HomeMy WebLinkAboutPW CNT 10-06/CNG 2 City of Oshkosh
Department of Public Works
215 Church Avenue
P.O. Box 1 130
Oshkosh, Wisconsin
54903 -1130
(-41 (920) 236 -5065
OJHKOJH
ON THE WATER
December 17, 2010
Mr. Leroy Fischer
Fischer -Ulman Construction, Inc.
1115 S. Theodore Street
Appleton, WI 54915
Re: Change Order #2 /Contract 10 -06
Dear Mr. Fischer:
Enclosed please find an executed copy of the Change Order between the City of Oshkosh and
Fischer -Ulman Construction, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
d tV oL C. A,& /cb-
David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, City Attorney (w /copy)
File Copy (w /original)
CHANGE ORDER # 2
DATED: December 1, 2010
TO: FISCHER -ULMAN CONSTRUCTION
1115 S. THEODORE STREET
APPLETON, WI 54915
Your present contract with the City of Oshkosh, Contract No. 10 -06 , is hereby amended
and changed as follows:
NET DECREASE TO CONTRACT: ($28,136.81)
CITY OF OSHKOSH
BY: AL Ar R
Recommended: `
Director of Pub4ic Works City Clerk
A•proved and ac - • ed:
4,
A iiI i ._ id / A
Co tr. ctor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
L f Idaimptroller
Appr• -d as to form:
�.....�.. _ emu. .►
�� City Attor -y
CONTRACT: 10 -06 CHANGE ORDER # 2
CONCRETE SIDEWALK (New and Reconstruction)
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Sidewalk removal &
driveway removal, Square
complete as specified Feet 94,250.00 90,001.74 - 4,248.26 0.33 ($1,401.93)
2 Concrete /asphalt sawing, Linear
complete as specified Feet 4,750.00 5,528.21 778.21 2.00 1,556.42
3 Construct 4" thick concrete
sidewalk in various
locations in the City of
Oshkosh, complete as Square
specified Feet 91,000.00 90,591.05 - 408.95 2.84 ($1,161.42)
4 Construct 6" thick concrete
sidewalk in various
locations in the City of
Oshkosh, complete as Square
specified Feet 16,750.00 13,166.02 - 3,583.98 3.14 ($11,253.70)
5 Construct 7" thick
crosswalk areas, complete Square
as specified Feet 4,000.00 1,577.87 - 2,422.13 3.28 ($7,944.59)
6 Provide and install metal
detectable warning plates,
complete as specified Square
Feet 200.00 144.00 -56.00 28.00 ($1,568.00)
7 Three (3 ") inch asphalt
replacement, complete as Square
specified Feet 2,250.00 1,324.05 - 925.95 3.70 ($3,426.02)
8 Curb and gutter removal, Linear
complete as specified Feet 425.00 218.70 - 206.30 3.50 ($722.05)
9 Construct 30" curb and
gutter, complete as Linear
specified Feet 425.00 233.70 - 191.30 16.80 ($3,213.84)
10 Terrace restoration,
including seed, fertilizer,
and mulch, complete as Square
specified Yards 2,000.00 1,095.63 - 904.37 3.90 ($3,527.04)
11 Furnish and install
pavement ties, complete as
specified Each 150.00 65.00 _ -85.00 6.00 ($510.00)
12 Construct 4" thick concrete
sidewalk in Water Dept.
repair locations as approx.
60 sites, complete as Square
specified Feet 2,500.00 735.41 - 1,764.59 4.13 ($7,287.76)
13 Construct 6" thick concrete
sidewalk in Water Dept.
repair locations at approx.
