HomeMy WebLinkAboutPW CNT 08-01/CNG 3 CHANGE ORDER # 3
DATED: July 9, 2010
TO: S. J. LOUIS CONSTRUCTION, INC.
1351 W. BROADWAY STREET
P.O. BOX 459
ROCKVILLE, MN 56369
Your present contract with the City of Oshkosh, Contract No. 08 -01 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING ($75,612.34)
NET INCREASE TO: SECTION II - STORM SEWER $9,448.46
NET INCREASE TO: SECTION III - SANITARY SEWER $16,698.85
NET INCREASE TO: SECTION IV - WATER MAIN $41,967.50
NET INCREASE TO SECTION V - WORK UNIT B STORM SEWER $25,896.96
NET DECREASE TO CONTRACT: $18,399.43
CITY OF OSHKOSH
BY: /' ag__
Recommended: 1 City M. • - -
�o�d G. Pc�fe Ire �IL���•
Director of Public Works City Clerk
Approved and accepted:
Co actor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
omptroller
Approved as to form:
" 1 " ECEHE
low City Atto - AUG 1 1 ?D'0
CITY C E CFF1CF
•
CONTRACT: 08 -01 CHANGE ORDER # 3
SECTION 1- CONCRETE PAVING
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES WCREASE DECREASE UNIT
PRICE PRICE
100. Furnish and Install
temporary security fence, Linear
complete as specified Foot 9,000 7,091.97 - 1,908.03 $3.00 ($5,724.09)
101. Furnish and Install Traffic
Control, complete as Lump
specified Sum 1 1.00 $50,000.00
102. Furnish Clearing and
grubbing, complete as Lump
specified Sum 1 1.00 $13,000.00
103. Pavement removal with
integral curb, complete as Square
specified Yards 5,700 5,682.70 -17.30 $3.00 ($51.90)
104. Pavement removal in spot
locations, complete as Square
specified Yards 700 675.60 -24.40 $4.50 ($109.80)
105. Concrete sidewalk and
driveway removal, Square
complete as specified Feet 5,150 14,297.40 9,147.40 $1.00 $9,147.40
106. Concrete curb &/or
concrete curb and gutter
removal, complete as Linear
specified Feet 900 4,117.60 3,217.60 $2.00 $6,435.20
107. Unclassified Excavation, Lump
complete as specified Sum 1 1.00 $44,000.00
108. 8" non - reinforced concrete
pavement, including
integral curb, base in place,
complete as specified Square
Yards 5,500 4,914.30 - 585.70 $35.00 ($20,499.50)
109. 8" non - reinforced concrete
pavement, special H.E.S.
(9 -bag) including integral
curb, base in place,
complete as specified Square
Yards 300 998.90 698.90 $42.00 $29,353.80
110. 8" non - reinforced concrete
pavement, base in place,
spot locations, complete as Square
specified Yards 700 575.30 - 124.70 $45.00 ($5,611.50)
111. Concrete median nose and
sidewalk, complete as Square
specified Feet 900 143.80 - 756.20 $5.50 ($4,159.10)
112. Standard 30" curb and
gutter, 8" mainline, Linear
complete as specified Feet 900 1,386.70 486.70 $14.00 $6,813.80
113. Standard 30" curb and
gutter. 8" mainline, spot
repairs (Less than 30 feet
in length), complete as Linear
specified Feet 300 138.50 - 161.50 $23.00 ($3,714.50)
114. 6" concrete sidewalk &
driveway, complete as Square
specified Feet 6,500 5,152.40 - 1,347.60 $4.00 ($5,390.40)
115. 4" concrete sidewalk, Square
complete as specified Feet 2,000 5,625.20 3,625.20 $3.60_ $13,050.72
Page 1 of 11
•
CONTRACT: 08-01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
116. 2" asphaltic concrete
driveway and pathway,
lower layer, complete as
specified Tons 150 145.64 -4.36 $100.00 ($436.00)
