HomeMy WebLinkAbout11-427SEPTEMBER 27, 2011 11 -427 RESOLUTION CARRIED 6 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVE CONDITIONAL USE PERMIT & PLANNED DEVELOPMENT FOR CONSTRUCTION OF PRIVATE UTILITY STRUCTURE FOR ANR PIPELINE, SOUTH OF OMNI DRIVE AND EAST OF USH 45 INITIATED BY: ANR PIPELINE COMPANY, OWNER /PETITIONER PLAN COMMISSION RECOMMENDATION: Approved w /conditions BE IT RESOLVED by the Common Council of the City of Oshkosh that a conditional use permit for the planned development of a private utility structure for ANR Pipeline Company for development of an odorizing building /facility, per the attached, is hereby approved with the following conditions: 1) Base standard modifications for a 6.9 ft. side yard setback and a 10 ft. front yard setback for the structure. 2) Base standard modification to allow no on -site parking facilities. 3) A solid wood fence is required to screen the structure and concrete barriers. Q IHKOlH ON THE WATER TO: Honorable Mayor and Members of the Common Council FROM: Jeffrey Nau. Associate ner DATE: September 22, 2011 RE: Approve Planned Development to Construct a Private Utility Facility for ANR Pipeline, South Side of Omni Drive, East of U.S. Highway 45 (Plan Commission recommends approval) BACKGROUND ANR Pipeline Company intends to develop a 4,440 square foot vacant lot with an odorizing building/facility. The subject site is located on the south side of Omni Drive, east of and adjacent to U.S. Highway 45. The site is currently U.S. Highway 45 right -of -way; however, the Wisconsin Department of Transportation has agreed to sell this area to ANR Pipeline for site development. ANALYSIS ANR Pipeline Company is proposing to construct a 15 -foot by 31 -foot , 465 square foot structure to house an odorization facility to enable injection of odorant into their pipeline facilities. The site plan shows the building to have a 6.9 -foot side yard setback (10.0 feet required) and 10.0 foot front yard setback (25.0 feet required) requiring base standard modifications for the reduced setbacks. The building is proposed to be a pre - formed pebbly cast concrete with a three -foot tall concrete barrier surrounding the entire facility for protection from vehicles straying off Omni or Stearns Drives. As a condition of approval, the Plan Commission recommended the petitioner construct a solid wood fence to screen the building and concrete barrier. The site will be visited by employees three to four times a month for inspection and maintenance. The proposed site plan shows no area for off - street parking but on- street parking is available on Omni Drive and off - street parking at their hub facility to the west, therefore, the Plan Commission approved a base standard modification for no off - street parking. The petitioner states that once a year, a tanker will need to replenish odorization chemicals requiring temporary parking on Omni Drive. During these infrequent times, flagmen will be provided to ensure traffic is not disrupted. A landscape plan has not been submitted but will need to meet code requirements in relation to quantities and placement. Drainage and stormwater plans have not been submitted, but they will require approval by the Department of Public Works. FISCAL IMPACT None anticipated other than the project will add new property tax base to the community. RECOMMENDATION The Plan Commission approved of this request at its September 20, 2011 meeting. Approved, City Manager ITEM: CONDITIONAL USE PERMIT /PLANNED DEVELOPMENT REVIEW FOR PRIVATE UTILITY STRUCTURE, SOUTH OF OMNI DRIVE & EAST OF U.S. HIGHWAY 45 Plan Commission meeting of September 20, 2011 GENERAL INFORMATION Applicant: ANR Pipeline Company Property Owner: Omni Glass & Paint and Wisconsin Department of Transportation Action(s) Requested: ANR Pipeline Company is requesting approval of a Conditional Use Permit/Planned Development review for development of an odorizing building /facility. Applicable Ordinance Provisions: Private utility uses are permitted through a Planned Development in the C -2PD General Commercial District with Planned Development Overlay as regulated in Section 30 -28 of