January 20, 2010
Mr. Leroy Fischer
Fischer -Ulman Construction, Inc.
1115 S. Theodore Street
Appleton, WI 54915
Re: Change Order #2 /Contract 09 -06
Dear Mr. Fischer:
Enclosed please find an executed copy of the Change Order #2 between the City of Oshkosh and
Fischer -Ulman Construction, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
J«�.,1 C.
David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, City Attorney (w /copy)
File Copy (w /original)
CHANGE ORDER # 2
DATED: December 30, 2009
TO: FISCHER -ULMAN CONSTRUCTION
1115 S. THEODORE STREET
APPLETON, WI 54915
Your present contract with the City of Oshkosh, Contract No. 09 -06 , is hereby amended
and changed as follows:
NET INCREASE TO CONTRACT: $73,360.74
CITY OF OSHKOSH �
BY:_i
Recommended: City Manager I ,
c-. &L. •
Director of Public Works City Clerk
Approved and accepted:
E r
/ Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
/24
-cam
omp roller
Approved as to form:
C , L41
City Att. - ,
CONTRACT: 09 -06 CHANGE ORDER # 2
CONCRETE SIDEWALK (New and Reconstruction)
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Sidewalk removal &
driveway removal, Square
complete as specified Feet 95,520.00 106,019.38 10,499.38 0.33 3,464.80
2 Concrete /asphalt sawing, Linear
complete as specified Feet 4,750.00 4,826.20 76.20 2.00 152.40
3 Construct 4" thick concrete
sidewalk in various
locations in the City of
Oshkosh, complete as Square
specified Feet 92,500.00 97,452.64 4,952.64 2.72 13,471.18
4 Construct 6" thick concrete
sidewalk in various
locations in the City of
Oshkosh, complete as Square
specified Feet 18,000.00 17,890.10 - 109.90 3.08 ($338.49)
5 Construct 7" thick
crosswalk areas, complete Square
as specified Feet 5,000.00 3,006.77 - 1,993.23 3.28 ($6,537.79)
6 Provide and install metal
detectable warning plates,
complete as specified Square
Feet 272.00 248.00 -24.00 28.00 ($672.00)
7 Three (3 ") inch asphalt
replacement, complete as Square
specified Feet 2,000.00 2,313.35 313.35 3.70 1,159.40
8 Curb and gutter removal, Linear
complete as specified Feet 425.00 442.60 17.60 3.50 61.60
9 Construct 30" curb and
gutter, complete as Linear
specified Feet 425.00 442.60 17.60 16.80 295.68
10 Terrace restoration,
including seed, fertilizer,
and mulch, complete as Square
specified Yards 1,000.00 3,618.66 2,618.66 3.90 10,212.77
11 Furnish and install
pavement ties, complete as
specified Each 125.00 51.00 -74.00 7.00 ($518.00)
12 Construct 4" thick concrete
sidewalk in Water Dept.
repair locations as approx.
60 sites, complete as Square
specified Feet 2,500.00 2,141.85 - 358.15 4.10 ($1,468.42)
13 Construct 6" thick concrete
sidewalk in Water Dept.
repair locations at approx.
20 sites, complete as Square
specified Feet 1,500.00 630.93 - 869.07 4.26 ($3,702.24)
14 7" non - reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 100.00 126.01 26.01 39.00 1,014.39
Page 1 of 5
CONTRACT: 09 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
15 8" non - reinforced concrete
pavement removal and
replacement, including
sawing, pavement ties,
integral curb & grading,
terrace & traffic control,
complete as specified Square
Yards 1,500.00 311.37 - 1,188.63 39.00 ($46,356.57)
16 8" special High Early
Strength, non - reinforced
concrete pavement
removal and replacement,
including sawing,
pavement ties, integral
curb and grading, terracing
and traffic control, Square
complete as specified Yards 175.00 8.00 - 167.00 46.50 ($7,765.50)
17 Extra crushed stone base,
complete as specified Tons 250.00 79.20 - 170.80 14.00 ($2,391.20)
18 No. 4 epoxy- coated
reinforced rods, installed Linear
as specified Feet 300.00 260.00 -40.00 1.50 ($60.00)
19 Furnish, install, and
maintain Type "C" inlet
protection, complete as
specified Each 15.00 0.00 -15.00 40.00 ($600.00)
20 Furnish, install, and
maintain Type "D" inlet
protection, complete as
specified Each 5.00 41.00 36.00 40.00 1,440.00
21 Construct 12" wide radius
curb head, complete as Linear
specified Feet 175.00 113.50 -61.50 3.50 ($215.25)
22 Furnish, install, and
maintain erosion mat, Square
complete as specified Yards 600.00 70.60 - 529.40 1.75 ($926.45)
23 Profile sawcut concrete Linear
curb, complete as specified Feet 60.00 37.40 -22.60 40.00 ($904.00)
SUB -TOTAL CONCRETE SIDEWALK (NEW & RECONSTRUCTION) 31,272.22 ($72,455.91)
CHANGES TO CHANGE ORDER #1
ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT
CONCRETE PAVING
ITEM C/O #1 INSTALLED NET NET COST PER INCREASE 1N DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
1 Pavement removal Square
Yards 453.30 442.80 -10.50 7.00 ($73.50)
2 Sidewalk & driveway Square
removal Feet 10,141.00 11,565.20 1,424.20 0.33 469.99
