HomeMy WebLinkAboutPW CNT 09-10/CNG 2 4M. L \
STRAND JUL 2 9 2010
ASSOCIATES, INC.'
ENGINEERS
Transmittal Letter C CLERK O$ FIC`
910 West Wingra Drive To City of Oshkosh
Madison, WI 53715
Phone: 608- 251 -4843
Fax: 608 - 251 -8655
Office Locations
Madison, WI
Joliet, IL Date: June 7, 2010 Project No.: 1382.034
Lexington, KY
Louisville, KY Attention: Steve Brand
Mobile, AL RE: Oshkosh Wastewater Utility Heating and Ventilation Improvements
Columbus, IN
Columbus, OH
Indianapolis, IN
Milwaukee, WI
Cincinnati, OH WE ARE SENDING YOU: ® Attached ❑ Under Separate Cover
Phoenix, AZ
www.strand.com ❑ Shop Drawings ❑ Change Order ❑ Copy of Letter
❑ Specifications ❑ Drawings ❑ Samples
® Other: Change Order No. 2_
Copies Date No. Description
3 Change Order No. 2
THESE ARE TRANSMITTED as checked below:
® For approval ❑ Approved as submitted ❑ Resubmit copies for approval
® For your use ❑ Approved as noted ❑ Submit copies for distribution
❑ As requested ❑ Returned for corrections ❑ Return corrected prints
❑ For review and comment ❑ Other
Remarks:
Please have all appropriate parties sign the three copies of the Change Order and return
two copies to us. Contact me with any questions.
7- 7.5 20l0 9ffo ' �,d �tti - f - wo
Copy to: �- (� Signed:^�-
- -°�"`` rc��C Matthew Merten
U21.,,L6
S: \MAD1 1300-- 13991138210341Wrd \Construction Services Contract\Constructieri Documents \TFansfiittal Lett Change Order No. 2 (REV)City of Oshkosh.doc
CaviVa,c1 o 7 - !a Fc (1A/Hi. `ts>o
f
STRAND
ASSOCIATES, INC.'
E E J G I N E E A S
910 West Wingra Drive
Madison, WI 53715 May 27, 2010
Phone: 608-251-4843
Fax: 608-251-8655
Office Locations
CHANGE ORDER NO. 2
Madison, WI
Joliet, IL
Louisville, KY PROJECT: Wastewater Utility Heating and Ventilation Improvements
Lexington, KY OWNER: City of Oshkosh
Mobile, AL
Columbus, IN CONTRACT: 09 -10
Columbus, OH CONTRACTOR: B &P Mechanical, Inc.
Indianapolis, IN
Milwaukee, WI
Cincinnati, OH
Phoenix, AZ Description of Change
www.strand.com
2a Owner's cost to have sheave installed on the DEDUCT ($1,165.00)
blower motor and the burner modified for
MAU -1 at Broad Street Lift Station so the
makeup air unit would operate according to
the Contract Documents.
2b Owner's cost to balance the blower motor DEDUCT ($ 339.00)
sheave for RTU -1 at the Headworks Building
to resolve the unit's vibration issue.
TOTAL VALUE OF THIS CHANGE ORDER: DEDUCT ($1,504.00)
Contract Price Adjustment
Original Contract Price $319,000.00
Previous Change Order Adjustments $ 9,044.00
Adjustment in Contract Price this Change Order ($ 1,504.00)
Current Contract Price including this Change Order $326,540.00
Contract Completion Date Adjustment
Original Contract Completion Date January 29, 2010
Contract Completion Date Adjustments due to None
previous Change Orders
Contract Completion Date Adjustments due to this None
Change Order
Current Contract Completion Dates including all January 29, 2010
Change Orders
MI City of Oshkosh -B &P Mechanical, Inc.
Contract No. 09 -10, Change Order No. 2
STRAND Page 2
ASSOCIATES, INC."
ENGINEERS May27,2010
This document shall become a supplement to the Contract and all provisions will apply
hereto.
RECOMMENDED
/l« - !1i.. 5/21/ to
ENGINEER - Strand Associates, Inc. Date
APPRO)D ,
/iv," i ,,,,, s`7d'i 0
CONTRACTOR -B &P Mechanical, Inc. Date
RECOMMENDED BY OWNER
�0.,.d G. P4-14- 7- 19 -2oio
Director of Public Works Date
APPROVED
/,,-- Ac eird-lid 7// f /?' "
Mark A. Rohloff -City Manager. Date
<v
. - t I to* 7/1c0 ( o
Pamela R. Ubrig -City Clerk Date
I certify that provision has been made to pay - the liability
that will accrue to the City of Oshkosh, Wisconsin, under
this ange Order
-7 /7 ,2 0//0
Peggy t- director of Finance Date
APP 'OVEDASTOFS M
� 4 D �• • 1 akk QJ J \'`-�
' - n L s renson -City Atto ey Date
MJM:Ir\R. \MAD'Documents\ Specifications \Archive'2009 \Oshkosh, WI 09- I0.1382.034.mjm \Change Orders \CO 2.docx