March 9, 2011
Mr. Glen Joski
Advance Construction, Inc.
2141 Woodale Avenue
Green Bay, WI 54313
Re: Change Order #1 /Contract 10 -04
Dear Mr. Joski:
Enclosed please find an executed copy of the Change Order between the City of Oshkosh and Advance
Construction regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
0624' of C . l David C. C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original) 4148 1 O
Lynn Lorenson, Assistant City Attorney (w /copy) 20/f
File Copy (w /original)
1:\Engineering110 -04 Concrete Paving \Project_ Information \Contract Info \CHANGE Page 1 of 1
ORDERS110 -04 Change Order Letter #1.doc
CHANGE ORDER # 1
DATED: February 9, 2011
TO: Advance Construction Inc.
2141 Woodale Avenue
Green Bay WI 54313
Your present contract with the City of Oshkosh, Contract No. 10 -04 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION I - CONCRETE PAVING $79,083.81
NET DECREASE TO: SECTION II - STORM SEWER ($21,410.60)
NET INCREASE TO: SECTION III - SANITARY SEWER $19,780.53
NET INCREASE TO: SECTION IV - WATER MAIN $52,230.18
NET INCREASE TO CONTRACT: $129,683.92
CITY OF OSHKOSH
BY: -1�¢ SH
Recommended: City Manager ; , ,
-‘-i,i,;(1 Cd. 494k , ) Director of Public Works City Clerk / (,)
Approved an. - - - • =•:
Contractor
certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
P12/41(d Yekt9
11 Comptroller
AID. •ved as to form
( , 1L. 1 A i4��� A
\�- 1 C ity Atto7-11r
CONTRACT: 10 -04 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER
DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
100 Pavement removal, . Square
complete as specified Yards 4,970 5,379.20 409.20 $3.00 $1,227.60
101 Sidewalk and driveway
removal, complete as Square
specified Feet 41,630 44,193.00 2,563.00 $0.50 $1,281.50
102 Excavation, complete as Cubic
specified Yards 15,290 17,980.80 2,690.80 $6.20 $16,682.96
103 7" non - reinforced concrete
pavement, including
integral curb, 5" base
material and grading, Square
complete as specified Yards 27,875 27,944.00 69.00 $26.75 $1,845.75
104 8" concrete pavement,
HES, including integral curb
and 6" base material and
grading, complete as Square
specified Yards 1,745 1,983.20 238.20 $35.27 $8,401.31
105 12" wide radius curb head,
complete as specified Linear
Feet 1,625 1,866.30 241.30 $12.00 $2,895.60
106 Standard 24" curb & gutter,
7" (tie -in), complete as Linear
specified Feet 32 210.00 178.00 $25.00 $4,450.00
107 Standard 30" curb & gutter,
7" (tie -in), complete as Linear
specified Feet 240 134.50 - 105.50 $25.00 ($2,637.50)
108 Sidewalk curb, complete as Linear
specified Feet 200 60.20 - 139.80 $18.00 ($2,516.40)
109 4" concrete sidewalk, Square
complete as specified Feet 22,520 23,946.00 1,426.00 $3.03 $4,320.78
110 6" concrete sidewalk &
driveway, complete as Square
specified Feet 31,555 28,692.30 - 2,862.70 $3.18 ($9,103.39)
111 3 1 /2" asphaltic concrete
driveway, complete as Square
specified Feet 95 940.30 845.30 $3.91 $3,305.12
112 2" Asphaltic concrete
transition with base and
asphaltic curb, complete as Square
specified Yards 370 243.00 - 127.00 $17.75 ($2,254.25)
113 3 A" asphaltic concrete
transition, with base, Square
complete as specified Yard 860 1,371.50 511.50 $34.85 $17,825.78
114 Furnish and install crushed
stone base course,
complete as specified
Tons 4,590 6,277.00 1,687.00 $7.77 $13,107.99
115 Sawing, complete as Linear
specified Feet 2,400 2,424.20 24.20 $1.65 $39.93
116 Furnish and install
pavement ties (epoxy
coated), complete as
specified Each 460 376.00 -84.00 $6.00 ($504.00)
117 Adjust manholes and inlets,
complete as specified
Each 241 229.00 -12.00 $250.00 _ ($3,000.00)
Page 1 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
118 Furnish and install No. 4
reinforcing bars (epoxy
coated), complete as Linear
specified Feet 660 210.00 - 450.00 $1.00 ($450.00)
119 Remove trees and stumps,
complete as specified Inch
Diameter 270 238.20 -31.80 $22.00 ($699.60)
120 Furnish and install trees,
complete as specified Each 12 9.00 -3.00 $220.00 ($660.00)
