HomeMy WebLinkAbout11-62FEBRUARY 22, 2011 11 -62 RESOLUTION
(CARRIED 6 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 3 FOR PUBLIC WORKS
CONTRACT NO. 10 -05 WITH CARL BOWERS & SONS
CONSTRUC -TION CO. FOR VARIOUS CONCRETE PAVING &
UTILITY PROJECTS — SOUTH SIDE PAVING PROJECT
(-$60,002.33)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
CARL BOWERS & SONS CONSTRUCTION CO.
N1844 Maloney Rd.
Kaukauna, WI 54130
Net Decrease to contract: (- $60,002.33)
PURPOSE: See attached Change Order.
CHANGE ORDER # 3
DATED: January 31, 2011
TO: Carl Bowers & Sons Constr. Co., Inc.
N1844 Maloney Rd
Kaukauna WI 54130
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
NET INCREASE TO: SECTION I -CONCRETE PAVING
NET DECREASE TO: SECTION II - STORM SEWER
NET DECREASE TO: SECTION III - SANITARY SEWER
NET DECREASE TO: SECTION IV - WATER MAIN
NET DECREASE TO CONTRACT:
Recommended:
Director of Public Works
BY:
10 -05 , is hereby amended
$8,439.70
($29,271.25)
($19,387.78)
($19,783.00)
($60,002.33)
CITY OF OSHKOSH
City Manager
City Clerk
Ap roved and accepted:
1
ontractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 10 -05 CHANGE ORDER # 3
SECTION I - CONCRETE PAVING
ITEM
Pavement removal,
Square
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
IN
DECREASE
UNIT
CONTRACT
CONTRACT
I
101
Sidewalk and driveway
PRICE
PRICE
100
Pavement removal,
Square
complete as specified
Yards
'11,045
14,810.30
3,765.30
$2.00
$7,530.60
101
Sidewalk and driveway
removal, complete as
Square
specified
Feet
38,205
39,399.50
1,194.50
$0.60
$716.70
102
Excavation, complete as
Cubic
. specified
Yards
9,775
10,749.80
974.80
$8.50
$8,285.80
103
7" non - reinforced concrete
pavement, including
integral curb, 5" base
material and grading,
complete as specified
Square
Yards
23,230
23,266.80
36.80
$26.15
$962.32
104
8" doweled concrete
pavement, including
integral curb and 6" base
material and grading,
Square
complete asspecified
Yards
335
371.90
36.90
$43.20
$1,594.08
105
12" wide radius curb head,
complete as specified
Linear
Feet
780
759.20
-20.80
$6.00
($124.80)
106
Standard 30" curb & gutter,
7" (tie -in), complete as
Linear
specified
Feet
415
201.60
- 213.40
$25.00
($5,335.00)
107
Sidewalk curb, complete as
Linear
specified
Feet
145
68.90
-76.10
$18.00
($1,369.80)
108
4" concrete sidewalk,
Square
complete asspecified
Feet
11,500
13,277.60
1,777.60
$3.00
$5,332.80
109
6" concrete sidewalk &
driveway, complete as
Square
. specified
Feet
29,975
29,449.80
- 525.20
$3.35
($1,759.42)
110
3'/" asphaltic concrete
driveway, complete as
Square
specified
Feet
140
290.80
150.80
$5.50
$829.40
111
3' /z" asphaltic concrete
transition, with base,
Square
. complete asspecified
Yard
560
614.40
54.40
$34.00
$1,849.60
112
Furnish and install crushed
stone base course,
complete as specified
Tons
3,735
2,645.80
- 1,089.20
$6.00
($6,535.20)
113
Sawing, complete as
Linear
specified
Feet
1,730
1,095.40
- 634.60
$1.80
($1,142.28)
114
Furnish and install
pavement ties (epoxy
coated), complete as
specified
Each
325
117.00
- 208.00
$8.00
($1,664.00)
115
Adjust manholes and inlets,
complete as specified
Each
170
164.00
-6.00
$240.00
($1,440.00)
116
Furnish and install No. 4
reinforcing bars (epoxy
coated), complete as
Linear
specified
Feet
240
1,110.00
870.00
$1.00
$870.00
Page 1 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE 1N
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
[INCREASEIN
CONTRACT
CONTRACT
Avenue
1.00
1.00
$165.00
PRICE
PRICE
117
Remove trees and stumps,
Lump
complete as specified
Inch
to 6th Ave.