the Zoning Ordinance. Criteria used for Conditional Use Permits are located in Section 30 -11 and criteria for Planned Developments are located in Section 30 -33 of the Zoning Ordinance. Property Location and Background Information: The subject site is currently Wisconsin Department of Transportation right -of -way which the State has agreed to sell to ANR Pipeline. The proposed triangular- shaped parcel is approximately 4,440 square feet (0.10 acres). The site is adjacent to ANR's gas transmission valve hub site located on Omni Glass and Paint's property located just to the northwest. Subject Site Existin Land Use Zoning Vacant/U.S. Highway 41 Right -of -Way C -2PD Adjacent Land Use and Zoning Existing Uses Zonin North Industrial - Gas Transmission Valve Hub Site C -2PD w /Hwy 41 Overlay South Vacant/U.S. Highway 41 Right -of -Way C -2PD East Commercial /Industrial — Omni Glass & Paint C -2PD w /Hwy 41 Overlay West U.S. Highway 45 C -2PD Comprehensive Plan Land Use Recommendation Land Use 10 Year Land Use Recommendation Commercial 20 Year Land Use Recommendation Commercial ANALYSIS ANR Pipeline is proposing to construct a 15 -foot by 31 -foot , 465 square foot structure to house an odorization facility to enable injection of odorant into their pipeline facilities. The site plan shows the building to have a 6.9 -foot side yard setback (10.0 feet required) and a 10.0 front yard setback (25.0 feet required) requiring base standard modifications for the reduced setbacks. Staff is supportive of the reduced setbacks due to the small size of the proposed parcel and close proximity to the hub station. The building is proposed to be a pre - formed pebbly cast concrete with a three -foot tall concrete barrier surrounding the entire facility for protection from vehicles straying off Omni or Stearns Drives. The petitioner is proposing to screen the building and concrete barrier with a six -foot tall chain link fencing with slats topped with barbed wire. Staff is opposed to the proposed fencing with barbed wire and is recommending a solid wood fence without barbed wire to be used to better screen the site and be more aesthetic. The petitioner states in their application that the site will be visited by employees three to four times a month. The proposed site plan shows no area for off - street parking but on- street parking is available on Omni Drive. Staff has no concern with the proposal not providing off - street parking as the facility will have extremely low maintenance /monitoring requirements and is recommending a base standard modification for not providing any off - street parking. The petitioner states that once a year, a tanker will need to replenish odorization chemicals requiring temporary parking on Omni Drive. During these infrequent times, flagmen will be provided to ensure traffic is not disrupted. RECOMMENDATION Based on the information provided in the application as well as the information contained in the staff report, staff recommends approval of the CUP /PD for a private utility structure /facility with the following conditions: 1) Base standard modifications for a 6.9 -foot side yard setback and 10 -foot front -yard setback for the proposed structure. 2) Base standard modification to allow no on -site parking facilities. 3) A solid wood fence be required to screen the structure and concrete barriers. The Plan Commission approved of the conditional use permit for the planned development of a private utility structure /facility. The following is the Plan Commission's discussion on this item. Mr. Thorns inquired if landscaping will be required? Also, is the barbed wire permitted? If so, is it a safety issue? Mr. Nau replied that landscaping will be required. Mr. Buck stated barbed wire is only permitted in manufacturing districts and this site is zoned commercial. Staff does not support a base standard modification to allow the barbed wire. Item — CUP /PD Omni Dr — ANR Pipeline Mr. Larry Huber of ANR Pipeline, Eden, Wisconsin, stated barbed wire is used for security reasons -- to keep people out. This is considered a pipeline and safety precautions must be taken. Mr. Huber inquired