December 16, 2009
Mr. Bradley Lake
Strand Associates, Inc.
910 W. Wingra Drive
Madison, WI 53715
Re: Change Order #2 /Contract 08 -03
Dear Mr. Lake:
2
Enclosed please find an exe ut copy of the Change Order between the City of Oshkosh and Strand
Associates, Inc. regarding the above - mentioned project.
If you have any questions, please call our office at (920) 236 -5065. Thank you.
Sincerely,
4i'd /Stek
David C. Patek
Director of Public Works
DCP /clm
Enclosure
cc: Pam Ubrig, City Clerk (w /original) \ � \\\
Lynn Lorenson, City Attorney (w /original) "
.
File Copy (w /original) t�� 000
G)I
Sa
STRAND
ASSOCIATES. INC."
E N G I N E E R S
September 18, 2009
910 West Wingra Drive
Madison, WI 53715
Phone: 608- 251 -4843 CHANGE ORDER NO. 2 (FINAL)
Fax: 608-251-8655
Office Locations PROJECT: Headworks and Stormwater Control Improvements Project
Madison, WI OWNER: City of Oshkosh, Wisconsin
Joliet, IL CONTRACT: 08 -03
Louisville, KY
Lexington, KY CONTRACTOR: J.F. Ahern Co.
Mobile, AL
Columbus, IN
Columbus, OH
Indianapolis, IN Description of Change
Milwaukee, WI
Cincinnati, OH 2a Credit for the Unsuitable Foundation Material for DEDUCT ($600.00)
Phoenix, AZ Structures and Roads Allowance (Section 02222,
paragraph 1.01.C) that was unused during
www.strand.com construction (40 cubic yards at $15.00 per cubic
yard).
2b Additional cost to excavate additional material from ADD $1,959.00
the drive area where liquid chemical loads are
received. See attached J.F. Ahern summary letter
dated March 2, 2009.
2c Credit for eliminating the preparation and painting DEDUCT ($424.00)
of the steel components of the three existing IDI
mechanical bar screens. See attached J.F. Ahern
summary letter dated June 17, 2009.
2d Credit for eliminating the relocation of the 2 inch DEDUCT ($306.16)
sodium bisulfate vent line which was completed by
City staff. See attached J.F. Ahern e -mail dated
September 1, 2009.
2e Credit for one -half of the cost associated with DEDUCT ($1,100.00)
replacement of the slide gate stem (upstream of the
north mechanical bar screen) which was found to be
inoperable during construction.
TOTAL VALUE OF THIS CHANGE ORDER DEDUCT ($471.16)
Contract Price Adjustment
Original Contract Price $465,600.00
Previous Change Order Adjustments $7,829.00
Adjustment in Contract Price this Change Order ($471.16)
Current Contract Price including this Change Order $472,957.84
Contract Completion Date Adjustment
Original Contract Completion Date March 31, 2009
Contract Completion Date Adjustments due to previous Change
Orders None
Sai City of Oshkosh, Wisconsin —J.F. Ahern, Co.
STRAND Contract 08 -03, Change Order No. 2 (Final)
ASSOCIATES, INCA' Page 2
E N G I N E E R S
September 18, 2009
Contract Completion Date Adjustments due to this Change Order None
Current Contract Completion Dates including all Change Orders March 31, 2009
This document shall become a supplement to the Contract and all provisions will apply
hereto.
RE dr 1ED Agir
EN . EER —Str ik A elates, Inc. Date
APPROVED
��= q z'/y'
CONTRACTOR —J.F. Ahern Co. Dat'e
APPROVED
tee Ct'� ex stet
OWNER —City of Oshkosh Date
I3li,:mro ^NAL' ;1300- 1399`,I3821037\Wrd`Change Orders CO 2 . WIP doc
Sa,
City of Oshkosh, Wisconsin -J.F. Ahern, Co.
STRAND Contract 08 -03, Change Order No. 2 (Final)
ASSOCIATES. INC., Page 3
E N G I N E E R S September 18, 2009
RECOMMENDED BY OWNER
Director of Public Works Date
APPROVED BY OWNER
/?16- /.. - //a /4 9
City anager Date
`
b iii :.r
JIL , i.`.11-- ( )- ( 2
City Clerk ® Date
I certify that provision has been made to pay the liability
that will accrue to the City of Oshkosh, Wisconsin, under
this Change Order.
