HomeMy WebLinkAbout11-354AUGUST 10, 2011 11 -354 RESOLUTION (CARRIED 7-0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 FOR PUBLIC WORKS CONTRACT NO. 09 -19 WITH FAITH TECHNOLOGIES, INC. FOR THE WASTEWATER TREATMENT PLANT PUMPING & METER STATIONS SCADA UPGRADES (- $49,814.17) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: FAITH TECHNOLOGIES, INC. 2662 American Drive Appleton, WI 54914 Net Decrease to contract: $49,814.17 PURPOSE: See attached Change Order. STRAND ASSOCIATES. INC- E N G I N E E R S $ 100,000.00 June 10, 2011 910 West Wingra Drive 45,179.80 Madison, WI 53715 $ Phone: 608 -251 -4843 Fax: 608- 251 -8655 CHANGE ORDER NO. 2 Office Locations PROJECT: Lift Stations and Flow Stations SCADA Upgrade Madison, WI OWNER: City of Oshkosh Joliet, IL Louisville, KY CONTRACT: 09 -19 Lexington, KY CONTRACTOR: Faith Technologies, Inc. Mobile, AL Columbus, IN Adjustment in Contract Price this Change Order Columbus, OH 981,995.83 Indianapolis, IN Milwaukee, WI Description of Change Cincinnati, OH Phoenix, AZ 2a Provide 40 -foot light pole at County Road Y ADD $5,006.03 Lift Station for mounting of radio antenna to achieve a strong radio signal at Tower No. 4 www.strand.com and the Lift Station. TOTAL VALUE OF THIS CHANGE ORDER: ADD $5,006.03 Contract Price Adjustment Original Contract Price including the Contract Contingency Allowance $1,031,810.00 Contract Contingency Allowance for Changes $ 100,000.00 Previous Change Order Adjustments to the Contingency Allowance $ 45,179.80 Total Value of this Change Order $ 5,006.03 Total Change Order Adjustments to the Contingency Allowance $ 50,185.83 Current Contingency Allowance Balance including this Change Order $ 49,814.17 Change Order No. 2 Credit to Owner for Remaining Balance to the $ 49,814.17 Contingency Allowance Adjustment in Contract Price this Change Order $ 981,995.83 Contract Completion Date Adjustment Original Contract Completion Date October 29, 2010 Contract Completion Date Adjustments due to previous Change Orders 94 Days Contract Completion Date Adjustments due to this Change Order 150 Days Current Contract Completion Dates including all Change Orders June 30, 2011 MEM:chn \S:\MAD \130D -- 1399\1382 \044\Wrd \Construction ServicesaRs & Change Orders \Change Order No. 2 Draft(Final).docx ��--�: �. STRAND ASSOCIATES, INC.- E N G I N E E R S City of Oshkosh -Faith Technologies, Inc. Contract 09 -19, Change Order No. 2 Page 2 June 10, 2011 This document shall become a supplement to the Contract and all provisions will apply hereto. RECOMMENDED Assoc,iates, Inc. APPROVED CONTRACTOR_ Faith Technologies, Inc. RECOMMENDED BY OWNER OWNER — Director of Public Works, City of Oshkosh APPROVED BY OWNER G (1 Date (9 4z .D I<< Date Date OWNER —Mark A. Rohloff, City Manager, City of Oshkosh Date OWNER — Pamela R. Ubrig, City Clerk, City of Oshkosh Date I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under this Change Order. OWNER—Peggy Steeno, Director of Finance, City of Oshkosh Date APPROVED AS TO FORM Date OWNER —Lynn Lorenson, City Attorney, City of Oshkosh MEM:clm \S:\ MAD \1300 -- 1399 \1382 \044 \Wrd \Construction Services'\RFPs & Change Orders \Change Order No. 2 Draft(Final).docx ( 0 OOH ON THE WATER MEMORANDUM TO: FROM: DATE: RE: Honorable Mayor and Members of the Common Council Stephan M. Brand, Utilities Superintendent August 4, 2011 Change Order No. 2 for Contract No. 09 -19 Wastewater Treatment Plant Pumping & Meter Stations SCADA (Supervisory Control and Data Acquisition) Upgrades BACKGROUND Change Order No. 2 for Contract 09 -19 is scheduled for consideration by the Common Council at their August 10, 2011 meeting. This project includes upgrades to the wastewater system liftstation telemetry technology from a telephone dial up system to radio communications, related software upgrades, and replacement of electric control panels at various locations. The contract was originally awarded to Faith Technologies of Appleton in October of 2009. ANALYSIS This change order include an increase of $5006.03 for changing the antenna height at the CTH Y pumping station from 20 feet to 40 feet due to unanticipated radio signal interference and reception issues with the original installation. Also included in this change order is a reduction in the contract price by $49,814.17 for unused contract contingency allowance. FISCAL IMPACT The project low bid of $1,031,810.00 included a $100,000.00 contingency allowance. Change order No. 1 utilized $45,179.80 of the contingency fund and this change order No. 2 will utilize $5006.03 bringing the total to $50,185.83. The balance of the unused contingency fund $49,814.17 will be subtracted from the contract amount of $1,031,810.00 adjusting the final contract price to $981,995.83. Funds have been budgeted in the Capital Improvement Program under the Property Improvements Section utilizing Wastewater Utility Funds for this project. RECOMMENDATIONS I recommend approval of the Change Order No. 2 to Contract No. 09 -19 to the final contract amount of $981,995.83 with Faith Technologies. Respectfully Submitted, Approved: Stephan M. Brand Mark Rohloff Utilities Superintendent City Manager