HomeMy WebLinkAbout11-24JANUARY 25, 2011 11 -24 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS CONTRACT NO. 10-25 WITH VINTON CONSTRUCTION CO. FOR CONCRETE PAVING /STREET PATCHING /SIDEWALK/ UTILITIES (- $73,223.90) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: VINTON CONSTRUCTION CO. PO Box 1987 Manitowoc, WI 54221 Net Decrease to contract: (- $73,223.90) PURPOSE: See attached Change Order. ( 0 Of HKO H ON THE WATER MEMORANDUM TO: Honorable Mayor and Members of the Common Council FROM: Steven M. Gohde, Assistant Director of Public Works DATE: January 19, 2011 RE: Change Order #1 for Public Works Contract No. 10 -25; for Vinton Construction Co. for Concrete Paving / Street Patching / Sidewalk / Utilities (- $73,223.90) BACKGROUND Change Order #1 for Contract 10 -25 is scheduled for consideration by the Common Council at the January 25, 2011 meeting. The contract was originally awarded to Vinton Construction Co. in September of 2010. This change order is for additional work required to complete the contract and removes work for the project that was not able to be completed. ANALYSIS Following is a summary of the significant additional work items performed for each section of the CIP. - Street/Sidewalk — Sidewalk on 9th Ave was not installed due to the need to acquire additional right of way. - Sanitary Sewer — Additional pipe was repaired and additional chimney seals were installed. -Storm Sewer — Storm sewer work on 9 Ave was not completed due to the elimination of the sidewalk installation. FISCAL IMPACT Contract Section Change Order Amount CIP Budget Amount New Contract Total Street/Sidewalk - $67,738.40 $293,823.65 $379,445.60 Sanitary Sewer $5,469.50 NA $21,999.50 Storm Sewer - $10,955.00 NA $2,250.00 Totals - $73,223.90 $293,823.65 $403,695.10 Adequate funds are available in the relating sections of the 2010 Capital Improvement Budget. We are able to do additional paving and utility work beyond what was budgeted due to other projects coming in under budget or not being constructed (Washburn Street resurfacing). RECOMMENDATIONS recommend approval of the Change Order #1 to Contact No. 10 -25 in the amount of - $73,223.90 to Vinton Construction Co. Respectfully Submitted, Steven M. Gohde Asst. Director of Public Works Approved: City Manager I: \Engineering \10 -25 Conc. Paving, Pav't. Repair, New Sidewalk\Project_ Information \Correspondence\Memo \CO #I exp 10- 25.doc CHANGE ORDER # 1 DATED: January 6, 2011 TO: Vinton Construction Co. P. O. Box 1987 Manitowoc, WI 54221 Your present contract with the City of Oshkosh, Contract No and changed as follows: NET DECREASE TO: SECTION I - CONCRETE PAVING NET DECREASE TO: SECTION II - STORM SEWER NET INCREASE TO: SECTION III - SANITARY SEWER NET DECREASE TO CONTRACT: Recommended: Director of Public Works 10 -25 , is hereby amended ($67,738.40) ($10,955.00) $5,469.50 ($73,223.90) CITY OF OSHKOSH City Manager City Clerk Approved and accepted: C� ntractor " I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Comptroller Approved as to form: City Attorney CONTRACT: 10 -25 CHANGE ORDER # 1 SECTION I - CONCRETE PAVING 100 Pavement removal, Square INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER Sidewalk and driveway QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 100 Pavement removal, Square complete asspecified Yards 5 2.80 -2.20 $13.00 ($28.60) 101 Sidewalk and driveway removal, complete as Square specified Feet 220 - 220.00 $0.85 ($187.00) 102 Excavation, complete as Cubic , specified Yards 335 317.80 -17.20 $12.00 ($206.40) 103 7" Non - reinforced concrete pavement, including integral curb and grading, base in place, complete as specified Square Yards 785 779.30 -5.70 $33.07 ($188.50) 104 8" Non - reinforced concrete pavement, including integral curb and grading, base in place, complete as specified Square Yards 3,525 3,490.70 -34.30 $30.55 ($1,047.87) 105 8" Non - reinforced concrete pavement removal and replacement (HES), including sawing, pavement ties, integral curb & grading, & traffic control, complete as Square specified Yards 4,990 4,902.80 -87.20 $42.07 ($3,668.50) 106 Sidewalk curb, complete as Linear specified Feet 40 -40.00 $30.00 ($1,200.00) 107 4" Concrete sidewalk, Square complete asspecified Feet 8,025 - 8,025.00 $4.45 ($35,711.25) 108 6" Concrete sidewalk & driveway, complete as Square , specified Feet 1,650 231.60 - 1,418.40 $5.00 ($7,092.00) 109 3 %" Asphaltic concrete transition and driveway, Square complete asspecified Yard 425 369.80 -55.20 $17.63 ($973.18) 110 Furnish and install crushed stone base course, complete as specified Tons 670 840.00 170.00 $10.50 $1,785.00 111 Sawing, complete as Linear specified Feet 265 117.80 - 147.20 $3.00 ($441.60) 112 Furnish and install pavement ties (epoxy coated), complete as specified Each 26 24.00 -2.00 $8.00 ($16.00) 113 Adjust manholes and inlets, complete as specified Each 29 30.00 1.00 $300.00 $300.00 114 Furnish and install No. 4 reinforcing bars (epoxy coated), complete as Linear , specified Feet 420 - 420.00 $1.50 ($630.00) Page 1 of 4 CONTRACT: 10 -25 CHANGE ORDER # 1 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COSTPER INCREASE IN CONTRACT DECREASE IN CONTRACT NUMBER Sewer, complete as Linear QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 115 Remove trees and stumps, UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT 201 complete as specified Inch PRICE PRICE Storm Sewer with Diameter 92 -92.00 $20.00 ($1,840.00) 116 Provide and install metal Linear detectable warning plates, Feet 60 0.00 -60.00 $50.00 ($3,000.00) complete as specified Square Feet 72 -72.00 $30.00 ($2,160.00) 117 Profile sawcut concrete curb, complete as specified Linear Feet 20 -20.00 $30.00 ($600.00) 118 Rout and seal existing transverse cracks, Linear complete asspecified Feet 90 412.50 322.50 $5.00 $1,612.50 119 Furnish and install cold weather covering, 1 -layer visquine, complete as Square specified Yards 3,100 - 3,100.00 $1.25 ($3,875.00) 120 Furnish and install cold weather covering, 2 -layer visquine, complete as Square specified Yards 3,100 - 3,100.00 $0.01 ($31.00) 121 Furnish and install cold weather covering, 2 -layer visquine and 6" hay, Square complete asspecified Yards 3,100 - 3,100.00 $0.01 ($31.00) 122 Terrace work on Omni Drive, complete as Lump s ecified Sum 1 1.00 $7,200.00 123 Terrace work on Oakwood Road, Westhaven Drive, Witzel Avenue, and W. 9` Avenue, complete as specified Square Yards 2,500 1 308.00 1 1 - 2,192.00 $5.25 ($11,508.00) SECTION I - (BID ITEMS 100 - 123) - SUB - TOTALS $3,697.50 ($71,435.90) NET DECREASE TO: SECTION 1 ($67,738.40) SECTION 11 - STORM SEWER 200 Furnish and install 8" Storm INCREASE IN DECREASE IN ITEM Sewer, complete as Linear CONTRACT INSTALLED NET NET COST PER NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT 201 Furnish and install 12" PRICE PRICE 200 Furnish and install 8" Storm Sewer, complete as Linear specified Feet 6 0.00 -6.00 $37.50 ($225.00) 201 Furnish and install 12" Storm Sewer with endwalls, complete as Linear , specified Feet 60 0.00 -60.00 $50.00 ($3,000.00) Page 2 of 4 CONTRACT: 10 -25 CHANGE ORDER # 1 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN CONTRACT DECREASE IN CONTRACT NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 202 Furnish and install 15" Feet QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 301 Storm Sewer with endwalls, complete as Linear s ecified Feet 60 0.00 -60.00 1 $56.00 ($3,360.00) 203 Furnish and install Std. Storm Manhole (2' inside Each 8.00 9.00 1.00 $535.00 $535.00 diameter) in one location with casting, complete as , specified Each 1 0.00 -1.00 $990.00 ($990.00) 204 Furnish and install Std. Storm Manhole (4' inside diameter) in one location with casting and 518" steel plate, complete as s ecified Each 1 0.00 -1.00 $1,700.00 ($1,700.00) 205 Furnish, install, and maintain Type "D" Inlet Protection Std., complete asspecified Each 37 25.00 -12.00 $90.00 ($1,080.00) 206 Furnish, install, and maintain stone bag ditch checks, complete as specified Each 8 0.00 -8.00 $75.00 ($600.00) I I SECTION II - (BID ITEMS 200 - 206) - SUB - TOTALS $0.00 ($10,955.00) NET DECREASE TO: SECTION II ($10,955.00) SECTION III - SANITARY SEWER 300 Furnish and install 10" INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER complete asspecified Feet QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 300 Furnish and install 10" sanitary sewer (relay), Linear complete asspecified Feet 70.00 89.50 19.50 $175.00 $3,412.50 301 Furnish and install 9" Cretex external manhole chimney seal (or equivalent), 34" diameter, complete asspecified Each 8.00 9.00 1.00 $535.00 $535.00 SECTION III - (BID ITEMS 300 - 301 ) - SUB - TOTALS $3,947.50 $0.00 Page 3 of 4 CONTRACT: 10 -25 CHANGE ORDER # 1 ITEM Furnish & install 8" Exteral CONTRACT INSTALLED NET NET COSTPER INCREASE IN DECREASE IN NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT Each 5.00 5.00 $184.00 PRICE PRICE ADDITIONAL WORK REQUIRED: C.O. # 1- SECTION III ITEM Furnish & install 8" Exteral CONTRACT INSTALLED NET NET COST PER INCREASE IN DECREASE IN NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT CONTRACT CONTRACT Each 5.00 5.00 $184.00 PRICE PRICE 302 Furnish & install 8" Exteral Chimney Seal extensions Each 5.00 5.00 $184.00 $920.00 303 Furnish & install internal Chinme Seal Each 2.00 2.00 $301.00 $602.00 ADDITIONAL WORK: C. O. # 1 - (ITEMS 302 - 303) - SUB -TOTAL $1,522.00 $0.00 NET INCREASE TO: SECTION 111 $5,469.50 NET INCREASE TO SECTIONS I, 11, 111 $9,167.00 NET DECREASE TO SECTIONS I, 11, III ($82,390.90) NET DECREASE TO CONTRACT: ($73,223.90) Page 4 of 4