/4 Ye,,,,e, A-2/,/,)
City Compt 1 r Date
AP 'aOVED AS T I ORM
.. is I • . 4 ' ' 14-2-4i46.1:te /41 ( LC /0 9
City • /Assistant City Attorney Date
WC mro1S: MAD\ 1300- -1399' 1382 \ 037 \ W rd\Change Orders \CO 2. W IP. doc
855 Morris Street
P.O. Box 1316
J . F. A IhERN CO. Fo nd du L.c . 54936 -1316
MEchANicAL & FiRE P pf: -.. p . 4 929-8825
OTECTION CONTRACTORS �, • hern.com
HERN
March 2, 2009
Ph: (608) 251 -4843
Fx : (608) 251 -8655
Mr. Bradley Lake
Strand Associates, Inc.
910 West Wingra Drive
Madison, WI 53715
RE: Oshkosh Headworks
J. F. AHERN CO. JOB #: 211896
CUSTOMER CONTRACT #: 08 -03
ADDITIONAL EXCAVATIION WORK
Dear Bradley:
Cost to excavate additional material from drive area on west side.
Respond by: 04/01/2009
ONE THOUSAND NINE HUNDRED FIFTY - NINE AND 00 /100 DOLLARS $1,959.00
This proposal only covers the direct costs of labor, materials and equipment to execute the changed work
described in the proposal.
At the present time, we cannot assess or evaluate the overall impact of the changed work on our original
scope of work.
We thereby reserve our rights to claim for any indirect costs which may arise in the future as a result of
delays to the work, out of sequence work, inefficiencies, extended contract completion, labor and material
escalation and / or acceleration and extended warranties.
Sincerely,
J . AHERN CO
16"4
'"Pfl/Q (A) PETER WACHS
PROJECT MANAGER
WATER/WASTEWATER DEPT.
Enclosures fl E C ,. E 0 W
E
File: 211896 3 - 0
I MAR - 6 2
STRA,' ,`.;.A I ES,1NC.
MADISON, WI
Building the Midwest Since 1880
Change Order Summary
HERN
Project: Oshkosh Headworks
Project #: 211896
Proposal Date: 03/02/2009
Change Order #: 3
Revision: 0
Description of Work: Additional excavatiion work
Total CO Amount: $1959.00
Unit of Unit Price
Item Description Calc Type Quantity Measure or Rate PCT % Total Amount
Subtotal Subcontracts Lump Sum Lump Sum $1847.22 $1847.22
TOTAL S - Subcontract $1847
Overhead & Profit - Subcontractor Percent 1847.22 5.00 $92.36
TOTAL 0 - Overhead & Profit $
Bond and Insurance Percent 1940.00 1.00 $19.40
TOTAL B - Bond & Insurance $19
Grand Total: $19591
This proposal only covers the direct costs of labor, materials and equipment to
execute the changed work described in the proposal.
At the present time, we cannot assess or evaluate the overall impact of the
changed work on our original scope of work.
We thereby reserve our rights to claim for any indirect costs which may arise
in the future as a result of delays to the work, out of sequence work,
inefficiencies, extended contract completion, labor and material escalation and
/ or acceleration and extended warranties.
Page 1 of 1
,/ �i
OV SINCE 1875
IA B UILDING THE FUTURE
OF COMMUNITIES & BUSINESS
November 13, 2008
Pete Wachs
JF Ahern
Fond du lac, WI
Re: Oshkosh WWTP
Pete
This is the cost for extra excavation for the drive area to the west. We over excavated a
total of 106 cu yds.
73 cu. yds. @ $ 25.00 our unit price = $1,847.22
Sincerely
Richard Paulsen
President
855 Morris Street
P.O. Box 1316
1 F. AhERN CO. C- " "' • WI 54936 -1316
MEChANICAL & FIRE P . 1 • - -' / Fx (920)929 -8825
PROTECTION CONTRACTORS www.jfahern.com
HERN
June 17, 2009
Ph: (608) 251 -4843
Fx : (608) 251 -8655
Mr. Bradley Lake
Strand Associates, Inc.
910 West Wingra Drive
Madison, WI 53715
RE: Oshkosh Headworks
J. F. AHERN CO. JOB #: 211896
CUSTOMER CONTRACT #: 08 -03
6 STEEL MEMBERS PAINTING
Dear Bradley:
Deduct to not paint 6 steel members @ existing screens.