Diameter
410
384.00
1.00
-26.00
$15.00
$1,040.00
($390.00)
118
Remove stumps, complete
Inch
asspecified
Diameter
16
15.00
-1.00
$10.00
($10.00)
119
Furnish and install trees,
complete asspecified
Each
18
16.00
-2.00
$200.00
($400.00)
120
Provide and install metal
detectable warning plates,
complete as specified
Square
Feet
400
320.00
-80.00
$28.00
1
($2,240.00)
121
Terrace work on Dakota
Street (8 Ave to 6 1h Ave),
complete as specified
Lump
Sum
1
1.00
$1,000.00
122
Terrace work on Dakota
Street (6` Ave to 5 1h Ave),
complete as specified
Lump
Sum
1
1.00
$1,000.00
123
Terrace work on Idaho
Street, complete as
Lump
specified
Sum
1
1.00
$6,000.00
124
Terrace work on W. 4`
Avenue, complete as
Lump
s ecified
Sum
I 1
1.00
$10,500.00
125
Terrace work on W. 5`
Avenue, complete as
Lump
specified
Sum
1
1.00
$10,500.00
126
Terrace work on W. 6`
Ave., complete as specified
Lump
Sum
1 1
1.00
1 $550.00
127
Terrace work on W. 8`
Avenue, complete as
Lump
s ecified
Sum
1
1.00
$10,500.00
128
2" Asphaltic concrete
transition with base and
asphaltic curb, complete as
Square
specified
Yards
930
1,018.10
88.10
$19.00
$1,673.90
SECTION I - (BID ITEMS 100 - 128) - SUB - TOTALS
ADDITIONAL WORK REQUIRED: C.O. # 3 - SECTION I
$29,645.20 ($22,410.50)
ITEM
Diamond cut curb for
Lump
CONTRACT
INSTALLED
NET
NET
COST PER
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
I QUANTITIES
INCREASE
I DECREASE
UNIT
[INCREASEIN
CONTRACT
CONTRACT
Avenue
1.00
1.00
$165.00
PRICE
PRICE
129
Diamond cut curb for
Lump
driveway opening on 5th
Sum
Avenue
1.00
1.00
$165.00
$165.00
130
Additional Grading on
Lump
Idaho Street from 5th Ave.
Sum
to 6th Ave.
I
I
1 1.00
1.00
$1,040.00
$1,040.00
ADDITIONAL WORK: C.O. 41 - (ITEMS 129 -130) - SUB -TOTAL
NET INCREASE TO: SECTION I
$1,205.00 $0.00
$8,439.70
Page 2 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
Furnish and install 12"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
specified
Feet
1,260
1,197.60
-62.40
$41.00
PRICE
PRICE
SECTION II - STORM SEWER
ITEM
Furnish and install 12"
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
I
specified
Feet
1,260
1,197.60
-62.40
$41.00
PRICE
PRICE
200
Furnish and install 12"
Storm Sewer, complete as
Linear
specified
Feet
1,260
1,197.60
-62.40
$41.00
($2,558.40)
201
Furnish and install 15"
Storm Sewer, complete as
Linear
, specified
Feet
558
520.90
-37.10
$43.00
1
($1,595.30)
202
Furnish and install 18"
Storm Sewer, complete as
Linear
specified
Feet
602
570.90
-31.10
$51.00
($1,586.10)
203
Furnish and install 24"
Storm Sewer, complete as
Linear
, specified
Feet
630
593.00
-37.00
$54.00
($1,998.00)
204
Furnish and install 27"
Storm Sewer, complete as
Linear
specified
Feet
385
348.00
-37.00
$65.00
($2,405.00)
