HomeMy WebLinkAbout10-383DECEMBER 14, 2010 10 -383 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDERS FOR RIVERSIDE PARK PHASE 2 SEAWALL & RIVERWALK CONSTRUCTION WITH PHENCO, INC. ( +$99,952.74) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: PHENCO, INC. 133 S. Fieldcrest Dr. Neenah, WI 54903 Net Increase to contract: $99,952.74 PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Acct. No. 561 - 2010- 1799 -00000 Storm Water Utility— Construction Work In Progress Acct. No. 323 - 0740 - 7216 -06020 Property Improvement- Riverwalk/Riverside Park CITY HALL 215 Church Avenue P.O. Box 1130 Os Wisconsin 549 -1 03 - 1130 130 City of Oshkosh 0 OIHKOIH TO: Honorable Mayor and Members of the Common Council FROM: Ray Maurer, Parks Director DATE: December 8, 2010 RE: Change Orders for Riverside Park Phase 2 Seawall & River Walk Project BACKGROUND Change orders for the Riverside Park Phase 2 Seawall & River Walk Project are scheduled for consideration by the Common Council at the December 14, 2010 meeting. The contract was originally awarded to Phenco, Inc. of Neenah, WI in May, 2010. The original project budget was approximately $1,350,000. ANALYSIS Change order 1 reflects a modification to the security fence from the original plan to accommodate events at the Convention Center. Change order 2 reflects a modification in the seawall from the original plan to not disturb the integrity of the water main crossing within the project area. Change order 3 reflects work on storm sewer connections through the project area that is being charged to the Storm Water Utility as this work was a connection to the Main Street project. Change order 4 reflects storm sewer connections that were discovered during the project from the Convention Center site and roof to the storm sewers within the project area. This discovery required an upsizing in the pipe size for these connections. Change order 5 reflects the demolition of the old gazebo that was located on the site. Change order 6 reflects the need for the contractor to provide 2 additional months of Builders Risk Insurance through the completion of the project (lights and bollards need to be installed yet). The lights and bollards were ordered by the city and there has been a delay in the delivery of these items. The remainder of the change order adjusts the estimated bid quantities to the actual quantities installed during the construction. FISCAL IMPACT The original bid award of $871,933.33 will be increased to $971,886.07. A total of $36,606 from Change Order #3 will be charged to the Storm Water Utility as part of the Main Street reconstruction. The remaining $63,346.74 is within the project contingency. The project will remain under budget by approximately $375,000. RECOMMENDATION I recommend approval of the change orders for the Riverside Park Phase 2 Seawall & River Walk Project in the amount of $99,952.74 to Phenco, Inc. Respectfully Submitted, J4a_c -� ay Maurer, Parks Director Approved: Mark Rohloff, City Manager n CHANGE ORDERS DATED: December 3, 2010 TO; Phenco, Inc. 133 S Fieldcrest Drive Neenah, Wisconsin 54903 Your present contract with the City of Oshkosh, Contract for Riverside Park Phase 2 Seawall and Riverwalk Construction, is hereby amended and changed as follows: Item Number /Description Add CO 1 Security Fence Modification $564.00 CO 2 Water Main Crossing Modification $17,888.00 CO 3 Additional Storm Sewer, Connection to Main Street $36,606.00 CO 4 Convention Center Storm Sewer Modification $17,012.25 CO 5 Gazebo Demolition $200.00 CO 6 Additional 2 Months of Builders Risk Insurance $ 900.00 C -2 Landfill Transportation add 995 CYD. $8,308.25 C -5 Clean Fill Timber bulkhead and Steel Wall add 61.43 tons $890.73 D -4 Concrete Walk Way add 60 SF $582.00 D -7 Replacement Curb add 34 LF $2,244.00 E -1 Erosion Control Silt Fence add 520 If $1,040.00 E -5 Erosion Control Matting add 3,895 SY $5,842.50 G -5 Seed and Fertilizer add 3,895 SY $12,853.35 $104,931.08 Subtotal Additions Item Number /Description < Deduct> C -4 Select Crushed Stone Backf ill deduct 340.11 tons < $3,520.14> H -4 Heavy Rip Rap deduct 63.4 tons < $1,458.20 > < $4,978.34> Subtotal Deductions. NET INCREASE TO CONTRACT 99,952.74 2 ORGINAL CONTRACT AMOUNT $871,933.33 REVISED CONTRACT AMOUNT $971,886.07 City of Oshkosh By: .l And: Approved and accepted: Phenco, Inc. By: Contractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order.