HomeMy WebLinkAbout11-101MARCH 8, 2011 11 -101 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 10 -09 WITH MIRON CONSTRUCTION, INC.
FOR MELVIN STORM WATER PUMP STATION ($0)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
MIRON CONSTRUCTION, INC.
1416 McMahon Dr.
Neenah, WI 54956
Net Increase to contract: $0
PURPOSE: See attached Change Order.
MARCH 8, 2011 11 -101 RESOLUTION
(CARRIED LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 10 -09 WITH MIRON CONSTRUCTION, INC.
FOR MELVIN STORM WATER PUMP STATION ($0)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
MIRON CONSTRUCTION, INC.
1416 McMahon Dr.
Neenah, WI 54956
Net Increase to contract: $0
PURPOSE: See attached Change Order.
( 0
Of HKO
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: James E. Rabe, Civil Engineer II
DATE: March 3, 2011
RE: Change Order #1 for Public Works Contract No. 10 -09; with Miron Construction Co., Inc. for
Melvin Avenue Storm Water Pump Station ($0.00)
BACKGROUND
Change Order #1 for Contract 10 -09 is scheduled for consideration by the Common Council at the March 8,
2011 meeting. The contract was originally awarded to Miron Construction Co. Inc. in March of 2010. This
change order is to finalize all quantities and adjust the completion dates.
ANALYSIS
Following is a summary of the significant changes to the project:
— Revise Water Service per Water Distribution Recommendation.
— Deletion of concrete support slab under floor slab.
— Revise Duct Banks per approved Contractor Requests for Clarification.
— Include conduit through foundation for installation of future security system.
— Install additional dowels at locations where box culverts meet structural wall.
— Paint overhead door to match building colors.
— Add 29 days to Substantial Completion.
— Add 19 days to Final Completion.
FISCAL IMPACT
The cost of the additional work performed is offset by the additional days allotted to the completion of the
project. Therefore, there is no cost change associated with this change order.
RECOMMENDATIONS
recommend approval of the Change Order #1 to Contact No. 10 -09 in the amount of $0.00 for Miron
Construction Co., Inc.
Respectfully Submitted,
James E Rabe
Civil Engineer II
Approved:
Mark A. Rohloff
City Manager
(:\Engineering \10 -09 Melvin Avenue Storm Water Pump Station\ Project_ Information \Correspondence\Memo \CO #1 10 -09 CC Memo.doc
A COM
February 10, 2011
Change Order No. 1
Project: Melvin Storm Water Pump Station, City Contract 10 -09
Owner: City of Oshkosh
Contract: 10 -09
Contractor: Miron Construction Co., Inc.
Description of Change
Request for Quote PM No.
Change 1 ' /2 inch copper water service/
Access Road to 16 ft. / ramp widening /area drain
$0
Mud Slab
$0
Duct Banks A and B CCIR 003 Rev
$0
4" conduit through foundation future fiber optics line
$0
Drill and epoxy dowels around
grouted area box culvert meets wall
$0
Paint OH door to thatch color
$0
TOTAL VALUE OF THIS CHANGE ORDER
ADD $0
Contract Price Adjustment
Original Contract Price
$3,029,860.00
Previous Change Orders
$0
Adjustments in Contract Price this Change Order
$0
Current Contract Price including this Change Order
$3,029,860.00
Contract Completion Date Adjustment (Not to Exceed)
Original Contract Completion Date Substantial Completion
August 30, 2010
Final Completion
October 31, 2010
Contract Completion Date Adjustments Substantial Completion
0
due to previous Change Orders Final Completion
0
Contract Completion Date Adjustments Substantial Completion
add 29 days
due to this Change Order Final Completion
add 19 days
Current Contract Completion Dates Substantial Completion
September 28, 2010
including all Change Orders Final Completion
November 19, 2010
A: [OM
This document shall become a supplement to the Contract and all provisions will apply hereto.
RECOMMENDED
Engineer — AECOM Date
APP R ED
CO TRACTOR — Miron Cons uction Co., Inc. D to
David G. Voss J President
RECOMMENDED BY OWNER
Director of Public Works
Date
APPROVED BY OWNER
City Manager
Date
City Clerk
Date
I certify that provision has been made to pay the liability that will
accrue to the City of
Oshkosh, Wisconsin under this Change Order.
City Comptroller
Date
APPROVED AS TO FORM:
City Attorney
Date