205
Furnish and install 30"
Storm Sewer, complete as
Linear
, specified
Feet
770
727.10
-42.90
$69.00
($2,960.10)
206
Furnish and install 36"
Storm Sewer, complete as
Linear
specified
Feet
72
47.90
-24.10
$82.00
($1,976.20)
207
Furnish and install 42"
RCP Class III Storm
Sewer, complete as
Linear
. specified
Feet
219
206.80
-12.20
$91.00
($1,110.20)
208
Furnish and install 19" x
30" RCP Class III Storm
Sewer, complete as
Linear
specified
Feet
1,180
1,163.40
-16.60
$75.00
($1,245.00)
209
Furnish and install 24" x
38" RCP Class III Storm
Sewer, complete as
Linear
. specified
Feet
150
149.00
-1.00
$83.00
($83.00)
210
Furnish and install 4' x 6'
Box Culvert Storm Sewer,
Linear
complete asspecified
Feet
504
490.00
-14.00
$325.00
($4,550.00)
211
Furnish and install 4' x 8'
Box Culvert Storm Sewer,
Linear
, complete asspecified
Feet
1,260
1,276.60
16.60
$355.00
$5,893.00
212
Furnish and install 5'x 8'
Box Culvert Storm Sewer,
Linear
complete asspecified
Feet
33
32.00
-1.00
$550.00
($550.00)
213
Furnish and install 4'x 6'
Box Culvert Storm Sewer
w/ Manhole Riser,
Linear
. Complete
asspecified
Feet
16
13.00
-3.00
$485.00
($1,455.00)
214
Furnish and install 4' x 8'
Box Culvert Storm Sewer
w/ Manhole Riser,
Linear
complete asspecified
Feet
48
32.50
-15.50
$520.00
($8,060.00)
Page 3 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASEIN
CONTRACT
DECREASEIN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
215
Furnish and install Std.
Inlets (Type 3 with 18"
sump) with castings,
com fete asspecified
Each
75
74.00
-1.00
$1,120.00
($1,120.00)
216
Furnish and install Std.
Inlets (Type 3 with no
sump) with castings,
complete asspecified
Each
6
8.00
2.00
$1,000.00
$2,000.00
217
Furnish and install Std.
Storm Manhole (4' Inside
Diameter) in 15 locations
Vertical
without casting
Feet
65
65.29
0.29
$280.00
$81.20
218
Furnish and install Std.
Storm Manhole (5' Inside
Diameter) in 14 locations
without casting, complete
Vertical
asspecified
Feet
60
54.41
-5.59
$400.00
($2,236.00)
219
Furnish and install Std.
Storm Manhole (6' Inside
Diameter) in 2 locations
without casting, complete
Vertical
asspecified
Feet
8
14.62
6.62
$500.00
$3,310.00
220
Furnish and install Std.
Storm Manhole Riser (4'
Inside Diameter) in 8
locations without casting,
Vertical
, complete asspecified
Feet
16
12.92
-3.08
$280.00
($862.40)
221
Furnish and install Std.
Storm Inlet Manhole (4'
Inside Diameter) in one (1)
location with casting,
Vertical
complete asspecified
Feet
4
3.13
-0.87
$325.00
($282.75)
222
Furnish and install Std.
Storm Inlet Manhole (5'
Inside Diameter) in one (1)
location with casting,
Vertical
. complete asspecified
Feet
4
4.62
0.62
$425.00
$263.50
223
Furnish and install Std.