121 Provide and install metal
detectable warning plates,
complete as specified Square
Feet 680 792.00 112,00 $27.00 $3,024.00
122 Terrace work on Broad
Street, complete as
specified Lump Sum 1 1.00 $5,345.00
123 Terrace work on Grand
Street, complete as
specified Lump Sum 1 1.00 $8,600.00
124 Terrace work on E. Melvin
Avenue, complete as
specified Lump Sum 1 1.00 $17,000.00
125 Terrace work on Ostertag
Place, complete as
specified Lump Sum 1 1.00 $150.00
126 Terrace work on Powers
Street, complete as
specified Lump Sum 1 1.00 $9,750.00
127 Terrace work on Rock
Place, complete as
specified Lump Sum 1 1.00 $600.00
128 Terrace work on E.
Tennessee Avenue,
complete as specified Lump Sum 1 1.00 $1,750.00
SECTION I - (BID ITEMS 100 - 128) - SUB - TOTALS $78,408.32 ($21,825.14)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
129 Haul contaminated soil per
contract supplement,
complete as specified Tons 0.00 589.10 589.10 $12.00 $7,069.20
130 8" concrete sidewalk and
driveways and 6" base
material and grading, Square
complete as specified Yards 0.00 61.53 61.53 $35.27 $2,170.16
131 7" concrete pavement,
HES, including integral curb
and 6" base material and
grading, complete as Square
specified Yards 0.00 241.70 241.70 $35.81 $8,655.28
132 Furnish and install 3" clear
stone breaker run used in
undercut areas, complete
as specified Tons 0.00 175.40 175.40 $15.29 $2,681.87
Page 2 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
133 Furnish and install 5" hot
mix asphaltic pavement, Square
complete as specified Yards 0.00 12.40 12.40 $52.60 $652.24
134 Remove additional
concrete sidewalk to realign
sidewalk by Sub - Contractor
per Inspector's orders,
complete as specified Square
Feet 0.00 152.50 152.50 $0.75 $114.38
135 Additional landscaping
beyond the project limits, Lump
complete as specified Sum 0.00 1.00 1.00 $223.00 $223.00
136 Added hot water to
concrete mix at batch plant
due to late season
installation, complete as Lump
specified Sum 0.00 1.00 1.00 $934.50 $934.50
137 Additional days added to
contract for various
additional work per letter
dated July 6, 2010 Days 0.00 0.00 12.00 $0.00 _
ADDITIONAL WORK: C.O. # 1 - (ITEMS 129 - 136) - SUB -TOTAL $22,500.63 $0.00
NET INCREASE TO: SECTION I $79,083.81
SECTION II - STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
200 Furnish and install 12"
storm sewer, complete as Linear
specified Feet 1,824 1982.30 158.30 $45.50 $7,202.65
201 Furnish and install 15"
storm sewer, complete as Linear
specified Feet 2,248 2129.00 - 119.00 $45.50 ($5,414.50)
202 Furnish and install 18"
storm sewer, complete as Linear
specified Feet 508 487.50 -20.50 $46.85 ($960.43)
203 Furnish and install 21"
storm sewer, complete as Linear
specified Feet 919 880.90 -38.10 $49.50 ($1,885.95)
204 Furnish and install 24"
storm sewer, complete as Linear
specified Feet 580 422.50 - 157.50 $51.40 ($8,095.50)
205 Furnish and install 36"
storm sewer, complete as Linear
specified Feet 570 524.60 -45.40 $66.60 ($3,023.64)
206 Furnish and install 42"
storm sewer, complete as Linear
specified Feet 616 568.50 -47.50 $77.60 ($3,686.00)
207 Furnish and install 48"
storm sewer, complete as Linear
specified Feet 222 206.30 -15.70 $93.10 ($1,461.67)
Page 3 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
208 Furnish and install 48" RCP
Class 111 storm sewer,
complete as specified Linear
Feet 59 74.00 15.00 $93.10 $1,396.50
209 Furnish and install 38" x
60" RCP Class 111 storm
sewer, complete as Linear
specified Feet 274 228.10 -45.90 $112.15 ($5,147.69)
210 Furnish and install 48" x
76" RCP Class III storm
sewer, complete as Linear
specified Feet 453 438.40 -14.60 $151.85 ($2,217.01)
211 Furnish and install 4' x 6'
box culvert storm sewer, Linear
complete as specified Feet 1,150 1134.20 -15.80 $218.35 ($3,449.93)
212 Furnish and install 4' x 8'
box culvert storm sewer, Linear
complete as specified Feet 997 980.20 -16.80 $304.00 ($5,107.20)
213 Furnish and install 4' x 6'
box culvert storm sewer
w /manhole riser, complete Linear
as specified Feet 72 60.00 -12.00 $218.35 ($2,620.20)