Respond by: 07/17/2009
FOUR HUNDRED TWENTY -FOUR AND 00 /100 DOLLARS ($424.00)
This proposal only covers the direct costs of labor, materials and equipment to execute the changed work
described in the proposal.
At the present time, we cannot assess or evaluate the overall impact of the changed work on our original
scope of work.
We thereby reserve our rights to claim for any indirect costs which may arise in the future as a result of
delays to the work, out of sequence work, inefficiencies, extended contract completion, labor and material
escalation and / or acceleration and extended warranties.
Sincerely,
J. F. AHERN CO
p
PETER WACHS
PROJECT MANAGER
WATER/WASTEWATER DEPT.
Enclosures @ -
File: 211896 4 - 0 D _
JUN 1 8 2009
STRA " i LS, INC
Building the Midwest Since 1880 MAUI.;ON, WI
Change Order Summary
Project: Oshkosh Headworks
Project #: 211896
Proposal Date: 06/17/2009
Change Order #: 4
Revision: 0
Description of Work: 6 steel members painting
Total CO Amount: ($424.00)
Unit of Unit Price
Item Description Calc Type Quantity Measure or Rate PCT % Total Amount
coatings Subcontractor Lump Sum 0.00 Lump Sum - 424.00 0.00 - 424.00
TOTAL S - Subcontract ($424)
Grand Total: I ($424)1
This proposal only covers the direct costs of labor, materials and equipment to
execute the changed work described in the proposal.
At the present time, we cannot assess or evaluate the overall impact of the
changed work on our original scope of work.
We thereby reserve our rights to claim for any indirect costs which may arise in
the future as a result of delays to the work, out of sequence work, inefficiencies,
extended contract completion, labor and material escalation and / or acceleration
and extended warranties.
Page 1 of 1
MAY. 22. 2009 10:25AM OMNI GLASS_ &_PAINT NO, 561 P. 1/1
OMNI GLASS & PAINT, INC.
3530 OMNI DRIVE * OSHKOSH, WISCONSIN 54904
PHONES: ®OSHKOSH (920) 233 -3333
❑GREEN BAY (920) 434 -7772 ❑SCHOFIELD (715) 355 -893
PAINT JOB CHANGE #CP68017
Date: May 22, 2009
To: JF Ahern
Attn: Pete Wachs
Project: Oshkosh Headworks
CHANGE FOR THE ABOVE LISTED PROJECT:
Existing Carbon Steel at Screens
Pete,
Pursuant to your request regarding changes at the above referenced, we have the following to report:
To eliminate painting of six steel members at the existing screens, totaling approximately 144 lineal feet, please
DEDUCT the sum of $424.00 from our contract.
Thank you for the opportunity to do this project. If you have any questions, please call me at our office.
Karl Keas, Project Manager PH: 920 -236 -2353
KK/amd
CC: CF, RW
Saved as: KK/Oshkosh Headworks JC CP68017 052209
IMPORTANT — PLEASE READ
• Terms are Net 10 Days from date of Invoice
• Past due accounts are subject to interest at the rate of 1 -1 /2% per month (18% annually)
• Retainages (when allowed) are due immediately upon payment from owner
• All materials used are under warranty by the manufacturer. Warranties may vary by manufacturer. Omni Glass & Paint, Inc. does not warranty
materials
• Quotation excludes any overtime unless otherwise noted
• All workmanship is warranted for one year from date of installation
• It is understood that if you use your own contract form, the conditions of this quotation fully apply, unless specifically written out and mutually agreed
upon
• Backcharges for any services not specifically agreed to in writing, and/or backcharges of any other nature for delays to the project caused by conditions
beyond our control will not be honored and is not part of this quotations
• Seller reserves the right to stop work or delivery whenever an account is in arrears, without recourse by affected parties
Accepted OMNI GLASS & PAINT, INC.
Date By
.Lake, Bradley
From: Peter C Wachs [pwachs @jfahern.com]
Sent: Tuesday, September 01, 2009 2:11 PM
To: Lake, Bradley
Subject: Credit for not moving vent at Oshkosh
Brad,
Our credit for not moving the 2 inch vent line is 4 hours @ $51.54 /hour and $100 for material for a total of
$306.16. If this is acceptable I will issue a credit. Let me know please.
Peter Wachs