20 sites, complete as Square
specified Feet 1,000.00 116.50 - 883.50 4.30 ($3,799.05)
14 7" non - reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 100.00 32.50 -67.50 39.00 ($2,632.50)
Page 1 of 4
CONTRACT: 10 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
15 8" non - reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb & grading,
terrace & traffic control, Square
complete as specified Yards 1,750.00 439.16 - 1,310.84 39.20 ($51,384.93)
16 8" special High Early
Strength, non - reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb and grading, terracing
and traffic control, Square
complete as specified Yards 150.00 0.00 - 150.00 46.50 ($6,975.00)
17 Extra crushed stone base,
complete as specified Tons 150.00 182.30 32.30 12.00 387.60
18 No. 4 epoxy- coated
reinforced rods, installed Linear
as specified Feet 300.00 92.00 - 208.00 1.50 ($312.00)
19 Furnish, install, and
maintain Type "C" inlet
protection, complete as
specified Each 5.00 0.00 -5.00 40.00 ($200.00)
20 Furnish, install, and
maintain Type "D" inlet
protection, complete as
specified Each 40.00 66.00 26.00 40.00 1,040.00
21 Construct 12" wide radius
curb head, complete as Linear
specified Feet 150.00 71.00 -79.00 3.50 ($276.50)
22 Furnish, install, and
maintain erosion mat, Square
complete as specified Yards 100.00 214.71 114.71 1.75 200.74
23 Profile sawcut concrete Linear
curb, complete as specified Feet 50.00 0.00 -50.00 40.00 ($2,000.00)
SUB -TOTAL CONCRETE SIDEWALK (NEW & RECONSTRUCTION) 3,184.76 ($109,596.33)
CONCRETE SIDEWALK (New and Reconstruction)
ADDITIONAL ITEMS
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
24 8 "/7 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 882.19 882.19 45.25 39,919.10
Page 2 of 4
CONTRACT: 10 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
25 8 "/8 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 528.73 528.73 46.04 24,342.73
26 Construct 8" thick concrete
sidewalk, complete as Square
specified Feet 0.00 1,937.60 1,937.60 4.19 8,118.54
27 Construct 8" thick concrete
sidewalk, 9 -bag mix,
complete as specified Square
Feet 0.00 220.00 220.00 6.85 1,507.00
28 Construct 4" thick concrete
sidewalk, 8 -bag mix,
complete as specified Linear
Feet 0.00 157.52 157.52 5.72 901.01
ADDITIONAL ITEMS - CONCRETE SIDEWALK 74,788.38 $0.00
CHANGES TO CHANGE ORDER #1
ADDITIONAL WORK PER QUOTE FOR W. MURDOCK AVENUE PAVEMENT:
CONCRETE PAVING
ITEM C/O #1 INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER
DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
100 Sidewalk & driveway Square
removal, complete as Feet
specified 585.00 554.20 -30.80 0.50 ($15.40)
101 8" Concrete pavement
including integral curb,
pavement removal, sawcut, Square
pavement ties, and Yards
landscaping, complete as
specified 625.00 683.40 58.40 42.75 2,496.60
102 12" Radius curb head, Linear
complete as specified Feet 48.00 74.90 26.90 4.00 107.60
103 Standard 30" curb & gutter, Linear
7" (tie -in), complete as Feet
specified 15.00 14.10 -0.90 22.50 ($20.25)
104 4" Concrete sidewalk, Square
complete as specified Feet 300.00 457.20 157.20 2.90 455.88
105 6" Concrete sidewalk & Square
driveway, complete as Feet
specified 286.00 98.20 - 187.80 3.35 ($629.13)
106 3 1/2" Asphaltic concrete
transition, with base, Square
complete as specified Yards 105.00 107.20 2.20 41.40 91.08
107 Adjust manholes and inlets,
complete as specified Each
4.00 8.00 4.00 250.00 1,000.00
Page 3of4
CONTRACT: 10 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
108 Provide and install metal Square
detectable warning plates, Feet
complete as specified 16.00 16.00 28.00
CHANGES TO CHANGE ORDER #1 - CONCRETE PAVING - SUB - TOTALS 4,151.16 ($664.78)
82,124.30 ($110,261.11)
NET DECREASE TO CONTRACT 10 -06: (28,136.81)
Page 4 of 4