HomeMy WebLinkAbout10-242AUGUST 10, 2010 10 -242 RESOLUTION
(CARRIED 6 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC
WORKS CONTRACT 09 -18 WITH NORTHEAST ASPHALT
INC. FOR ASPHALT PAVING & UNDERGROUND WORK
(-$31,356.00)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
NORTHEAST ASPHALT INC.
W6380 Design Drive
Greenville, WI 54952
Net Decrease to contract: (- $31,356.00)
PURPOSE: See attached Change Order.
CHANGE ORDER # 1
DATED: June 23, 2010
TO: Northeast Ashpalt Inc
W6380 Design Drive
Greenville, WI 54952
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
NET DECREASE TO: SECTION I -ASPHALT PAVING
NET DECREASE TO: SECTION II - STORM SEWER
NET DECREASE TO: SECTION III - SANITARY SEWER
NET DECREASE TO CONTRACT:
Recommended:
Director of Public Works
09 -18 , is hereby amended
($26,374.15)
($1,059.85)
($3,922.00)
($31,356.00)
CITY OF OSHKOSH
BY:
City Manager
City Clerk
App a and accepted:
Contractor
7�
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 09 -18 CHANGE ORDER # 1
SECTION I - ASPHALT PAVING
100.
Sidewalk and driveway
INCREASE IN
DECREASE IN
ITEM
removal, complete as
Square
CONTRACT
INSTALLED
NET
NET
COST PER
DESCRIPTION
UNIT
1,745
2,099.00
354.00
$1.48
CONTRACT
CONTRACT
NUMBER
Excavation, complete as
Cubic
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
specified
Yards
1,230
694.00
- 536.00
$15.26
PRICE
PRICE
100.
Sidewalk and driveway
removal, complete as
Square
specified
Feet
1,745
2,099.00
354.00
$1.48
$523.92
101.
Excavation, complete as
Cubic
specified
Yards
1,230
694.00
- 536.00
$15.26
($8,179.36
102.
Asphalt pavement milling,
Square
complete asspecified
Yards
9,600
9,600.00
$2.35
103.
Asphaltic concrete
pavement, lower layer,
complete asspecified
Tons
1,430
1,612.00
182.00
$62.00
$11,284.00
104.
Asphaltic concrete
pavement, upper layer,
complete asspecified
Tons
1 1,220
1,109.00
- 111.00 1
$62.00
($6,882.00)
105.
3 ' /1 ' asphaltic concrete
driveway, complete as
Square
s ecified
Feet
1,950
1,454.00
- 496.00
$4.75
$2,356.00
106.
Asphalt pavement repair,
Square
, complete asspecified
Yards
60
83.00
23.00
$35.00
$805.00
107.
Tack or prime coat,
complete asspecified
Gallon
330
300.00
-30.00
$3.00
($90.00
108.
4" concrete sidewalk,
Square
complete asspecified
Feet
1,000
1,192.00
192.00
$3.50
$672.00
109.
6" concrete sidewalk &
driveway, complete as
Square
specified
Feet
385
332.00
-53.00
$3.75
($198.75
110.
6" H.E.S. concrete
sidewalk & driveway,
Square
complete asspecified
Feet
320
562.00
242.00
$4.77
$1,154.34
111.
Furnish and install crushed
stone base course,
complete as specified
Tons
2,100
1,058.00
- 1,042.00
$13.50
$14,067.00)
112.
One foot (1') gravel
shoulder, complete as
Linear
specified
Feet
6,700
6,844.00
144.00
$1.00
$144.00
113.
Sawing, complete as
Linear
specified
Feet
1,390
1,279.00
- 111.00
$1.30
($144.30
114.
Adjust manholes and inlets,
complete as specified
Each
30
6.00
-24.00
$415.00
$9,960.00)
115.
Remove trees and stumps,
complete as specified
Inch
Diameter
1 65
88.00
23.00
1 $40.00
$920.00
116.
Furnish and install trees,
. Complete asspecified
Each
3
3.00
$500.00
117.
Preparation of foundation
for asphalt paving on
Congress Avenue,
complete asspecified
Lump Sum
1
1.00
$1,990.00
118.
Preparation of foundation
for asphalt paving on
Stoney Beach Road,
com lete asspecified
Lump Sum
1
1.00
$3,000.00
Page 1 of 4
CONTRACT: 09 -18 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
119.
Preparation of foundation
PRICE
PRICE
for asphalt paving on
Stoney Beach Lane,
complete asspecified
Lump Sum
1
1.00
$3,075.00
120.
Preparation of foundation
for asphalt paving on
Stoney Beach Street,
complete asspecified
Lump Sum
1
1.00
$3,100.00
121.
Preparation of foundation
for asphalt paving on public
alley south of Oshkosh
Avenue (N. Eagle St. to
Punhoqua St.), complete
as specified
Lump Sum
1
1.00
$3,050.00
122.
Preparation of foundation
for asphalt paving on public
alley north of Algoma Blvd.,
complete as specified
Lump Sum
1
1.00
$1,975.00
123.
Preparation of foundation
for asphalt paving on W.
25th Avenue cul -de -sac,
complete asspecified
Lump Suml
1
1.00
$2,500.00
124.
Preparation of foundation
for asphalt paving on
Progress Drive, complete
asspecified
Lump Sum
1
1.00
$2,300.00
125.
Terrace work on Stoney
Beach Road, complete as
, specified
Lump Sum
1
1.00
$8,600.00
126.
Terrace work on Stoney
Beach Lane, complete as
specified
Lump Sum
1
1.00
$4,800.00
127.