117. 1 ' /z' asphaltic concrete
driveway and pathway,
upper layer, complete as
specified Tons 125 145.64 20.64 $87.00 $1,795.68
118. 3 W asphaltic concrete
pavement, lower layer,
complete as specified Tons 730 662.04 -67.96 $65.00 ($4,417.40)
119. 1 %' asphaltic concrete
pavement, upper layer,
complete as specified Tons 600 547.45 -52.55 $65.00 ($3,415.75)
120. Preparation of foundation
for asphalt paving on New
York Avenue, complete as Lump
specified Sum 1 1.00 $5,600.00
121. Tack or prime coat,
complete as specified Gallon 150 100.00 -50.00 $3.50 ($175.00)
122. Furnish and install crushed
stone base course,
complete as specified
Tons 13,000 5,615.00 - 7,385.00 $11.00 ($81,235.00)
123. Sawing, complete as Linear
specified Feet 2,000 4,584.00 2,584.00 $4.00 $10,336.00
124. Furnish and install
pavement ties (epoxy
coated), complete as
specified Each 1,500 1,187.00 - 313.00 $5.00 ($1,565.00)
125. Adjust manholes and inlets,
complete as specified
Each 110 73.00 -37.00 $225.00 ($8,325.00)
126. Furnish and install No. 4
reinforcing bars (epoxy
coated), complete as
specified Each 100 45.00 -55.00 $1.00 ($55.00)
127. Provide and install metal
detectable warning plates,
complete as specified Square
Feet 288 224.00 -64.00 $30.00 ($1,920.00)
128. Furnish and install
Geotextile fabric, complete Square
as specified Yards 100 0.00 - 100.00 $10.00 ($1,000.00)
129. Remove and replace traffic
signal loop detectors,
complete as specified Linear
Feet 150 0.00 - 150.00 $30.00 ($4,500.00)
130. Terrace work in
Menominee Park from
Parkway Avenue to New
York Avenue, complete as Lump
specified Sum 1 1.00 $165,000.00
131. Terrace work on New York
Avenue from Hazel Street
to Bowen Street, complete Lump
as specified Sum 1 1.00 $24,000.00
Page 2 of 11
•
CONTRACT: 08 -01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
132. Terrace work on New York
Avenue from Bowen Street
to Canadian National
Railroad Tracks, complete Lump
as specified Sum 1 1.00 $18,000.00
133.
12" wide radius curb head, Linear
complete as specified Feet 700 670.00 -30.00 $8.00 ($240.00)
SECTION I - (BID ITEMS 100 - 133) - SUB - TOTALS $76,932.60 ($152,544.94)
NET DECREASE TO: SECTION I ($75,612.34)
SECTION II - STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
200. Furnish and install 10"
storm sewer, complete as Linear
specified Feet 44 44.00 $22.00
201. Furnish and install 12"
storm sewer, complete as Linear
specified Feet 510 519.00 9.00 $23.00 $207.00
202. Furnish and install 15"
storm sewer, complete as Linear
specified Feet 20 69.00 49.00 $24.00 $1,176.00
203. Furnish and install 18"
storm sewer, complete as Linear
specked Feet 70 94.00 24.00 $29.00 $696.00
204. Furnish and install 21"
storm sewer, complete as Linear
specified Feet 20 22.00 2.00 $33.00 $66.00
205. Furnish and install 24"
storm sewer, complete as Linear
specified Feet 20 24.00 4.00 $35.00 $140.00
207. Furnish and install 30"
storm sewer, complete as Linear
specified Feet 60 61.00 1.00 $47.00 $47.00
207. Furnish and install 42"
storm sewer, complete as Linear
specified Feet 95 94.00 -1.00 $77.00 ($77.00)
208. Furnish and install std.
inlets (Type 3 with 18"