if it was necessary to modify the existing fencing? Mr. Buck indicated that would be grandfathered in, but having all fencing the same would improve the aesthetics of the site. Mr. Huber indicated they could consider refencing the entire site but he would have to check with the office to see what can be accomplished. With the fence to the lot line, landscaping would be difficult. Mr. Nau stated the ordinance would require a couple of shrubs and trees and they would have to be outside the fence. Motion by Hinz to move approval of a conditional use permit and planned development approval for a private utility structure with the following conditions: 1) Base standard modifications for a 6.9 ft. side yard setback and a 10 ft. front yard setback for the structure. 2) Base standard modification to allow no on -site parking facilities. 3) A solid wood fence is required to screen the structure and concrete barriers. Seconded by Vajgrt. Motion carried 5-0. Item — CUP /PD Omni Dr —ANR Pipeline City of Oshkosh Application ❑ Planned Development Review OYHKOYH ❑ Conditional Use Permit Review ON THE WATER * *PLEASE TYPE OR PRINT USING BLACK INK ** SUBMIT TO: Dept. of Community Developmc 215 Church Ave., P.O. Box 1131 Oshkosh, Wisconsin 54903 -1131 PHONE: (920) 236 -5059 APPLICANT INFORMATION Petitioner: l� e z `�;\i `� y� +��`i v� Date: �—O --,::t V) Petitioner's Address: W 5'12. City: tL C -r State: Zip: 5, 3 " (`� 3 Telephone #: ) ' �� ° c-�-- 3 Fax: (`j Other Contact # or Email: } � '' = a Status of Petitioner (Please Check): ❑ Owner F<e presentative enant ❑ Prospective Buyer Petitioner's Signature (required): =� = 'NI C- -? ,, OWNER INFORMATION Owner(s): Its. Owner(s) Address: Telephone #: ( Fax: ( ) City: 71f t t lL �= Date: c' �{- Date: _ State: Zip: Other Contact # or Email: Ownership Status (Please Check): ❑ Individual ❑ Trust ❑ Partnership ❑ Corporation Property Owner Consent: (required) By signature hereon, UWe acknowledge that City officials and/or employees may, in the performance of their functions, enter upon the property to inspect or gather other information necessary to process this application. I also understand that all meeting dates are tentative and may be postponed by the Planning Services Division for incomplete submissions or other administrative reasons. Property Owner's Signature: SITE INFORMATION Date: Address/Location of Proposed Project: 00 - 4 1 �. Ti ,�) Parcel No. `1 tZ -7 a ° `� C , t =:' Proposed Project Type: (L" & C i Current Use of Property: �'� `= ` `'U s 4- :�;:�S.vl c s g f 3 Zoning: Land Uses Surrounding Site: North: 02-1 1 e^ - -e-t 0, South: V- \ 4 f I CD East: C---. " ``" c � l West: 1"1--�"k 4-- 1 t O "Please note that a meeting notice will be mailed to all abutting property owners regarding your request. ➢ Application fees are due at time of submittal. Make check payable to City of Oshkosh. ➢ Please refer to the fee schedule for appropriate fee. FEE IS NON - REFUNDABLE For more information please the City's website at www.ci.oshkosh.wi.us/ Community_Development /Planning.htm Staff " U Date Rec'd 5,P q Permit Submittal Requirements Odorization of ANR's pipeline facility is being required by the U. S. Department of Transportation, Pipeline and Hazardous Material Safety Administration to try to create a safer and easier to monitor condition of this pipeline system in the Oshkosh area. Existing property use is a natural ga transmission mainline valve hub site; the proposed use will remain the same with the addition of odorizing building and equipment. One building structure will be added, an Ordorization building for injecting of odorant into these pipeline facilities. Plans are to widen the road shoulder to make a driveway /pull over area to the odorant site to be mainly used during odorant delivery. Employees will be on site on an as needed basis, expected to be three to four times a month. Effects to the adjoining properties to be the same as currently existing other than during construction phase. Traffic will be the same as currently in place except during construction phase. Odorant to be delivered once a year to minimize possible odorant releasing during