Re: Change Order #1 /Contract 09 -20
Dear Mr. Kalupa:
Enclosed please find an executed copy of the Change Order between the City of Oshkosh and Four -
Way Construction of WI, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
Qom) C. ( 7 ° .a.
David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original)
Lynn Lorenson, City Attorney (w /copy)
File Copy (w /original)
CHANGE ORDER # 1
DATED: October 30, 2009
TO: Four -Way Construction Co. of WI, Inc.
P. O. Box 133
Berlin, WI 54923
Your present contract with the City of Oshkosh, Contract No. 09 -20 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING ($353.04)
NET DECREASE TO: SECTION II - STORM SEWER ($401.00)
NET DECREASE TO CONTRACT: ($754.04)
CITY OF OSHKOSH
BY: a---- i odi
Recommended: City Manager ■
bovvei C., -pa ii• a, Li. ..
Director of Public Works City Clerk
Approved d acce•ted:
.., 7
Coh ra tor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
e-ei !J gt mptroller
Approved as to form
1: —\, ,
.1
4 IA �� 1r ' — ` ? ;. `s
4
y y
_ - '' it A": ney � � ? �; `, ` NOV 1 9 2 009 § �, ` � _
I
Fo/g o-
! � a
CONTRACT: 09 -20 CHANGE ORDER # 1
SECTION 1- CONCRETE PAVING
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
100 Pavement removal, Square
complete as specified Yards 64 33.70 -30.30 $4.65 ($140.89)
101 Sidewalk removal, Square
complete as specified Feet 112 404.65 292.65 $1.00 $292.65
102 Concrete pavement,
including curb and grading,
complete as specified Square
Feet 438 180.60 - 257.40 $10.00 ($2,574.00)
103 Asphalt pavement,
including grading, complete Square
as specified Feet 138 122.00 -16.00 $8.45 ($135.20)
104 4" concrete sidewalk, Square
complete as specified Feet 112 404.65 292.65 $8.00 $2,341.20
105 Sawing, complete as Linear
specified Feet 215 160.28 -54.72 $2.50 ($136.80)
106 Terrace work at 1220
Greenfield Trail, complete Lump
as specified Sum 1 0.00 -1.00 $200.00 ($200.00)
107 Terrace work at 1242
Liberty Street, complete as Lump
specified Sum 1 1.00 $150.00
108 Terrace work at 1516
Menominee Drive, Lump
complete as specified Sum 1 1.00 $300.00
109 Terrace work at 2205
Allerton Drive, complete as Lump
specified Sum 1 1.00 $200.00
110 Terrace work at 1906
Doemel Street, complete Lump
as specified Sum 1 1.00 $150.00
111 Terrace work at 1633
through 1719 Doemel
Street, complete as Lump
specified Sum 1 1.00 $1,020.00
112 Terrace work at 1815 East
Murdock Avenue and 1790
Cliffview Drive, complete Lump
as specified Sum 1 1.00 $850.00
113 Terrace work at 1511
Coolidge Avenue, complete Lump
as specified Sum 1 1.00 $175.00
114 Terrace work and
restoration for storm sewer
easement at 539 West
17th Avenue, complete as Lump
specified Sum 1 1.00 $300.00
115 Terrace work at 151 West
Fernau Avenue, complete Lump
as specified Sum 1 1.00 $210.00
SECTION 1- (BID ITEMS 100 - 115) - SUB - TOTALS $2,633.85 ($3,186.89)
Page 1 of 3
CONTRACT: 09 -20 CHANGE ORDER # 1
INCREASE IN DECREASE IN
ITEM CONTRACT INSTALLED NET NET COST PER
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
116 Terrace work at 1285
Heritage Trail, complete as Lump
specified Sum 1.00 1.00 $200.00 $200.00
ADDITIONAL WORK: C.O. # 1 - (ITEM 116) - SUB -TOTAL $200.00 $0.00
NET DECREASE TO: SECTION I ($353.04)
SECTION II - STORM SEWER
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
200. Furnish and install 6" storm
sewer, complete as Linear
specified Feet 380 399.00 19.00 $26.95 $512.05
201. Furnish and install 12"
storm sewer, complete as Linear
specified Feet 56 42.00 - 14.00 $46.60 ($652.40)
202. Furnish and install std.
inlets (Type 1 with no
sump) with castings,
complete as specified Each 1 1.00 $985.00
203. Furnish and install std.
storm manhole (4' inside
diameter) in 1 (one)
location without casting, Vertical
complete as specified Feet 3.53 3.96 0.43 $354.00 $152.22
204. Furnish and install 6" storm
lateral, complete as Linear
specified Feet 208 195.50 -12.50 $52.95 ($661.87)
205. Furnish and install storm
lateral marker balls,
complete as specified Each 28 29.00 1.00 $20.00 $20.00
206. Furnish, install, and
maintain Type "D" inlet
protection std., complete
as specified Each 26 24.00 -2.00 $85.00 ($170.00)
207. Connection to existing
storm sewer Each 5 3.00 -2.00 $85.00 ($170.00)
208. Tap existing storm inlet,
complete as specified Each 5 7.00 2.00 $85.00_ $170.00
SECTION II - (BID ITEMS 200 - 208) - SUB - TOTALS $854.27 ($1,654.27)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION II
Page 2 of 3
CONTRACT: 09 -20 CHANGE ORDER # 1
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT
PRICE PRICE
209 Frost sleeves for
clean -outs Each 7.00 7.00 $57.00 $399.00
ADDITIONAL WORK: C.O. # 1 - (ITEM 209) - SUB -TOTAL $399.00 $0.00
NET DECREASE TO: SECTION II ($401.00)
NET INCREASE TO SECTIONS I, II $4,087.12
NET DECREASE TO SECTIONS I, II ($4,841.16)
NET DECREASE TO CONTRACT: ($754.04)
Page 3 of 3
CHANGE ORDER # 3
DATED: October 22, 2009
TO: Four -Way Construction of WI Inc.
P 0 Box 133
Berlin, WI 54923
Your present contract with the City of Oshkosh, Contract No. 09 -05 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION IV - WATER MAIN $6,310.00
NET INCREASE TO CONTRACT: $6,310.00
CITY OF OSHKOSH
BY:
Recommended: City Manage
-bd I _ 'yI
Director of Publi Works City Clerk
Approved an. accepted:
Co 'tra or
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Pze
Ap• .ved as to form
A 77-7
A,. • A 1111111111111.4 . 17,E t
City Attorne L
� b
� � NOV 1 9 2009
E '(
3{ 'tee' r < + .`. -•. -'•4"° }' '� M i
CONTRACT: 09-05 CHANGE ORDER # 3
SECTION IV - WATER MAIN
ADDITIONAL WORK REQUIRED: C.O. # 3 - SECTION IV
ITEM CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT
PRICE PRICE
CHANGE S TO ITEM 429 FROM CHANGE ORDER #2
429 Abandon water valve
Changes manhole, complete as
from specified
Co #2 Each 1.00 1.00 $4,700.00 $4,700.00
ADDITIONAL WORK REQUIRED: ITEM # 431
431 Labor and equipment to
install city supplied 16"
gate valve on Marine Drive,
per invoice dated 10/21/09,
complete as specified
Each 1.00 1.00 _ $1,610.00 $1,610.00
ADDITIONAL WORK: C.O. # 3 (ITEMS 429 & 431) - SUB - TOTAL $6,310.00 $0.00
NET INCREASE TO: SECTION IV $6,310.00
NET INCREASE TO CONTRACT: $6,310.00