HomeMy WebLinkAbout11-24JANUARY 25, 2011 11 -24 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 10-25 WITH VINTON CONSTRUCTION CO. FOR
CONCRETE PAVING /STREET PATCHING /SIDEWALK/
UTILITIES (- $73,223.90)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
VINTON CONSTRUCTION CO.
PO Box 1987
Manitowoc, WI 54221
Net Decrease to contract: (- $73,223.90)
PURPOSE: See attached Change Order.
( 0
Of HKO H
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: January 19, 2011
RE: Change Order #1 for Public Works Contract No. 10 -25; for Vinton Construction Co. for Concrete
Paving / Street Patching / Sidewalk / Utilities (- $73,223.90)
BACKGROUND
Change Order #1 for Contract 10 -25 is scheduled for consideration by the Common Council at the January 25,
2011 meeting. The contract was originally awarded to Vinton Construction Co. in September of 2010. This
change order is for additional work required to complete the contract and removes work for the project that was
not able to be completed.
ANALYSIS
Following is a summary of the significant additional work items performed for each section of the CIP.
- Street/Sidewalk — Sidewalk on 9th Ave was not installed due to the need to acquire additional right of
way.
- Sanitary Sewer — Additional pipe was repaired and additional chimney seals were installed.
-Storm Sewer — Storm sewer work on 9 Ave was not completed due to the elimination of the sidewalk
installation.
FISCAL IMPACT
Contract Section
Change Order Amount
CIP Budget Amount
New Contract Total
Street/Sidewalk
- $67,738.40
$293,823.65
$379,445.60
Sanitary Sewer
$5,469.50
NA
$21,999.50
Storm Sewer
- $10,955.00
NA
$2,250.00
Totals
- $73,223.90
$293,823.65
$403,695.10
Adequate funds are available in the relating sections of the 2010 Capital Improvement Budget. We are able to
do additional paving and utility work beyond what was budgeted due to other projects coming in under budget or
not being constructed (Washburn Street resurfacing).
RECOMMENDATIONS
recommend approval of the Change Order #1 to Contact No. 10 -25 in the amount of - $73,223.90 to Vinton
Construction Co.
Respectfully Submitted,
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
I: \Engineering \10 -25 Conc. Paving, Pav't. Repair, New Sidewalk\Project_ Information \Correspondence\Memo \CO #I exp 10- 25.doc
CHANGE ORDER # 1
DATED: January 6, 2011
TO: Vinton Construction Co.
P. O. Box 1987
Manitowoc, WI 54221
Your present contract with the City of Oshkosh, Contract No
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING
NET DECREASE TO: SECTION II - STORM SEWER
NET INCREASE TO: SECTION III - SANITARY SEWER
NET DECREASE TO CONTRACT:
Recommended:
Director of Public Works
10 -25 , is hereby amended
($67,738.40)
($10,955.00)
$5,469.50
($73,223.90)
CITY OF OSHKOSH
City Manager
City Clerk
Approved and accepted:
C� ntractor "
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 10 -25 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
100
Pavement removal,
Square
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
Sidewalk and driveway
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
100
Pavement removal,
Square
complete asspecified
Yards
5
2.80
-2.20
$13.00
($28.60)
101
Sidewalk and driveway
removal, complete as
Square
specified
Feet
220
- 220.00
$0.85
($187.00)
102
Excavation, complete as
Cubic
, specified
Yards
335
317.80
-17.20
$12.00
($206.40)
103
7" Non - reinforced concrete
pavement, including
integral curb and grading,
base in place, complete as
specified
Square
Yards
785
779.30
-5.70
$33.07
($188.50)
104
8" Non - reinforced concrete
pavement, including
integral curb and grading,
base in place, complete as
specified
Square
Yards
3,525
3,490.70
-34.30
$30.55
($1,047.87)
105
8" Non - reinforced concrete
pavement removal and
replacement (HES),
including sawing,
pavement ties, integral
curb & grading, & traffic
control, complete as
Square
specified
Yards
4,990
4,902.80
-87.20
$42.07
($3,668.50)
106
Sidewalk curb, complete as
Linear
specified
Feet
40
-40.00
$30.00
($1,200.00)
107
4" Concrete sidewalk,
Square
complete asspecified
Feet
8,025
- 8,025.00
$4.45
($35,711.25)
108
6" Concrete sidewalk &
driveway, complete as
Square
, specified
Feet
1,650
231.60
- 1,418.40
$5.00
($7,092.00)
109
3 %" Asphaltic concrete
transition and driveway,
Square
complete asspecified
Yard
425
369.80
-55.20
$17.63
($973.18)
110
Furnish and install crushed
stone base course,
complete as specified
Tons
670
840.00
170.00
$10.50
$1,785.00
111
Sawing, complete as
Linear
specified
Feet
265
117.80
- 147.20
$3.00
($441.60)
112
Furnish and install
