NET INCREASE TO CONTRACT: $126,525.59
Page 6 of 6
CONTRACT: 11 -04 CHANGE ORDER # 1
SECTION IV - WATER MAIN
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
ITEM BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
PRICE PRICE
40000 Additional labor, materials,
and equipment to move
and install new 12 -inch
water main to match the
field conditions and avoid
conflicts with the proposed
sanitary and storm sewer
and the existing 20 -inch
watermain, per Invoice
(011) dated 5/24/11, Lump
complete as specified Sum 0.00 1.00 1.00 $11,588.81 $11,588.81
40001 Additional cost for installing
Megalugs on at bends and
fittings, per Involve (013)
dated 6/21/11, complete as
specified Lump
Sum 0.00 1.00 1.00 $17,914.70 $17,914.70
40002 Additional labor, materials,
and equipment to remove
fittings for tee and valve on
Elmwood Avenue at
Woodland Avenue, once it
was determined that there
was a conflict with re-
routed sanitary sewer, per
Invoice (016) dated
6/21/11, complete as Lump
specified Sum 0.00 1.0D 1.00 $1,247.18 81,247.18
40003 Additional labor, materials,
and equipment to offset
proposed water main on
Elmwood Avneue at
Woodland Avenue over
the exisitng storm that was
in conflict, per Invoice
(017) dated 6/21/11, Lump
complete as specified Sum 0.00 1.00 1.00 $1,870.76 $1,870.76
40004 Additional labor, materials,
and equipment to offset
proposed water main on
Elmwood Avenue at Vine
Avenue under the existing
storm sewer that was in
conflict, per Invoice (017)
dated 6/21/11, complete as Lump
specified Sum 0.00 1.00 1.00 $1,364.91 $1,364.91
40005 Additional labor, materials,
and equipment to re- install
watermain that was in
conflict with the UW-
Oshkosh fiber duct
package on Elmwood
Avenue between Amherst
Avenue and Irving Avenue,
per Invoice (023) dated
6/28/11, complete as Lump
specified Sum 0.00 1.00 1.00 $7,133.81 57,133.81
Page 5 of 6