sump), with castings,
complete as specified Each 19 21.00 2.00 $1,150.00 $2,300.00
209. Furnish and install std.
Storm manhole (4' inside
diameter) in various
locations without casting, Vertical
complete as specified Feet 12 17.25 5.25 $600.00 $3,150.00
210. Furnish and install std.
Inlets (Type 1 with 18"
sump) with castings,
complete as specified Each 3 3.00 $1,150.00
Page 3 of 11
CONTRACT: 08 -01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
211. Furnish, install, and
maintain Type "C" inlet
protection in 10 locations,
complete as specified Each 10 16.00 6.00 $44.00 $264.00
212. Furnish and install, and
maintain Type "D" inlet
protection in 75 locations,
complete as specified Each 75 119.00 44.00 $100.00 $4,400.00
213. Furnish and install, and
maintain silt fence, as
shown on the plans, Linear
complete as specified Feet 5,000 3,539.73 - 1,460.27 $2.00 ($2,920.54)
214. Furnish and install
connections of new storm
sewer to existing main
(various sizes and
locations), complete as
specified Each 29 29.00 $800.00
SECTION II - (BID ITEMS 200 - 214) - SUB - TOTALS $12,446.00 ($2,997.54)
NET INCREASE TO: SECTION II $9,448.46
SECTION III - SANITARY SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
300. Furnish and install 60"
sanitary sewer (Hobas
Pipe), with native backfill Linear
complete as specified Feet 3,270 3,187.60 -82.40 $370.00 ($30,488.00)
301.
Furnish and install 60"
sanitary sewer (Hobas
Pipe) with granular backfill, Linear
complete as specified Feet 1,800 1,883.95 83.95 $375.00 $31,481.25
302.
Furnish and install 24"
sanitary sewer (PVC Pipe), Linear
complete as specified Feet 1,290 1,234.62 -55.38 $100.00 ($5,538.00)
303.
Furnish and install 18"
sanitary sewer (PVC Pipe), Linear
complete as specified Feet 60 241.00 181.00 $90.00 $16,290.00
304.
Furnish and install 15"
sanitary sewer (PVC Pipe), Linear
complete as specified Feet 960 958.61 -1.39 $80.00 ($111.20)
305.
Furnish and install 12"
sanitary sewer (PVC Pipe), Linear
complete as specified Feet 110, 170.14 60.14 $75.00 $4,510.50
306.
Furnish and install 10"
sanitary sewer (PVC Pipe), Linear
complete as specified Feet 100 116.72 16.72 $60.00 $1,003.20
Page 4of11
•
CONTRACT: 08 -01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
307.
Furnish and install 8"
sanitary sewer (PVC Pipe), Linear
complete as specified Feet 135 129.15 -5.85 $55.00 ($321.75)
308. Jack and bore 36" steel
casing pipe, complete as Lineal
specified Feet 50 70.00 20.00 $1,200.00 $24,000.00
309. Furnish and install MH H -1,
complete as specified, Lump
without casting Sum 1 0.60 -0.40 $30,000.00 ($12,000.00)
310. Furnish and install MH H -2,
complete as specified, Lump
without casting Sum 1 1.00 $28,000.00
311. Furnish and install MH H -3
(Hobas Base Tee with
Riser), complete as Lump
specified, without casting Sum 1 1.00 $25,000.00
312. Furnish and install MH H-4
(Hobas Base Tee with
Riser), complete as Lump
specified, without casting Sum 1 1.00 $24,000.00
313. Furnish and install MH H -5
(Hobas Base Tee with
Riser and Fabricated Bend,
complete as specified, Lump
without casting Sum 1 1.00 $27,000.00
314. Furnish and install MH H-6
(Hobas Base Tee with
Riser and Fabricated Bend,
complete as specified, Lump
without casting Sum 1 1.00 $28,000.00
315. Furnish and install MH H -7
(Hobas Tee with Riser),
complete as specified, Lump
without casting Sum 1 1.00 $24,000.00
316. Furnish and install MH H -8
(Hobas Tee with Riser),
complete as specified, Lump
without casting Sum 1 1.00 $24,000.00
317. Furnish and install MH H -9
(Hobas Tee with Riser and
Fabricated Bend),
complete as specified, Lump
without casting Sum 1 1.00 $29,000.00
318. Furnish and install MH H-
10, complete as specified, Lump
without casting Sum 1 1.00 $25,000.00
319. Furnish and install MH H-
11, complete as specified, Lump
without casting Sum 1 1.00 $36,000.00
320. Furnish and install MH N -1,
complete as specified, Lump
without casting Sum 1 1.00 $32,000.00
321. Furnish and install MH N-4,
complete as specified, Lump
without casting Sum 1 1.00 $25,000.00
322. Furnish and install MH N -5,
complete as specified, Lump
without casting Sum 1 1.00 $25,000.00
Page 5 of 11
CONTRACT: 08 -01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
323. Furnish and install MH N -6,
complete as specified, Lump
without casting Sum 1 1.00 $24,000.00
324. Furnish and install MH N -7,
complete as specified, Lump
without casting Sum 1 1.00 $25,000.00
325.