pavement ties (epoxy
coated), complete as
specified
Each
26
24.00
-2.00
$8.00
($16.00)
113
Adjust manholes and inlets,
complete as specified
Each
29
30.00
1.00
$300.00
$300.00
114
Furnish and install No. 4
reinforcing bars (epoxy
coated), complete as
Linear
, specified
Feet
420
- 420.00
$1.50
($630.00)
Page 1 of 4
CONTRACT: 10 -25 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
Sewer, complete as
Linear
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
115
Remove trees and stumps,
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
201
complete as specified
Inch
PRICE
PRICE
Storm Sewer with
Diameter
92
-92.00
$20.00
($1,840.00)
116
Provide and install metal
Linear
detectable warning plates,
Feet
60
0.00
-60.00
$50.00
($3,000.00)
complete as specified
Square
Feet
72
-72.00
$30.00
($2,160.00)
117
Profile sawcut concrete
curb, complete as specified
Linear
Feet
20
-20.00
$30.00
($600.00)
118
Rout and seal existing
transverse cracks,
Linear
complete asspecified
Feet
90
412.50
322.50
$5.00
$1,612.50
119
Furnish and install cold
weather covering, 1 -layer
visquine, complete as
Square
specified
Yards
3,100
- 3,100.00
$1.25
($3,875.00)
120
Furnish and install cold
weather covering, 2 -layer
visquine, complete as
Square
specified
Yards
3,100
- 3,100.00
$0.01
($31.00)
121
Furnish and install cold
weather covering, 2 -layer
visquine and 6" hay,
Square
complete asspecified
Yards
3,100
- 3,100.00
$0.01
($31.00)
122
Terrace work on Omni
Drive, complete as
Lump
s ecified
Sum
1
1.00
$7,200.00
123
Terrace work on Oakwood
Road, Westhaven Drive,
Witzel Avenue, and W. 9`
Avenue, complete as
specified
Square
Yards
2,500
1 308.00
1
1 - 2,192.00
$5.25
($11,508.00)
SECTION I - (BID ITEMS 100 - 123) - SUB - TOTALS $3,697.50 ($71,435.90)
NET DECREASE TO: SECTION 1 ($67,738.40)
SECTION 11 - STORM SEWER
200
Furnish and install 8" Storm
INCREASE IN
DECREASE IN
ITEM
Sewer, complete as
Linear
CONTRACT
INSTALLED
NET
NET
COST PER
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
201
Furnish and install 12"
PRICE
PRICE
200
Furnish and install 8" Storm
Sewer, complete as
Linear
specified
Feet
6
0.00
-6.00
$37.50
($225.00)
201
Furnish and install 12"
Storm Sewer with
endwalls, complete as
Linear
, specified
Feet
60
0.00
-60.00
$50.00
($3,000.00)
Page 2 of 4
CONTRACT: 10 -25 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
202
Furnish and install 15"
Feet
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
301
Storm Sewer with
endwalls, complete as
Linear
s ecified
Feet
60
0.00
-60.00 1
$56.00
($3,360.00)
203
Furnish and install Std.
Storm Manhole (2' inside
Each
8.00
9.00
1.00
$535.00
$535.00
diameter) in one location
with casting, complete as
, specified
Each
1
0.00
-1.00
$990.00
($990.00)
204
Furnish and install Std.
Storm Manhole (4' inside
diameter) in one location
with casting and 518" steel
plate, complete as
s ecified
Each
1
0.00
-1.00
$1,700.00
($1,700.00)
205
Furnish, install, and
maintain Type "D" Inlet
Protection Std., complete
asspecified
Each
37
25.00
-12.00
$90.00
($1,080.00)
206
Furnish, install, and
maintain stone bag ditch
checks, complete as
specified
Each
8
0.00
-8.00
$75.00
($600.00)
I I
SECTION II - (BID ITEMS 200 - 206) - SUB - TOTALS $0.00 ($10,955.00)
NET DECREASE TO: SECTION II ($10,955.00)
SECTION III - SANITARY SEWER
300
Furnish and install 10"
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
complete asspecified
Feet
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
300
Furnish and install 10"
sanitary sewer (relay),
Linear
complete asspecified
Feet
70.00
89.50
19.50
$175.00
$3,412.50
301
Furnish and install 9"
Cretex external manhole
chimney seal (or
equivalent), 34" diameter,
complete asspecified
Each
8.00
9.00
1.00
$535.00
$535.00
SECTION III - (BID ITEMS 300 - 301 ) - SUB - TOTALS $3,947.50 $0.00
Page 3 of 4
CONTRACT: 10 -25 CHANGE ORDER # 1
ITEM
Furnish & install 8" Exteral
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
Each
5.00
5.00
$184.00
PRICE
PRICE
ADDITIONAL WORK REQUIRED: C.O. # 1- SECTION III
ITEM
Furnish & install 8" Exteral
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
Each
5.00
5.00
$184.00
PRICE
PRICE
302
Furnish & install 8" Exteral
Chimney Seal extensions
Each
5.00
5.00
$184.00
$920.00
303
Furnish & install internal
Chinme Seal
Each
2.00
2.00
$301.00
$602.00
ADDITIONAL WORK: C. O. # 1 - (ITEMS 302 - 303) - SUB -TOTAL $1,522.00 $0.00
NET INCREASE TO: SECTION 111 $5,469.50
NET INCREASE TO SECTIONS I, 11, 111 $9,167.00
NET DECREASE TO SECTIONS I, 11, III ($82,390.90)
NET DECREASE TO CONTRACT: ($73,223.90)
Page 4 of 4