Terrace work on Stoney
Beach Street, complete as
s ecified
Lump Sum
1
1.00
$6,700.00
128.
Terrace work on public
alley south of Oshkosh
Avenue (N. Eagle St. to
Punhoqua St.), complete
asspecified
Lump Sum
1
1.00
$2,900.00
129.
Terrace work on W. 25th
Avenue cul -de -sac,
complete ass ecified
Lump Sum
1
1.00
$1,500.00
SECTION I - (BID ITEMS 100 -129) - SUB - TOTALS $15,503.26 ($41,877.41)
NET DECREASE TO: SECTION 1 ($26,374.15)
SECTION II - STORM SEWER
ITEM
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
Page 2 of 4
CONTRACT: 09 -18 CHANGE ORDER # 1
ITEM
Furnish and install 8"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
complete as specified
Linear
PRICE
PRICE
200.
Furnish and install 12"
Feet
15
7.50
-7.50
$200.00
($1,500.00)
301.
storm sewer, complete as
Linear
specified
Feet
85
85.40
0.40
$18.00
$7.20
201.
Furnish and install 15"
Linear
storm sewer, complete as
Linear
40
18.00
-22.00
$100.00
($2,200.00)
302.
specified
Feet
270
264.90
-5.10
$21.50
($109.65)
202.
Furnish and install std. type
1 inlet (30" inside diameter
Lump Sum
1
1.00
$1,100.00
303.
with 18" sump) without
casting, complete as
. specified
Each
5
5.00
$800.00
203.
Rebuild with base std.
storm manhole (V inside
diameter) in one location
without casting, complete
Vertical
asspecified
Feet
3.3
3.40
0.10
$540.00
$54.00
204.
Furnish and install 6" storm
lateral, complete as
Linear
specified
Feet
90
66.50
-23.50
$14.40
($338.40)
205.
Furnish and install storm
lateral marker balls,
complete asspecified
Each
11
6.00
-5.00
$25.00
$125.00)
206.
Remove 6" storm sewer,
Linear
complete asspecified
Feet
310
186.00
- 124.00
$2.00
$248.00)
207.
Abandon inlets or
manholes, complete as
specified
Each
2
2.00
$280.00
208.
Furnish, install, and
maintain Type "D" inlet
protection, complete as
, specified
Each
25
22.00
-3.00
$100.00
$300.00
SECTION II - (BID ITEMS 200 - 208) - SUB - TOTALS $61.20 ($1,121.05)
NET DECREASE TO: SECTION II ($1,059.85)
SECTION III - SANITARY SEWER
ITEM
Furnish and install 8"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
complete as specified
Linear
PRICE
PRICE
300.
Furnish and install 8"
sanitary sewer spot repair,
complete as specified
Linear
Feet
15
7.50
-7.50
$200.00
($1,500.00)
301.
Furnish and install 10"
sanitary sewer spot repair,
complete as specified
Linear
Feet
40
18.00
-22.00
$100.00
($2,200.00)
302.
Remove and replace 8"
sanitary sewer drop,
complete asspecified
Lump Sum
1
1.00
$1,100.00
303.
Furnish and install 8" x 4"
factory wyes or tees,
complete asspecified
Each
2
2.00
$130.00
Page 3 of 4
CONTRACT: 09 -18 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
304.
Furnish and install 10" x 6"
factory wyes or tees,
—
complete asspecified
Each
4
4.00
$190.00
305.
Furnish and install 4'76"
sanitary lateral relay,
Linear
complete asspecified
Feet
25
17.60
-7.40
$30.00
($222.00)
306.
Furnish and install sanitary
lateral marker balls,
complete as specified
Each
6
6.00
$15.00
307.
Furnish and install
connections of new
sanitary main to existing
main (various locations and
sizes), complete as
specified
Each
9
9.00
$200.00
SECTION III - (BID ITEMS 300 - 307) - SUB - TOTALS
NET DECREASE TO: SECTION III
$0.00 ($3,922.00)
($3,922.00)
NET INCREASE TO SECTIONS I, II, III $15,564.46
NET DECREASE TO SECTIONS I, 11, III ($46,920.46)
NET DECREASE TO CONTRACT: ($31,356.00)
Page 4 of 4
( 0
O HKO H
ON THE WATER
MEMORANDUM
TO:
FROM:
DATE:
RE:
Honorable Mayor and Members of the Common Council
Steven M. Gohde, Assistant Director of Public Works
August 5, 2010
Change Order #1 for Public Works Contract No. 09 -18 / Northeast Asphalt Inc./
Asphalt Paving and Underground Work (- $31,356.00)
BACKGROUND
Change Order #1 for Contract 09 -18 is scheduled for consideration by the Common Council at the August
10, 2010 meeting. The contract was originally awarded to Northeast Asphalt Inc., of Greenville, WI in
September of 2009.
ANALYSIS
This change order adjusts the estimated bid quantities to the actual quantities installed during the
construction. Reductions in the paving section were due to not needing as much stone base as
estimated. Reductions in the storm sewer and sanitary sewer section were due to reduced quantities of
items needed to match field conditions.
FISCAL IMPACT
Funding for the project is in the 2009 Capital Improvement Program Budgets. The original contract
amount was $356,060.05. The change order amounts are - $26,374.15 for Paving, - $1,059.85 for Storm
Sewer, and - $3,922.00 for Sanitary Sewer.
RECOMMENDATIONS
recommend approval of the Change Order # 1 to Contact No. 19 -18 in the amount of - $31,356.00 to
Northeast Asphalt Inc.
Respectfully Submitted,
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
1:\Engineering109 -18 Asphalt Paving\ Project_ Information \Correspondence\Memo\CO #I exp.doc