HomeMy WebLinkAboutPW CNT 09-13/CNG 3 CITY OF OSHKOSH
DEPARTMENT OF PUBLIC WORKS
215 CHURCH AVENUE, P.O. BOX 1130, OSHKOSH, WI 54903 -1130
PHONE: (920) 236 -5065 FAX (920) 236 -5068
LETTER OF TRANSMITTAL
To: Mr. Jon Kleist Date: August 18, 2011
Buteyn- Peterson Construction Co. Subject: Signed Change Order No. 3
N7337 Dairyland Drive Contract 09 -13
Sheboygan, WI 53083
Please find: ® Attached ❑ Under Separate Cover
❑ Copy of Letter El Contracts ❑ Amendment ❑ Report ❑ Agenda
❑ Meeting Notes ❑ Photos ❑ Mylars ® Change Order ❑ Plans
❑ Specifications ❑ Estimates ❑ Diskette ❑ Zip Disk ❑ Other
Quantity Description
1 Signed Change Order No. 3
These are being transmitted as indicated below:
❑ For Approval ® For Your Use ❑ As Requested ❑ For Review & Comment
Remarks:
Enclosed is the signed Change Order No. 3 for City of Oshkosh Contract 09 -13.
If you have any questions, please contact us.
City Attorney's Office — Copy
City Clerk's Office — Original
cc: _File — Original Signed: j .„4 /A■
Tra Tayl.
I: \Engineering \09 -I3 Tipler Detention Basin\Projecl_In formation \ Correspondence \Transmillals \09 -13 LOT- Buleyn_Signed CO _8 -I8 -1 I.doc
CHANGE ORDER # 3
DATED: July 15, 2011
TO: Buteyn- Peterson Construction Co
N7337 Dairyland Drive
Sheboygan, WI 54083
Your present contract with the City of Oshkosh, Contract No. 09 -13 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - PAVING ($996.20)
NET DECREASE TO: SECTION II - STORM SEWER ($19,774.01)
NET DECREASE TO CONTRACT : ($20,770.21)
CITY OF OSHKOSH
BY:
Recommended: City Manager
� .a
Director of Public Works City Clerk
Approve. an. cepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
110b, ge_0410
troller
Ap• as to for
At V
10 A !" 'L... � 7--'
City t' e
Y Y
' CONTRACT: 09 -13 CHANGE ORDER # 3
SECTION I - PAVING
INCREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT DECREASE IN
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE CONTRACT PRICE
Excavation for track facility
and undercut in Bismarck
102 Avenue and Eagle Street, Cubic 70 0.00 -70.00 $12.62
complete as specified Yards ($883.40)
(Engineer's Estimate 620
CY)
6 -IN concrete sidewalk at Square
105 Barrier -Free Ramp, 640 624.00 -16.00 $15.60 ($249.60)
complete as specified Feet
SECTION I - (BID ITEM 102 -105) - SUB -TOTAL $0.00 ($1,133.00)
ADDITIONAL WORK REQUIRED: C.O. #3 - SECTION I
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT PRICE
PRICE
Sidewalk and Driveway
101 Removal, complete as Square 320 400.00 80.00 $1.71 $136.80
specified Feet
ADDITIONAL WORK REQUIRED: C.O. #3 - SECTION I $136.80 $0.00
NET DECREASE TO: SECTION I ($996.20)
SECTION II - STORM SEWER
INCREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT DECREASE IN
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE CONTRACT PRICE
Storm Sewer Marker Balls,
220 complete as specified Each 51 42.00 -9.00 $20.00 ($180.00)
Furnish, install, maintain Linear
222 and remove silt fence, Feet 595 500.00 -95.00 $1.20 ($114.00)
complete as specified
Erosion Control
226 Revegetative Mat (Class I, Square 55,035 52,544.00 - 2,491.00 $0.86
Type B), complete as Yard ($2,142.26)
specified
240 Maintenance Mowing, Each 10 4.00 -6.00 $200.00
complete as specified ($1,200.00)
Until turf is established
244 (City will supply hydrant Each Day 54 12.00 -42.00 $578.00 ($24,276.00)
water as requested)
SECTION II (BID ITEMS 220 - 244) $0.00 ($27,912.26)
Page 1 of 2
CONTRACT: 09 -13 CHANGE ORDER # 3
ADDITIONAL WORK REQUIRED: C.O. #3 SECTION 11
INCREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT DECREASE IN
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE CONTRACT PRICE
Temporary Construction
200 Fence, complete as Linear 1,900 2,243.00 343.00 $1.31 $449.33
specified Feet
Furnish and Install 12 -IN
209 RCP Class IV storm sewer, Linear 349 392.00 43.00 $47.70 $2,051.10
complete as specified Feet
Furnish and install 38 -IN x
210 60 IN HERCP Class III Linear 12 24.00 12.00 $261.04 $3,132.48
storm sewer w /joint ties, Feet
complete as specified
12 -IN PVC (C900) Pipe, Linear
212 complete as specified Feet 487 489.00 2.00 $26.22 $52.44
8 -IN PVC (C900) Pipe, Linear
213 complete as specified Feet 85 89.00 4.00 $19.90 $79.60
Furnish, install, maintain,
and remove Inlet Sediment
224 Control Protection, Type B, Each 15 17.00 2.00 $35.00 $70.00
complete as specified
Furnish, install, maintain,
and remove Inlet Sediment
225 Control Protection, Type D, Each 20 25.00 5.00 $85.00 $425.00
complete as specified
Remove and Replace
238 Fence, complete as Linear 340 360.00 20.00 $6.54 $130.80
specified Feet
Furnish and install 15 inch Linear
242 PVC, complete as specified Foot 312 317.00 5.00 $43.10 $215.50
245 Remobilize and furnish and Linear 95.00 95.00 $10.00 $950.00
install 4" drain tile Foot 0
246 Re -seed area affected by Lump 1.00 1.00 $582.00 $582.00
sediment Sum 0
ADDITIONAL WORK REQUIRED: C.O. #3 SECTION II $8,138.25 $0.00
NET DECREASE TO: SECTION II ($19,774.01)
NET INCREASE TO SECTIONS I & II $8,275.05
NET DECREASE TO SECTION I & II ($29,045.26)
NET DECREASE TO CONTRACT 9 -13 ($20,770.21)
Page 2 of 2