3 8" Concrete pavement with
integral curb, 6" base & Square
grading Yards _ 1,034.40 881.90 - 152.50 39.00 ($5,947.50)
Page 2 of 5
CONTRACT: 09 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
4 12" Radius curb head Linear
Feet 113.40 123.20 9.80 3.50 34.30
5 4" Concrete sidewalk Square
Feet 5,188.50 7,542.20 2,353.70 2.72 6,402.06
6 6" Concrete sidewalk Square
Feet 2,592.00 1,364.90 - 1,227.10 3.08 ($3,779.47)
7 Adjust manholes & inlets Each 13.00 15.00 2.00 125.00 250.00
8 No. 4 reinforcing bars Linear
(epoxy coated) Feet 240.00 540.00 300.00 1.50 450.00
9 Detectable warning field Square
Feet 48.00 56.00 8.00 28.00 224.00
10 Terrace work Square
Yards 922.40 744.60 - 177.80 3.90 ($693.42)
CHANGE TO ADDITIONAL ITEMS - CONCRETE PAVING - SUB - TOTALS 7,830.35 ($10,493.89)
CHANGES TO CHANGE ORDER #1
ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT
STORM SEWER
ITEM C/O #1 INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
11 12" Storm sewer Linear
Feet 159.00 157.80 -1.20 49.50 ($59.40)
12 Inlets (type 3 with 18"
sum. with castings Each 8.00 8.00 1,650.00
13 Rebuild storm manhole in
one location Each 2.50 6.86 4.36 1,375.00 5,995.00
14 Std. storm manhole in one
location (5' ID) Each 4.46 3.47 -0.99 550.00 ($544.50)
15 Abandon inlets or
manholes Each 5.00 5.00 385.00
16 Furnish, install, & maintain
type D inlet protection Each 17.00 6.00 -11.00 110.00 ($1,210.00)
17 Connect to ex storm
manhole Each 5.00 5.00 165.00
CHANGE TO ADDITIONAL ITEMS - STORM SEWER - SUB - TOTALS 5,995.00 ($1,813.90)
ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT - CIO #2
CONCRETE PAVING
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
18 Abandon two concrete
vaults on W. 8th Avenue, Lump
complete as specified Sum 0.00 1.00 1.00 1,845.00 1,845.00
19 Concrete sawing, complete Linear
as specified Feet 0.00 49.10 49.10 2.00 98.20
Page 3 of 5
CONTRACT: 09 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
20 8" Special High Early
Strength non - reinforced
concrete pavement
removal & replacement,
including sawing,
pavement ties, integral
curb and grading, terracing
and traffic control, Square
complete as specified Yards 0.00 40.50 40.50 46.50 1,883.25
21 Extra crushed stone base,
complete as specified Tons 0.00 250.00 250.00 14.00 3,500.00
22 8"/7-bag non - reinforced
concrete removal and
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing and traffic control, Square
complete as specified Yards 0.00 250.70 250.70 45.12 11,311.58
23 8" Concrete sidewalk, Square
complete as specified Feet 0.00 56.00 56.00 4.77 267.12
ADDITIONAL ITEMS - CONCRETE PAVING - SUB - TOTALS 18,905.15 $0.00
ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT - CIO #2
STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
24 6 Hours to relocate inlets
on W. 9th Avenue and
Nebraska Street Each 0.00 6.00 6.00 300.00 1,800.00
ADDITIONAL ITEMS - STORM SEWER - SUB - TOTALS 1,800.00 $0.00
CONCRETE SIDEWALK (New and Reconstruction)
ADDITIONAL ITEMS
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
25 7"17-Bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 72.51 72.51 44.55 3,230.32
Page 4 of 5
CONTRACT: 09 -06 CHANGE ORDER # 2
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
26 8 "/7 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 1,146.08 1,146.08 45.12 51,711.13
27 8 "/8 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 276.17 276.17 45.92 12,681.73
28 9 "17 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 164.52 164.52 54.75 9,007.47
29 9 "/8 -bag non - reinforced
concrete removal &
replacement, including
sawing, pavement ties,
integral curb & grading,
terracing & traffic control, Square
complete as specified Yards 0.00 92.25 92.25 59.85 5,521.16
30 8" curb, complete as Linear
specified Feet 0.00 63.00 63.00 5.17 325.71
31 8" sidewalk, complete as Square
specified Feet 0.00 1,560.00 1,560.00 4.77 7,441.20
32 Move shed at 3098
Jackson Street, complete Lump
as specified Sum 0.00 1.00 1.00 80.00 80.00
33 Remove trees, brush, and
stumps at 3098 Jackson
Street, complete as Lump
specified Sum 0.00 1.00 1.00 875.00 875.00
34 Remove two trees at 51
Fernau Avenue, complete Lump
as specified Sum 0.00 1.00 1.00 120.00 120.00
35 Remove 56 ft. of .5' curb at
2920 N. Main Street, Linear
complete as specified Feet 0.00 56.00 56.00 3.50 196.00
36 Replace 21 ft. of .5' curb at
2920 N. Main Street, Linear
complete as specified Feet 0.00 21.00 21.00 12.00 252.00
37 Grade fill under sidewalk at
miscellaneous locations, Lump
complete as specified Sum 0.00 1.00 1.00 880.00 880.00
ADDITIONAL ITEMS - CONCRETE SIDEWALK 92,321.72 $0.00
158,124.44 ($84,763.70)
NET INCREASE TO CONTRACT 09 -06: 73,360.74
Page 5 of 5