214 Furnish and install 4' x 8'
box culvert storm sewer
w /manhole riser, complete Linear
as specified Feet 48 63.00 15.00 $304.00 $4,560.00
215 Furnish and install 66" steel
casing pipe, complete as Linear
specified Feet 59 60.00 1.00 $1,100.00 $1,100.00
216 Furnish and install std.
inlets (type 3 with 18"
sump) with castings,
complete as specified Each 102 102.00 $1,400.00
217 Furnish and install std.
inlets (type 3 with no sump)
with castings, complete as
specified Each 3 4.00 1.00 $1,330.00 $1,330.00
218 Furnish and install std.
Storm manhole (4' inside
diameter) in 4 locations
without casting, complete Vertical
as specified Feet 121 117.42 -3.58 $170.00 ($608.60)
219 Furnish and install std.
storm manhole (5' Inside
diameter) in 3 locations
without casting, complete Vertical
as specified Feet 24 22.15 -1.85 $267.00 ($493.95)
220 Furnish and install std.
storm manhole (6' Inside
diameter) in 7 locations
without casting, complete Vertical
as specified Feet 50 50.00 $340.00
221 Furnish and install std.
storm box manhole (7' x 7')
in 1 location without
casting, complete as Vertical
specified Feet 10 28.37 18.37 $640.00 $11,756.80
Page 4 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
222 Furnish and install std.
storm manhole riser (4'
inside diameter) in 15
locations without casting, Vertical
complete as specified Feet 46 47.00 1.00 $116.00 $116.00
223 Furnish and install std.
storm inlet manhole (4'
inside diameter) in 2
locations with casting, Vertical
complete as specified Feet 8 8.67 0.67 $273.00 $182.91
224 Furnish and install std.
storm inlet manhole (5'
inside diameter) in 1
location with casting, Vertical
complete as specified Feet 7 6.00 -1.00 $320.00 ($320.00)
225 Furnish and install std.
storm box inlet manhole (7'
x 7') in 1 location with
casting, complete as Vertical
specified Feet 9 0.00 -9.00 $700.00 ($6,300.00)
226 Furnish and install std.
storm junction chambers
without casting, complete
as specified Each 6 6.00 $16,000.00
227 Furnish and install 6" storm
lateral, complete as Linear
specified Feet 3,908 3606.50 - 301.50 $38.00 ($11,457.00)
228 Furnish and install 8" storm
lateral, complete as Linear
specified Feet 26 36.00 10.00 $40.00 $400.00
229 Furnish and install storm
lateral marker balls,
complete as specified Each 290 283.00 -7.00 $13.00 ($91.00)
230 Abandon lineal feet of 8" -
12" storm sewer, complete Linear
as specified Feet 1,120 1100.00 -20.00 $3.00 ($60.00)
231 Abandon lineal feet of 15"
and larger storm sewer, Linear
complete as specified Feet 4,133 4100.00 -33.00 $5.00 ($165.00)
232 Abandon inlets or
manholes, complete as
specified Each 47 47.00 $250.00
233 Furnish, install, and
maintain Type "D" inlet
protection std., complete as
specified Each 271 192.00 -79.00 $75.00 ($5,925.00)
234 Furnish, install, and
maintain silt fence, Linear
complete as specified Feet 30 0.00 -30.00 $2.00 ($60.00)
235 Furnish, install, and
maintain stone bags,
complete as specified Each 5 0.00 -5.00 $8.00 ($40.00)
236 Utility line opening,
