December 17, 2010
Mr. Bill Bowers
Carl Bowers & Sons Construction Co.
N1844 Maloney Road
Kaukauna, WI 54130
Re: Change Order #1 /Contract 10 -07
Dear Mr. Bowers:
Enclosed please find an executed copy of the Change Order between the City of Oshkosh and Carl
Bowers & Sons Construction Company, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
o toirrL • �Q v`cibm/
David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, City Attorney (w /copy)
File Copy (w /original)
CHANGE ORDER # 1
DATED: October 19, 2010
TO: Carl Bowers & Sons Constr. Co.
N1844 Maloney Rd
Kaukauna, WI 54130
Your present contract with the City of Oshkosh, Contract No. 10 -07 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION II - STORM SEWER $15,710.00
NET INCREASE TO: SECTION III - SANITARY SEWER $1,880.00
NET INCREASE TO: SECTION IV - WATER MAIN $4,320.00
NET INCREASE TO CONTRACT: $21,910.00
CITY OF OSHKOSH
BY: _— _Air- a. ' • -
Recommended: - _ _
,h d 1.--44,, iia IL ■ Director of Public Works City Clerk l
Approved and accepted:
(...--- gP -- -,P4,..--.
L Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
/20444 ye.,02).0,0
Approved as to form: -
- c''. A (;----- - Mi.i.41\/
- City Atto
CONTRACT: 10 -07 CHANGE ORDER # 1
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION II
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
229 Furnish and install 8" storm
sewer, complete as Linear
specified Foot 0.00 12.00 12.00 $40.00 $480.00
230 Reconnect existing storm
lateral, complete as
specified Each 0.00 1.00 1.00 $350.00 $350.00
231 Additional labor and
equipment to excavate
around existing gas main
that was in conflict with
storm sewer on Prospect
Ave on July 19, 2010, per Lump
Invoice #SC10046 Sum 0.00 1.00 1.00 $1,640.00 $1,640.00
232 Additional labor and
equipment to work around
WPS crews on July 19,
2010, per Invoice Lump
#SC10047 Sum 0.00 1.00 1.00 $1,640.00 $1,640.00
233 Additional labor and
equipment to work around
WPS crews on July 20,
2010, per Invoice Lump
#SCI0048 Sum 0.00 1.00 1.00 $1,640.00 $1,640.00
234 Additional labor,
equipment, and materials
to core into proposed storm
manhole due to location of
gas main, per Invoice # Lump
SC10049 Sum 0.00 1.00 1.00 $600.00 $600.00
235 Additional labor,
equipment, and materials
to temporary hook up 30
inch storm sewer around
the 6 inch gas main in the
intersection of Prospect
Ave. and Merrill St., per Lump
Invoice SCI0050 Sum 0.00 1.00 1.00 $1,910.00 $1,910.00
236 Additional labor,
equipment, and materials
to try to install 24 inch
storm sewer around the
telephone duct package in
the Jackson St. ad
Prospect Ave Intersection.
When 24 inch pipe did not
fit, it was downsized to an
18 inch , per Invoice Lump
5010051 Sum 0.00 1.00 1.00 $1,640.00 $1,640.00
Page 1 of 3
CONTRACT: 10 -07 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
237 Additional labor,
equipment, and materials
to install storm sewer that
is in conflict with the water
main in the intersection of
Merrill St. and New York Lump
Ave., per Invoice #SC10052 Sum 0.00 1.00 1.00 $4,060.00 $4,060.00
238 Additional labor,
equipment, and materials
to install 4 inlets that were
all set 1 foot to low due to
inaccurate grades. Inlets
were removed and
replaced to correct grades,
per Invoice #SC10054 Lump
Sum 0.00 1.00 1.00 $930.00 $930.00
239 Additional labor,
equipment, and materials
to connect proposed 30
inch storm sewer to
manhole now that gas main
has been abandoned in the
intersection of Merrill St.
and Prospect Ave, per Lump
Invoice SC10055 Sum 0.00 1.00 1.00 $820.00 $820.00
ADDITIONAL WORK: C.O. # 1 - (ITEMS 229 - 239) - SUB -TOTAL $15,710.00 $0.00
NET INCREASE TO: SECTION II $15,710.00
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION III
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
318 Furnish and install
reconnections of existing
sanitary laterals, complete
as specified Each 0.00 1.00 1.00 $375.00 $375.00
319 Furnish and install 12"
sanitary sewer drop, Vertical
complete as specified Feet 0.00 2.10 2.10 $550.00 $1,155.00
320 Furnish and install low
permeable plugs, complete
as specified Each 0.00 2.00 2.00 $175.00 $350.00
ADDITIONAL WORK: C. O. # 1 - (ITEMS 318 -320) - SUB -TOTAL $1,880.00 $0.00
NET INCREASE TO: SECTION III $1,880.00
Page 2 of 3
CONTRACT: 10 -07 CHANGE ORDER # 1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
442 Furnish and install 2 inch
water service relay, Linear
complete as specified Feet 0.00 17.00 17.00 $55.00 $935.00
443 Furnish and install 2 inch
corporation and stop box,
complete as specified Each 0.00 1.00 1.00 $475.00 $475.00
444 Furnish and install 4 inch
sleeve, complete as
specified Each 0.00 2.00 2.00 $225.00 $450.00
445 Additional, labor,
equipment, and materials
to have Don Hieptas &
Sons redo a water main tie
in, in the intersection of
Bowen St. and Harney
Ave. On August 24, they
were all set to perform tie
in but water department
could not shut off water, so
they excavated valve and
installed new, so water
could be shut off the next
day for the tie in, per
Invoice #SC10056 Each 0.00 1.00 1.00 $2,460.00 $2,460.00
ADDITIONAL WORK: C.O. # 1 (ITEMS 442 - 445) - SUB - TOTAL $4,320.00 $0.00
NET INCREASE TO: SECTION IV $4,320.00
NET INCREASE TO SECTIONS 11,111, IV $21,910.00
NET DECREASE TO SECTIONS II, 111, IV $0.00
NET INCREASE TO CONTRACT: $21,910.00
Page 3 of 3