Storm Junction Chambers
without casting, complete
as specified
Each
5
5.00
$15,000.00
224
Furnish and install 6"
Storm Lateral, complete as
Linear
specified
Feet
4,407
4,323.00
-84.00
$27.00
($2,268.00)
225
Furnish and install 8"
Storm Lateral, complete as
Linear
specified
Feet
51
88.70
37.70
$55.00
$2,073.50
226
Furnish and install storm
lateral marker balls,
complete asspecified
Each
307
308.00
1.00
1
$19.00
$19.00
227
Abandon lineal feet of 8" -
12" storm sewer,
Linear
completed asspecified
Feet
1,618
1,618.00
$10.00
228
Abandon lineal feet of 15"
and larger storm sewer,
completed as specified
Linear
Feet
139
139.00
$20.00
Page 4 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
Furnish and install 8"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
complete asspecified
Feet
5,550
5,484.10
-65.90
$58.00
PRICE
PRICE
229
Abandon Inlets or
Manholes, complete as
Vertical
specified
Each
38
38.00
-4.59
$250.00
($1,377.00)
230
Furnish, install and
maintain Type "D" Inlet
Linear
Protection Std., complete
Feet
60
62.00
2.00
$70.00
$140.00
303
asspecified
Each
200
161.00
-39.00
$90.00
($3,510.00)
231
Furnish, install and
Vertical
maintain stone bags,
Feet
10
6.85
-3.15
$350.00
($1,102.50)
304
complete asspecified
Each
50
0.00
-50.00
$10.00
($500.00)
SECTION II - (BID ITEMS 200 - 231) - SUB - TOTALS $13,640.20 ($42,911.45)
NET DECREASE TO: SECTION II ($29,271.25)
SECTION III - SANITARY SEWER
ITEM
Furnish and install 8"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
I
complete asspecified
Feet
5,550
5,484.10
-65.90
$58.00
PRICE
PRICE
300
Furnish and install 8"
sanitary sewer (relay),
Linear
complete asspecified
Feet
5,550
5,484.10
-65.90
$58.00
($3,822.20)
301
Furnish and install 8"
sanitary sewer drop,
Vertical
, complete asspecified
Feet
10
5.41
-4.59
$300.00
($1,377.00)
302
Furnish and install 10"
sanitary sewer (relay),
Linear
complete asspecified
Feet
60
62.00
2.00
$70.00
$140.00
303
Furnish and install 10"
sanitary sewer drop,
Vertical
,complete asspecified
Feet
10
6.85
-3.15
$350.00
($1,102.50)
304
Furnish and install std.
sanitary manhole (4' inside
diameter) in various
locations, complete as
specified, without casting
Vertical
Feet
270
242.96
-27.04
$175.00
($4,732.00)
305
Furnish and install 8" x 4"
factory wyes or tees,
complete asspecified
Each
5
2.00
-3.00
$70.00
($210.00)
306
Furnish and install 8" x 6"
factory wyes or tees,
, complete asspecified
Each
160
147.00
-13.00
$90.00
($1,170.00)
307
Furnish and install
connections of new
sanitary main to existing
sanitary main (various
locations and sizes),
, complete
asspecified
Each
10
10.00
$500.00
308
Furnish and install concrete
collars, complete as
specified
Each
10
0.00
-10.00
$100.00
($1,000.00)
309
Furnish and install new 4"
sanitary laterals, complete
Linear
as s ecified
Feet
100
82.30
-17.70
1 $47.00
($831.90)
Page 5 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
Furnish and install 4"
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
w /poly wrap, complete as
PRICE
PRICE
310
Furnish and install 4 " /6"
Linear
sanitary lateral relay,
Linear
10
0.00
-10.00
$80.00
($800.00)
401
complete asspecified
Feet
4,250
4,058.06
- 191.94
$47.00
($9,021.18)
311
Furnish and install sanitary
lateral marker balls,
complete as specified
Linear
included )
Each
315
296.00
290.00
-19.00
$19.00
$16,820.00
($361.00)
312
Furnish and install 12"
casing pipe (18' lengths),
. complete asspecified
Each
2
8.00
6.00
$800.00
$4,800.00
313
Core into existing manhole,
Linear
complete as specified
Feet
6,200
6,013.00
- 187.00
$59.00
($11,033.00)
Each
4
3.00
-1.00
$700.00
($700.00)
314
Abandon sanitary
manholes at various
locations, complete as
. specified
Each
35
35.00
$365.00
315
Abandon 8" sanitary sewer
at various locations
Linear
complete asspecified
Feet
6,140
6,140.00
$3.00
316
Abandon 10" sanitary
sewer at various locations,
complete as specified
Linear
Feet
920
920.00
$3.00
317
Abandon 12" sanitary
sewer at various locations,
complete as specified
Linear
Feet
40
40.00
$8.00
SECTION III - (BID ITEMS 300 317) - SUB - TOTALS $4,940.00 ($24,327.78)