complete as specified Each 2 0.00 -2.00 $550.00 ($1,100.00)
SECTION II - (BID ITEMS 200 - 236) - SUB - TOTALS $28,044.86 ($69,690.27)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION II
Page 5 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE 1N DECREASE IN
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
237 Additional labor,
equipment, and materials to
install Type I inlet with 18"
sump, complete as Lump
specified Sum 0.00 1.00 1.00 $1,400.00 $1,400.00
238 Additional labor,
equipment, and materials to
repair 18" storm sewer on
Eastman St, complete as Lump
specified Sum 0.00 1.00 1.00 $2,222.18 $2,222.18
239 Additional labor,
equipment, and materials to
remove the rock
obstructions on the boring
of the railroad tracks on
Melvin Ave, complete as Lump
specified Sum 0.00 1.00 1.00 $3,901.37 $3,901.37
240 Additional labor,
equipment, and materials to
install clay dam at the
northeast corner of Melvin
Ave. and Grove St., Lump
complete as specified Sum 0.00 1.00 1.00 $3,086.16 $3,086.16
241 Additional labor,
equipment, and materials to
install clay dam through the
intersection of Melvin and
Grove, complete as Lump
specified Sum 0.00 1.00 1.00 $3,000.00 $3,000.00
242 Additional labor,
equipment, and materials to
install weir plate in MH M-
57 to prevent storm water
flow to allow completion of
storm water lift station,
complete as specified Lump
Sum 0.00 1.00 1.00 $925.10 $925.10
243 Additional labor,
equipment, and materials to
move yard inlet on Melvin
just west of tracks,
complete as specified Lump
Sum 0.00 1.00 1.00 $1,200.00 $1,200.00
244 Additional labor,
equipment, and materials to
recore manholes G28 and
G -30 to match field
conditions, complete as Lump
_specified Sum 0.00 1.00 1.00 $4,500.00 $4,500.00
ADDITIONAL WORK: C.O. # 1 - (ITEMS 237 - 243) - SUB -TOTAL $20,234.81 $0.00
NET DECREASE TO: SECTION II ($21,410.60)
Page 6 of 14
•
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE 1N
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
SECTION III - SANITARY SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
300 Furnish and install 8"
sanitary sewer (relay), Linear
complete as specified Feet 4,625 5038.20 413.20 $60.00 $24,792.00
301 Furnish and install 8"
sanitary sewer drop, Vertical
complete as specified Feet 30 15.01 -14.99 $250.00 ($3,747.50)
302 Furnish and install 10"
sanitary sewer (relay), Linear
complete as specified Feet 2,950 2598.00 - 352.00 $62.00 ($21,824.00)
303 Furnish and install 12"
sanitary sewer (relay), Vertical
complete as specified Feet 15 10.00 -5.00 $75.00 ($375.00)
304 Furnish and install 12"
sanitary sewer drop, Vertical
complete as specified Feet 5 0.00 -5.00 $300.00 ($1,500.00)
305 Furnish and install 15"
sanitary sewer (relay), Vertical
complete as specified Feet 5 5,00 $90.00
306 Furnish and install 18"
sanitary sewer (relay), Vertical
complete as specified Feet 50 50.00 $96.00
307 Furnish and install 30"
sanitary sewer (relay), Vertical
complete as specified Feet 5 0.00 -5.00 $150.00 ($750.00)