Furnish and install std.
sanitary manhole (4' inside
diameter) at 18 locations,
complete as specified, Vertical
without castings Feet 210 178.24 -31.76 $225.00 ($7,146.00)
326.
Furnish and install std.
sanitary manhole (5' inside
diameter) at 7 locations,
complete as specified, Vertical
without castings Feet 100 106.88 6.88 $400.00 $2,752.00
327. Furnish and install 4 "/6"
sanitary sewer lateral, Linear
complete as specified Feet 1,925 1,793.00 - 132.00 $30.00 ($3,960.00)
328.
Furnish and install cut in
wyes or "Insert-a- Tees" on
existing sanitary sewer,
complete as specified Each 16 14.00 -2.00 $500.00 ($1,000.00)
329. Furnish and install 24" X 6"
factory wyes, complete as
specified Each 24 23.00 -1.00 $2,000.00 ($2,000.00)
330. Furnish and install 15" X 6"
factory wyes, complete as
specified Each 25 22.00 -3.00 $750.00 ($2,250.00)
331. Furnish and install
connections of new
sanitary sewer to existing
main (Various sizes and
locations), complete as
specified Each 21 21.00 $3,000.00
332. Abandon existing sanitary
sewer as shown on plans
(Various sizes and
locations), complete as Lump
specified Sum 1 1.00 $15,000.00
333.
Furnish and install sanitary
sewer marker balls,
complete as specified Each 150 127.00 -23.00 $50.00 ($1,150.00)
334. Furnish and install rock
excavation, complete as Cubic
specified Yards 200 200.00 $100.00
335.
Core drill 4" sanitary lateral
in to MH H -5, connect with
a Kore "N" Seal connection,
complete as specified Each 1 1.00 $5,000.00
SECTION III - (BID ITEMS 300 - 335) - SUB - TOTALS $80,036.95 ($65,964.95)
ADDITIONAL WORK REQUIRED: C.O. # 3 - SECTION III
Page 6 of 11
CONTRACT: 08-01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
349 Furnish and install 8"
sanitary sewer drops,
complete as specified Each 15.36 15.66 0.30 $350.00 $105.00
350 Furnish and install 10"
sanitary sewer drops,
complete as specified Each 5.06 9.60 4.54 $415.00 $1,884.10
351 Furnish and install 12"
sanitary sewer drops,
complete as specified Each 28.66 29.35 0.69 $475.00 $327.75
352 Furnish and install 21"
sanitary sewer drops,
complete as specified Each 3.58 3.89 0.31 $1,000.00 $310.00
ADDITIONAL WORK: C. O. # 3 - (ITEMS 349 352) - SUB -TOTAL $2,626.85 $0.00
NET INCREASE TO: SECTION III $16,698.85
SECTION IV - WATER MAIN
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
400. Furnish and install 6"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 110 367.00 257.00 $30.00 $7,710.00
401. Furnish and install 8"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 300 314.00 14.00 $40.00 $560.00
402. Furnish and install 10"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
included) Feet 1,300 1,326.00 26.00 $50.00 $1,300.00
403. Fumish and install 1" water
service relay, complete as
specified, not including
corporation and stop box Linear
Feet 675 1,644.50 969.50 $35.00 $33,932.50
404. Furnish and install 1 Y"
water service, complete as
specified, not including
corporation and stop box Linear
Feet 60 0.00 -60.00 $40.00 ($2,400.00)
405. Furnish and install 2" water
service, complete as
specified not including Linear
corporation or stop box Feet 60 0.00 -60.00 $45.00 ($2,700.00)
Page 7 of 11
CONTRACT: 08-01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
406. Furnish and install 1"
corporation and stop box
with rod, complete as
specified Each 50 60.00 10.00 $400.00 $4,000.00
407. Furnish and install 1 '/2"
corporation and stop box
with rod, complete as
specified Each 2 0.00 -2.00 $700.00 ($1,400.00)
408. Furnish and install 2"
corporation and stop box
with rod, complete as
specified Each 2 0.00 -2.00 $1,000.00 ($2,000.00)
409. Furnish and install 6" gate
valve with box, complete as
specified Each 6 7.00 1.00 $1,300.00 $1,300.00
410. Furnish and install 8" gate
valve with box, complete as
specified Each 7 8.00 1.00 $1,600.00 $1,600.00
411. Furnish and install 10" gate