NET DECREASE TO: SECTION III ($19,387.78)
SECTION IV - WATER MAIN
ITEM
Furnish and install 4"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
w /poly wrap, complete as
PRICE
PRICE
400
Furnish and install 4"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
10
0.00
-10.00
$80.00
($800.00)
401
Furnish and install 6"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
475
765.00
290.00
$58.00
$16,820.00
402
Furnish and install 8"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
6,200
6,013.00
- 187.00
$59.00
($11,033.00)
Page 6 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
PRICE
PRICE
403
Furnish and install 1" water
service relay, complete as
specified, not including
corporation and stop box
Linear
Feet
3,725
3,690.50
-34.50
$41.00
($1,414.50)
404
Furnish and install new 1"
water service, complete as
specified, not including
corporation and stop box
Linear
Feet
75
19.50
-55.50
$41.00
($2,275.50)
405
Furnish and install 2"
casing pipe (18 foot
lengths), complete as
specified
Each
16
16.00
$200.00
406
Furnish and install 18"
casing pipe (18 foot
lengths), complete as
specified
Each
3
3.00
$900.00
407
Furnish and install 1"
corporation and stop box
with stainless steel rod,
complete asspecified
Each
165
153.00
-12.00
$240.00
($2,880.00)
408
Furnish and install 8" x 6"
tees, complete as specified
Each
20
19.00
-1.00
$310.00
($310.00)
409
Furnish and install 8" x 8"
tees, complete as specified
Each
10
4.00
-6.00
$370.00
($2,220.00)
410
Furnish and install 8" x 8"
cross, complete as
specified
Each
3
3.00
$350.00
411
Furnish and install 8" x 6"
cross, complete as
, specified
Each
2
0.00
-2.00
$325.00
($650.00)
412
Furnish and install 6"
valves, complete as
specified
Each
20
20.00
$1,050.00
413
Furnish and install 8"
valves, complete as
specified
Each
35
32.00
-3.00
$1,350.00
($4,050.00)
414
Furnish and install 6" x 6"
tapping valve and sleeve,
complete asspecified
Each
3
0.00
-3.00
$2,100.00
($6,300.00)
415
Furnish and install 4" - 22
degree bends, complete
asspecified
Each
2
0.00
-2.00
$165.00
($330.00)
416
Furnish and install 6" - 22
'/z degree bends, complete
asspecified
Each
2
0.00
-2.00
$215.00
($430.00)
417
Furnish and install 8" - 22
Y degree bends, complete
asspecified
Each
6
2.00
-4.00
$275.00
($1,100.00)
418
Furnish and install 4" - 45
degree bends, complete as
specified
Each
2
0.00
-2.00
$265.00
($530.00)
419
Furnish and install 6" - 45
degree bends, complete as
specified
Each
20
53.00
33.00
$225.00
$7,425.00
Page 7 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
420
Furnish and install 8" - 45
degree bends, complete as
specified
Each
10
5.00
-5.00
$270.00
($1,350.00)
421
Furnish and install 8" x 4"
reducer, complete as
specified
Each
2
0.00
-2.00
$160.00
($320.00)
422
Furnish and install 8" x 6"
reducers, complete as
specified
Each
15
10.00
-5.00
$240.00
($1,200.00)
423
Relocate hydrant, complete
asspecified
Each
1
0.00
-1.00
$600.00
($600.00)
424
Furnish and install
hydrants, complete as
specified
Each
20
17.00
-3.00
$2,700.00
($8,100.00)
425
Furnish and install
gradeloks for hydrant
branches, complete as
specified
Each
20
1.00
-19.00
$10.00
($190.00)
426
Furnish and install
connections of new water
main to existing water main
(various sizes and
locations), complete as
s ecified
Each
20
20.00
$1,000.00
427
Furnish and install 4" cap,
complete as specified
Each
2
0.00
-2.00
$150.00
($300.00)
428
Furnish and install 6" cap,
complete as specified
Each
2
0.00
-2.00
1 $175.00
($350.00)
429
Furnish and install 8" cap,
complete as specified
Each
2
0.00
-2.00
$210.00
($420.00)
430
Cut and cap existing 4"
water main, complete as
specified
Each
1
0.00
-1.00
$350.00 1
($350.00)
431
Cut and cap existing 6"
water main, complete as
specified
Each
1
0.00
-1.00
$400.00
($400.00)
432
Cut and cap existing 8"
water main, complete as
. specified
Each
1
0.00
-1.00
$450.00
$450.00)
433
Furnish and install 6"
sleeve, complete as
specified
Each
3
5.00
2.00
$225.00
$450.00
434
Furnish and install 8"
sleeve complete as
specified
Each
3
6.00
3.00
$275.00
$825.00
435
Abandon water main on
West 4th Avenue (Idaho St.