308 Furnish and install std.
sanitary manhole (4' inside
diameter) in various
locations, complete as
specified, without casting Vertical
Feet 440 473.16 33.16 $200.00 $6,632.00
309 Furnish and install 8" x 4"
factory wyes or tees,
complete as specified Each 1 0.00 -1.00 $40.00 ($40.00)
310 Furnish and install 8" x 6"
factory wyes or tees,
complete as specified Each 100 100.00 $61.00
311 Furnish and install 10" x 6"
factory wyes or tees,
complete as specified Each 30 27.00 -3.00 $95.00 ($285.00)
312 Furnish and install new 4"
sanitary laterals, complete Linear
as specified Feet 380 370.00 -10.00 $51.00 ($510.00)
313 Furnish and install 4 "/6"
sanitary lateral relay, Linear
complete as specified Feet 2,950 2785.50 - 164.50 $52.00 ($8,554.00)
314 Furnish and install sanitary
lateral marker balls,
complete as specified
Each 255 254.00 -1.00 $13.00 ($13.00)
315 Furnish and install concrete
collars, complete as
specified Each 2 4.00 2.00 $400.00 $800.00
Page 7 of 14
•
CONTRACT: 10 -04 CHANGE ORDER # 1
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
316 Core into existing manhole,
complete as specified
Each 6 5.00 -1.00 $550.00 ($550.00)
317 Abandon sanitary
manholes at various
locations, complete as
specified Each 8 8.00 $350.00
318 Abandon 8" sanitary sewer
at various locations Linear
complete as specified Feet 860 860.00 $2.70
319 Abandon 10" sanitary
sewer at various locations,
complete as specified Linear
Feet 815 815.00 $3.00
320 Abandon 12" sanitary
sewer at various locations,
complete as specified Linear
Feet 1,040 240.00 - 800.00 $3.40 ($2,720.00)
321 Furnish and install
connections of new sanitary
main to existing sanitary
main (various locations and
sizes), complete as
specified Each 23 18.00 -5.00 $550.00 ($2,750.00)
322 Furnish and install 8" plug,
complete as specified
Each 1 1.00 $250.00
323 Furnish and install 18"
casing pipe (18' lengths),
complete as specified Each 1 1.00 $2,000.00
324 Furnish and install 10" x 4"
factory wye or tee,
complete as specified Each 1 0.00 -1.00 $80.00 ($80.00)
325 Furnish and install 4"
sanitary lateral cleanout,
complete as specified Each 3 0.00 -3.00 $290.00 ($870.00)
SECTION III - (BID ITEMS 300 - 325) - SUB - TOTALS $32,224.00 ($44,568.50)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION III
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
326 Additional labor,
equipment, and materials to
install tracer wire and tracer
wire boxes for sanitary
lateral for the storm water
pump station, complete as Lump
specified Sum 0.00 1.00 1.00 $1,353.03 $1,353.03
327 Additional labor,
equipment, and materials to
jack hammer and remove
concrete ballast at the
connection to MH H -8,
complete as specified Hrs. 0.00 4.00 4.00 $850.00 $3,400.00
Page 8 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
328 Sanitary MH #18 was built
and delivered to site, upon
excavation it was
determined that the field
conditions did not match
MH #18 and manhole could
not be used, therefore the
city bought the manhole
section and it was delivered Lump
to City yard Sum 0.00 1.00 1.00
$1,604.75 $1,604.75
329 Existing field conditions did
not match inverts of MH M-
16, MH M10was
substituted for MH M -16,
and MH M -16 was bought
by City and delivered to the
City yard. Payment for
additional crew time was
granted for the switching of Lump
manholes Sum 0.00 1.00 1.00 $3,892.25 $3,892.25
330 Additional labor,
equipment, and materials to
rebuild and plug MH M -8 to
match existing field
conditions, complete as Hrs. 0.00 4.00 4.00 $750.00 $3,000.00
331 Additional labor,
equipment, and materials to
install 8" sanitary sewer
and casing pipe under the
box culvert at 705 Melvin,
complete as specified Lump
Sum 0.00 1.00 1.00 $1,200.00 $1,200.00
332 Additional crew time and
jack hammer rental to cut
off existing drops and
concrete casing on existing
sanitary manhole at Melvin
and Powers, complete as
specified Hours 0.00 4.00 4.00 $850.00 $3,400.00
333 Additional crew time and
jack hammer rental to cut
off existing drops and
concrete casing on existing
sanitary manhole MH N -10
at New York Ave., complete
as specified
Hours 0.00 3.50 3.50 $850.00 $2,975.00
334 Additional crew time and
jack hammer rental to cut