filling, road flagman to be provided during tank filling. This installation is to comply with Federal WDOT requirement for pipelines that fall in an odorization category. Impact Statement A. Water consumption — N/A B. Sewage Generation — N/A C. Vehicles Trips — Expected to be 3 to 4 times per month, expected one vehicle at a time, possible additional if maintenance is required D. Vehicles to be stored — None E. Proposed signage — Same as current, pipeline markers on roads, Signs on fence as currently in place identify company contact information for emergencies. Operating Hours — 24 hours per day, 365 days per year (same as current use) F. User Profile — Same as current profile (gas transmission facility). H. Proposed dates of construction, dependant on receipt of permits, but planned for October time frame and project is required to be completed before December 31 2011. I. Unusual conditions — Possible smell of odorant during filling (plans are to fill once a year to minimize) and odorant and natural gas being odorized are potential fire hazards. Heavy equipment activity and noise during construction phase. 14. No landscaping planned for this site to keep in compliance with company rules on planting in pipeline easements. S � \ . \ R` / : ± } k / z H 0 - - -- -ma \ \ ` z o z 0 C) (n 2mr- :z Z) ' i , 0 6 o 0 5. CD K I ns Lol \ � � ~ >\ � - / � \\ } � /\ % . , i 3 \\ :z 0- LLJ 6-1 \(( § } \)} :2 j 21 co cz co cl zi zi C) � � � » �` }} � � � \�� I� e =: ® = �G 0 2 13 0 (D E3MCD-- CD LLJ LLI � \ . \ R` / : ± } k / z H 0 - - -- -ma \ \ ` z o z 0 C) (n 2mr- :z Z) ' i , 0 6 o 0 5. CD K I ns Lol \ � � ~ >\ � - / � \\ } � /\ % . , i 3 \\ :z 0- LLJ 6-1 IR as - 7, i f LN � V4. Co I i 1 -7 CUP /PD- ODORIZATION FACILITY OMNI GLASS & PAINT INC WIS DEPT OF TRANSPORTATION S OF OMNI DR /E OF USH 45 3530 OMNI DR PO BOX 28080 PC: 09 -20 -11 OSHKOSH WI 54904 8512 GREEN BAY WI 54304 DOWLING DANIEL E PO BOX 3045 OSHKOSH WI 54903 3045 ANR PIPELINE CO W3925 PIPELINE LN EDEN WI 53019 9 r� FACILITY LOCATION IC i t n w 1/ v ' 00 r I � x; y x < x �x � < �< x �< x x ` X x^ `� / x X, >! `\ // T � < x X >< � < ✓ mac 7<' X \ ✓ X X � > ✓ / X i` \ ' O' o Co. / o cr \ ' x O ?3 _Z7l p F ANR PIPELINE co , 4U DISCLAIMER ANR PIPELINE This map is neither a legally recorded map nor O D O R I ZAT I O N FACILITY a survey it intended and not to be used as one. This drawing is N compilation v of records, data SOUTH O F O M N I DR & and information located in n various city, O✓ / HI[OJ 17 l county and state offices and other sources affecting or, THE wATM the area shown and it is to be used for reference EAST O F U S H 45 City of Oshkosh Th City Oshkosh purposes only. e of is not re- Department Of sponsible for any inaccuracies herein contained. If discrepencies are found, please contact the Community Development City of Oshkosh. Created by - dff Scale: 1 200 09/02/11 9 DISCLAIMER This map is neither a legally recorded map nor a survey and it is not intended to be used as one. This drawing is a compilation of records, data and information located in various city, county and state offices and other sources affecting the area shown and it is to be used for reference purposes only. The City of Oshkosh is not re- sponsible for any inaccuracies herein contained. If discrepencies are found, please contact the City of Oshkosh. Created by - dff ANR PIPELINE ODORIZATION FACILITY SOUTH OF OMNI DR & EAST OF USH 45 Scale: 1" = 1500' N 0.1HKOIH ON THE WATM City of Oshkosh Department of Community Development 09/02/11 /0 DISCLAIMER This map is neither a legally recorded map nor a survey and it is not intended to be used as one. This drawing is a compilation of records, data and information located in various city, county and state offices and other sources affecting the area shown and it is to be used for reference purposes only. The City of Oshkosh is not re- sponsible for any inaccuracies herein contained. If discrepencies are found, please contact the City of Oshkosh. Created by - dff ANR PIPELINE ODORIZATION FACILITY SOUTH OF OMNI DR & EAST OF USH 45 Scale: 1 " = 200' N O.IHKOfH ON THE WATM City of Oshkosh Department of Community Development 09/02/11