to Ohio St.), complete as
specified
Each
1
1.00
$2,500.00
436
Abandon water main on
West 5 th Avenue (Idaho St.
to Ohio St.), complete as
Lump
s ecified
Sum
1
1.00
$1,300.00
Page 8 of 9
CONTRACT: 10 -05 CHANGE ORDER # 3
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
437
Abandon water main on
West 8 th Avenue (Idaho St.
to Ohio St.), complete as
Lump
,specified
Sum
1
1.00
$1,400.00
438
Abandon water main on
Dakota Street (W. 5 th Ave.
to W. 6h Ave.), complete
Lump
ass ecified
Sum
1
1.00
$2,000.00
439
Abandon water main on
Idaho Street (W. 4 th Ave. to
W. 6 th Ave.), complete as
Lump
I SDecified
Sum
1
1.00
$1,400.00
440
Furnish and install 10" x 8"
tee, complete as specified
Each
1
1.00
$450.00
441
Furnish and install 10" — 45
degree bends, complete as
specified
Each
5
4.00
-1.00
$370.00
($370.00)
442
Furnish and install 10"
valve, complete as
specified
Each
1
1.00
$1,900.00
443
Furnish and install 10"
ductile iron watermain
w /poly wrap (fittings not
included) ,complete as
Linear
specified
Feet
5
41.00
36.00
$95.00
$3,420.00
SECTION IV - (BID ITEMS 400 - 443) - SUB - TOTALS
NET DECREASE TO: SECTION IV
NET INCREASE TO SECTIONS I, II, III, IV
NET DECREASE TO SECTIONS I, II, III, IV
NET DECREASE TO CONTRACT:
$28,940.00 ($48,723.00)
($19,783.00)
$78,370.40
($138,372.73)
($60,002.33)
Page 9 of 9
( 0
Of HKOf H
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: February 17, 2011
RE: Change Order #3 for Public Works Contract No. 10 -05; with Carl Bowers & Sons Construction
Co. for Concrete Paving and Utilities — South Side Paving Project (- $60,002.33)
BACKGROUND
Change Order #3 for Contract 10 -05 is scheduled for consideration by the Common Council at the February 22,
2011. The contract was originally awarded to Carl Bowers & Sons Construction Co. Inc. in March of 2010. This
change order is to finalize all quantities.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP.
- Concrete Paving — Additional pavement and sidewalk areas were removed and replaced.
-Storm Sewer — Actual installed quantities were below estimate quantities.
- Sanitary Sewer — Actual installed quantities were below estimate quantities.
-Water Main — Actual installed quantities were below estimate quantities.
FISCAL IMPACT
Contract Section
Change Order Amount
CIP Budget Amount
New Contract Total
Concrete Paving
$8,439.70
$1,696,000
$1,078,861.95
Storm Sewer
- $29,271.25
$841,800
$1,386,676.47
Sewer
- $19,387.78
$845,000
$644,860.29
- Sanitary
Water Main
- $19,783.00
$1,255,000
$781,522.00
Total
- $60,002.33
$4,637,800
$3,891,920.71
Adequate funds are available in the relating sections of the 2010 Capital Improvement Budget. Adequate
funding is available is the Storm Sewer section from other projects.
RECOMMENDATIONS
recommend approval of the Change Order #3 to Contact No. 10 -05 in the amount of - $60,002.33 Bowers &
Sons Construction Co. Inc.
Respectfully Submitted,
A )%V
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
L \Engineering \] 0 -05 Concrete Paving - SOUTH \Project_]nformation \Correspondence \Memo\CO #3 10 -05 exp.doc