off existing drops and
concrete casing on existing
sanitary manhole at Broad
and Irving Hours 0.00 1.50 1.50 $850.00 $1,275.00
335 Additional crew time and
jack hammer rental to cut
off existing drops and
concrete casing on existing
32" sanitary sewer on
Hazel St., complete as
specified Hours 0.00 3.50 3.50 $850.00 $2,975.00
Page 9 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
336 Existing 12" sanitary sewer
was slurry filled, per
Inspector's request, Linear
complete as specified Feet 0.00 800.00 800.00 $6.00 $4,800.00
337 Additional labor,
equipment, and matreials to
install additional access
point to lift station lateral,
per City of Oshkosh
Plumbing Inspector's
orders, complete as Lump
specified. Sum 0.00 1.00 1.00 $2,250.00 $2,250.00
ADDITIONAL WORK: C. O. 1 - (ITEMS 326 - 335) - SUB -TOTAL $32,125.03 $0.00
NET INCREASE TO: SECTION III $19,780.53
SECTION IV - WATER MAIN
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
400 Furnish and install 4"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 20 384.00 364.00 $80.00 $29,120.00
401 Furnish and install 6"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 325 327.00 2.00 $53.45 $106.90
402 Furnish and install 8"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 6,600 7010.00 410.00 $58.00 $23,780.00
403 Furnish and install 18"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 50 49.00 -1.00 $100.00 ($100.00)
404 Furnish and install 1" water
service relay, complete as
specified, not including
corporation and stop box Linear
Feet 3,000 2917.00 -83.00 $38.00 ($3,154.00)
405 Furnish and install new 1"
water service, complete as
specified, not including
corporation and stop box Linear
Feet 40 10.00 -30.00 $39.00 ($1,170.00)
406 Furnish and install 1"
corporation and stop box
with stainless steel rod,
complete as specified Each 125 122.00 -3.00 $300.00 ($900.00)
Page 10 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
407 Furnish and install 8" x 6"
tees, complete as specified
Each 23 20.00 -3.00 $325.00 ($975.00)
408 Furnish and install 8" x 8"
tees, complete as specified
Each 7 9.00 2.00 $350.00 $700.00
409 Furnish and install 8" x 8"
cross, complete as
specified Each 4 4.00 $336.00
410 Furnish and install 6"
valves, complete as
specified Each 21 21.00 $855.00
411 Furnish and install 8"
valves, complete as
specified Each 44 49.00 5.00 $1,120.00 $5,600.00
412 Furnish and install 18"
valves, complete as
specified Each 2 2.00 $9,100.00
413 Furnish and install 6" x 6"
tapping valve and sleeve,
complete as specified Each 1 0.00 -1.00 $2,200.00 ($2,200.00)
414 Furnish and install 12" x 8"
tapping valve and sleeve,
complete as specified
Each 2 0.00 -2.00 $2,888.00 ($5,776.00)
415 Furnish and install 4" - 22
'/� degree bends, complete
as specified Each 2 0.00 -2.00 $140.00 ($280.00)
416 Furnish and install 6" - 22
1 /2 degree bends, complete
as specified Each 3 0.00 -3.00 $180.00 ($540.00)
417 Furnish and install 8" - 22
1 /2 degree bends, complete
as specified Each 3 7.00 4.00 $245.00 $980.00
418 Furnish and install 4" - 45
degree bends, complete as
specified Each 2 6.00 4.00 $145.00 $580.00
419 Furnish and install 6" - 45
degree bends, complete as
specified Each 18 34.00 16.00 $190.00 $3,040.00
420 Furnish and install 8" - 45
degree bends, complete as
specified Each 34 53.00 19.00 $245.00 $4,655.00
421 Furnish and install 18" - 45
degree bends, complete as
specified Each 4 4.00 $1,330.00
422 Furnish and install 8" x 4"
reducer, complete as
specified Each 1 2.00 1.00 $200.00 $200.00
423 Furnish and install 8" x 6"
reducers, complete as
specified Each 18 19.00 1.00 $215.00 $215.00
424 Relocate hydrant, complete
as specified Each 2 0.00 -2.00 $800.00 ($1,600.00)
425 Furnish and install
hydrants, complete as
specified Each 17 20.00 3.00 $2,900.00 $8,700.00
Page 11 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
426 Furnish and install
gradeloks for hydrant
branches, complete as
specified Each 17 0.00 -17.00 $400.00 ($6,800.00)
427 Furnish and install
connections of new water
main to existing water main
(various sizes and
locations), complete as
specified Each 28 25.00 -3.00 $1,735.00 ($5,205.00)
428 Furnish and install 6" cap,
complete as specified