valve with box, complete as
specified Each 10 8.00 -2.00 $2,000.00 ($4,000.00)
412. Furnish and install 10" x
10" x4" tee, complete as
specified Each 1 0.00 -1.00 $500.00 ($500.00)
413. Furnish and install 10" x
10" x 6" tee, complete as
specified Each 5 7.00 2.00 $500.00 $1,000.00
414. Furnish and install 10" x
10" x 8" tee, complete as
specified Each 4 6.00 2.00 $500.00 $1,000.00
415. Furnish and install 8" x8" x
6" tee, complete as
specified Each 5 1.00 -4.00 $400.00 ($1,600.00)
416. Furnish and install 10" x 8"
cross, complete as
specified Each 2 2.00 $650.00
417. Furnish and install 10" x 8"
x 6" cross, complete as
specified Each 1 0.00 -1.00 $800.00 ($800.00)
418. Furnish and install 6" - 45
degree bends, complete as
specified Each 8 24.00 16.00 $250.00 $4,000.00
419. Furnish and install 8" - 45
degree bends, complete as
specified Each 8 17.00 9.00 $350.00 $3,150.00
420. Furnish and install 10" - 45
degree bends, complete as
specified Each 2 0.00 -2.00 $400.00 ($800.00)
421. Furnish and install
hydrants, complete as
specified Each 6 5.00 -1.00 $3,000.00 ($3,000.00)
422. Furnish and install 8" x 6"
reducer, complete as
specified Each 1 6.00 5.00 $300.00 $1,500.00
423. Furnish and install 8" cap,
complete as specified
Each 1 1.00 $250.00
424. Furnish and install 10" cap,
complete as specified
Each 1 2.00 1.00 $300.00 $300.00
Page 8 of 11
CONTRACT: 08 -01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
425. Fumish and install 4"
ductile iron water main
w /poly wrap, complete as
specified, not including Linear
fittings Feet 5 4.00 -1.00 $35.00 ($35.00)
426. Furnish and install
connections of new water
main to existing water main
(various sizes and
locations), complete as
specified Each 11 13.00 2.00 $1,000.00 $2,000.00
427. Furnish and install 2"
insulation, complete as Square
specified Feet 800 0.00 - 800.00 $3.00 ($2,400.00)
428. Abandon water main on
New York Avenue
(Canadian National railroad
tracks to Jefferson Street),
complete as specified Lump
Sum 1 1.00 $9,000.00
SECTION IV - (BID ITEMS 400 - 428) - SUB - TOTALS $63,352.50 ($21,635.00)
ADDITIONAL WORK REQUIRED: C.O. # 3 - SECTION IV
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
432 Furnish and install
6" - 22 1/2 degree bend,
complete as specified Each 2.00 3.00 1.00 $250.00 $250.00
ADDITIONAL WORK: C.O. # 3 (ITEMS 432) - SUB -TOTAL $250.00 $0.00
NET INCREASE TO: SECTION IV $41,967.50
SECTION V - WORK UNIT B - STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
501 Furnish and install 10"
Storm Sewer, complete as Linear
specified Feet 7 12.50 5.50 $24.00 $132.00
502 Furnish and install 12"
Storm Sewer, complete as Linear
specified Feet 527 527.60 0.60 $25.00 $15.00
503 Furnish and install 15"
Storm Sewer, complete as Linear
specified Feet 113 156.70 43.70 $27.00 $1,179.90
504 Furnish and install 30" RCP
Class III Storm Sewer,
complete as specified Linear
Feet 309 318.71 9.71 $46.00 $446.66
Page 9 of 11
CONTRACT: 08 -01 CHANGE ORDER # 3
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
505 Furnish and install 14" x23"
HERCP Class HE -III Storm
Sewer, complete as Linear
specified Feet 10 0.00 -10.00 $50.00 ($500.00)
506 Furnish and install 19" x30"
HERCP Class HE -III Storm
Sewer, complete as Linear
specified Feet 10 0.00 -10.00 $60.00 ($600.00)
507 Furnish and install 24" x38"
HERCP Class HE -III Storm
Sewer, complete as Linear
specified Feet 32 27.10 -4.90 $70.00 ($343.00)
508 Furnish and install 29" x45"
HERCP Class HE -III Storm
Sewer, complete as Linear
specified Feet 62.5 31.13 -31.37 $100.00 ($3,137.00)
509 Furnish and install 38" x
60" HERCP Class HE -III
Storm Sewer, complete as Linear
specified Feet 320 320.50 0.50 $130.00 $65.00
510 Furnish and install 48" x
76" HERCP Class HE -III
Storm Sewer, complete as
specified, per linear foot Linear
Feet 532 524.63 -7.37 $180.00 ($1,326.60)
