Auto Repair Building
Owner: Midas Realty Corporation
Tenant: Walt Ringer - -Midas Muffler Shop
360 South Koeller
Oshkosh, Winnebago County
Plan Number: 83- 03- 0037 -B
Inspection Fees Previously Paid
Supervising Architect: Westing E. Pence
Revised building plans have been reviewed by the Department of Industry, Labor
and Human Relations for compliance with the important code requirements. The
plans are stamped "Conditionally Approved," and construction may proceed sub -
ject to local regulations, but all items that are required to be changed by
this letter must be corrected before commencing that part of the work.
You are hereby advised that the owner as defined in Chapter 101.01 (2) (i)
of the Wisconsin State Statutes is responsible for all code requirements not
specifically cited herein. Code requirements are set forth in Chapters 50
through 64 of the Rules of the Department.
The building will be inspected during and after construction by a deputy of
this department to insure complete compliance with Wisconsin Codes. The owner
may notify the state building inspector listed below if a final inspection is
desired before taking possession of the building.
Ind 50.15 Evidence of approval. The architect, professional engineer,
designer, builder or owner shall keep at the building, one set of plans bearing
the stamp of approval.
NOTE: This revision covers the deletion of the "racking system," a decrease
in size of the mezzanine area above the office, and the addition of the
required stairway from the mezzanine.
Mr. Westing E. Pence
December 23, 1983
Page 2
I will also write to indicate receipt of additional structural calculations
requested by Mr. Covill's report and orders, which indicate a change in framing
from the originally approved plans to a double "C" channel, 10 inches deep and
having a metal thickness of 16- gauge. The calculations indicate these joists
are to be provided at 12 inches on center. In the future, such a change as
this should be reflected on the revised plan. Your revised plan, which I con-
ditionally approved, still indicates the "10 JP14" joists being used for the
mezzanine framing. This approval now reflects the double "C" joists which
should have been reflected on the plans. You are also reminded that these
double "C" joists are not approved as a substitute for the wood freeing
required for the 2 -hour ceiling assembly of the mechanical equipment room.
You are also reminded that as typically shown on Sheet A -1 "partial mezzanine
framing plan" a double joist is required to be provided at the edge of the
stairway opening. This will require two of the double "C" joists.
I will also use this letter to indicate that the plans for the storage racking
system, previously submitted, have been stamped "Not Approved," and are being
returned.
Sincerely,
Janes B. Smith
Plan Examiner
Tel. 608/266 -0251
JBS :FR2302
cc: R- 3—Covill, phone 715/346 -3493, Friday a.m.
,Oshkosh Building Inspector