Each 5 0.00 -5.00 $250.00 ($1,250.00)
429 Furnish and install 8" cap,
complete as specified
Each 7 3.00 -4.00 $300.00 ($1,200.00)
430 Cut and cap existing 4"
water main, complete as
specified Each 1 0.00 -1.00 $350.00 ($350.00)
431 Cut and cap existing 6"
water main, complete as
specified Each 3 0.00 -3.00 $380.00 ($1,140.00)
432 Cut and cap existing 8"
water main, complete as
specified Each 1 0.00 -1.00 $450.00 ($450.00)
433 Furnish and install 6"
sleeve, complete as
specified Each 5 6.00 1.00 $360.00 $360.00
434 Furnish and install 8"
sleeve complete as
specified Each 5 6.00 1.00 $410.00 $410.00
435 Furnish and install 10"
sleeve complete as
specified Each 5 0.00 -5.00 $550.00 ($2,750.00)
436 Furnish and install 12"
sleeve complete as
specified Each 5 1.00 -4.00 $700.00 ($2,800.00)
437 Abandon water main on
Broad Street (Parkway Ave
to Irving Ave), complete as Lump
specified Sum 1 1.00 $1,000.00
438 Abandon water main on
Grand Street (Lincoln Ave
to New York Ave), Lump
complete as specified Sum 1 1.00 $3,000.00
439 Abandon water main on
Melvin Avenue (Eastman
Ave to Hazel St), complete Lump
as specified Sum 1 1.00 $3,000.00
440 Abandon water main on
Powers St. (New York Ave
to Nevada Ave), complete Lump
as specified Sum 1 1.00 $1,000.00
441 Abandon water main on
Rock Place (Grand Ave to
CN RR ROW), complete as Lump
specified Sum 1 1.00 $1,000.00
Page 12 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
442 Furnish and install 2"
casing pipe (18 foot
lengths), complete as
specified Each 8 4.00 -4.00 $360.00 ($1,440.00)
443 Furnish and install 18"
casing pipe (18 foot
lengths), complete as
specified Each 5 5.00 $2,000.00
444 Furnish and install 36"
casing pipe (18 foot
lengths), complete as
specified Each 1 1.00 $5,000.00
445 Furnish and install 1
water service, complete as
specified, not including
corporation and stop box Linear
Feet 360 0.00 - 360.00 $48.00 ($17,280.00)
446 Furnish and install 1Y2"
corporation and stop box
with stainless steel rod,
_complete as specified Each _ 1 0.00 -1.00 $742.00 ($742.00)
SECTION IV - (BID ITEMS 400 - 446) - SUB - TOTALS $78,446.90 ($58,102.00)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
447 Additional labor,
equipment, and materials to
lower 12" water main in the
intersection of Broad St.
and Parkway Avenue,
complete as specified L.S. 0.00 1.00 1.00 $10,927.66 $10,927.66
448 Relay 1 -1/4" water service
on Powers and Nevada,
complete as specified L.F. 0.00 36.00 36.00 $48.00 $1,728.00
449 Additional labor,
equipment, and materials to
install 6" x 4" tapping valve
and sleeve for storm water
lift station, complete as
specified L.S. 0.00 1.00 1.00 $4,719.81 $4,719.81
450 Additional labor,
equipment, and materials to
relocate 8" water main on
Melvin St at Station 12 +45
to save large Oak tree,
complete as specified
L.S. 0.00 1.00 1.00 $2,250.00 $2,250.00
451 Additional labor,
equipment, and materials to
remove old leaded cross
and tee and replace new 6"
x 6" tee on Eastman and
Melvin, complete as
_specified L.S. 0.00 1.00 1.00 $4,058.17 $4,058.17
Page 13 of 14
CONTRACT: 10 -04 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
452 Additional labor,
equipment, and materials to
fix water main blowout on
8/30 on Grand St.,
complete as specified L.S. 0.00 1.00 1.00 $1,370.00 $1,370.00
453 Additional labor,
equipment, and materials to
fix crack in existing water
main on 8/23, complete as
specified Hrs. 0.00 1.50 1.50 $750.00 $1,125.00
454 Additional labor,
equipment, and materials to
temporary patch the
Eastman St. and Melvin
Ave. intersection where
water main was extended
and old water main was
abandoned, complete as
specified L.S. 0.00 1.00 1.00 $2,555.09 $2,555.09
455 Additional labor,
equipment, and materials to
fix leaking water service at
1002 Bong Ct., complete as
specified Hrs. 0.00 2.00 2.00 $750.00 $1,500.00
456 Furnish and install 18" solid
sleeve, complete as
_specified Each 0.00 1.00 1.00 $1,651.55 $1,651.55
ADDITIONAL WORK: C.O. # 1 (ITEMS 447 - 455) - SUB -TOTAL $31,885.28 $0.00
NET INCREASE TO: SECTION IV $52,230.18
NET INCREASE TO SECTIONS I, 11, III, IV $323,869.83
NET DECREASE TO SECTIONS I, II, III, IV ($194,185.91)
NET INCREASE TO CONTRACT: $129,683.92
Page 14 of 14