April 15, 2004
Riederer Engineering LLC
2626 E. Wisconsin Avenue
Appleton, WI 54911
Lourdes High School Addition (Phase I)
Ref: Plumbing Plan Approval: 110 N. Sawyer St., Oshkosh, WI
Plan ID# C6 -99- 0404 -P
Dear Sirs,
Examination of the plumbing plans and specifications for this project has been completed. In
accord with Chapter 145, Wisconsin Statute, and COMM 81 through 85, Wisconsin
Administrative Code, the plumbing plans and specifications are approved contingent upon
compliance with the stipulation(s) noted below.
1. Review of storm sewer design will include stipulation that the minimum size of
18" diameter indicated on the plan for the storm sewer on the north end of the
structure addition at 1/16 " /ft pitch is the correct size and pitch for the indicated
GPM load. No verification of the indicated load or invert elevations for either
existing drain or main sewer is determined by this review and field verification by
the installer will be required to satisfy the requirements of COMM 82.36 since
pipe size and pitch are at the minimums required by that code.
2. This review is for storm sewer only as "Phase I "and does not include
review of any other portion of the plumbing design.
In the event installation of this plumbing system has not commenced within two years from this
date, this approval shall become void. A new application accompanied by full examination
fees shall be filed and an updated approval received before work may commence.
In granting this approval, the City of Oshkosh or its representative does not hold itself liable for
any defects in plans or specifications, plan omissions, examination oversight, construction or
any damage that may result in or after installation. The City of Oshkosh reserves the right to
order changes or additions should conditions arise making this necessary.
It shall be necessary for the installing plumber to obtain a plumbing permit from the City of
Oshkosh before proceeding with actual installation of this plumbing system or any of its parts.
Res • ectfully,
Richard Wood,
Plumbing Inspector