511 Furnish and install std.
Storm Manhole (4' Inside
Diameter) in two (2)
locations, without casting,
complete as specified Vertical
Feet 10.34 10.05 -0.29 $600.00 ($174.00)
512 Furnish and install std.
Storm Manhole (5' Inside
Diameter) in three (3)
locations, without casting,
complete as specified Vertical
Feet 17.47 17.17 -0.30 $700.00 ($210.00)
513 Furnish and install std.
Storm Manhole (6' Inside
Diameter) in three (3)
locations, without casting,
complete as specified Vertical
Feet 16.39 16.02 -0.37 $800.00 ($296.00)
514 Furnish and install Std.
Inlet (Type 3 with 18"
sump) with castings,
complete as specified Each 24 24.00 $1,200.00
515 Furnish and install
materials to construct
Junction Chamber No.7,
without casting, complete Lump
as specified Sum 1 1.00 $30,000.00
516 Furnish and install
materials to construct
Junction Chamber No. 5,
without casting, complete Lump
as specified Sum 1 1.00 $30,000.00
Page 10 of 11
CONTRACT: 08 -01 CHANGE ORDER # 3
CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
517 Furnish and install
materials to construct
Junction Chamber No.2,
without casting, complete Lump
as specified Sum 1 1.00 $30,000.00
518 Furnish and install
materials to construct
Junction Chamber No.1,
without casting, complete Lump
as specified Sum 1 1.00 $38,000.00
519 Furnish and install 6" Storm
Lateral, complete as Linear
specified Feet 830 914.00 84.00 $30.00 $2,520.00
520 Furnish and install storm
lateral marker balls,
complete as specified Each 61 61.00 $50.00
521 Abandon 8" - 12" Storm
Sewer, completed as Linear
specified Feet 334 369.00 35.00 $10.00 $350.00
522 Abandon 15" Storm Sewer
and larger, completed as Linear
specified Feet 215 300.00 85.00 $15.00 $1,275.00
523 Abandon existing catch
basins and manholes,
complete as specified Each 10 63.00 53.00 $500.00 $26,500.00
SECTION V - (BID ITEMS 500 - 523) - SUB - TOTALS $32,483.56 ($6,586.60)
NET INCREASE TO: SECTION V $25,896.96
NET INCREASE TO SECTIONS 1, 11, 111, IV, V $268,128.46
NET DECREASE TO SECTIONS I, 11, 111, IV, V ($249,729.03)
NET DECREASE TO CONTRACT: $18,399.43
Page 11 of 11
City of Oshkosh
Department of Public Works
215 Church Avenue
P.O. Box 1130
Oshkosh, Wisconsin
54903 -1130
(920) 236 -5065
IP)
OJHKOIH
ON THE WATER
August 11, 2010
Mr. Mark Hinsz
S.J. Louis Construction, Inc.
1351 W. Broadway Street
P.O. Box 459
Rockville, MN 56369
Re: Change Order #3 /Contract 08 -01
Dear Mr. Hinsz:
Enclosed please find an executed copy of the Change Order between the City of Oshkosh and S.J.
Louis Construction, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
,aj(, C . /4.d / David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, City Attorney (w /copy)
File Copy (w /original)