HomeMy WebLinkAbout10-189JUNE 8, 2010 10 -189 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS CONTRACT NO. 10 -06 FOR FISCHER -ULMAN CONSTRUCTION FOR CONCRETE SIDEWALK- PAVEMENT REPAIRS ( +$35,163.85) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: FISCHER -ULMAN CONSTRUCTION 1115 S. Theodore Street Appleton, WI 54915 Net Increase to contract: $35,163.85 PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Acct. No. 541-1810-1799-00000 — Water Utility Construction Work in Progress Acct. No. 551-1910-1799-00000 — Sewer Utility Construction Work in Progress ( 0 OLHK ON THE WATER MEMORANDUM TO: FROM: DATE: RE: BACKGROUND Honorable Mayor and Members of the Common Council Steven M. Gohde, Assistant Director of Public Works June 3, 2010 Change Order #1 for Public Works Contract No. 10 -06 for Fisher - Ulman Construction for Concrete Sidewalk- Pavement Repairs ( +$35,163.85) Change Order #1 for Contract 10 -06 is scheduled for consideration by the Common Council at the June 8, 2010 meeting. The contract was originally awarded to Fisher - Ulman Construction Inc, of Appleton, WI in April of 2010. ANALYSIS The Department of Public Works requested prices from two contractors to do additional pavement repair in the area adjacent to the Jackson /Murdock Intersection project. The work included replacing defective concrete street pavement and adjacent sidewalk squares outside of the limits of the DOT contract. The lowest quote was received from Fisher - Ulman. FISCAL IMPACT Funding for this work is available in the 2010 Capital Improvement Program (CIP) under Arterial and Collector Street Concrete Pavement Repairs. $100,000 is available in the CIP. The original contract amount was $496,860.00. RECOMMENDATIONS recommend approval of the Change Order #1 to Contact No. 10 -06 in the amount of $35,163.85 to Fisher - Ulman Construction Inc. Respectfully Submitted, Steven M. Gohde Asst. Director of Public Works Approved: City Manager I:\Engineering \10 -06 Concrete Sidewalk\ Project_ Information \Correspondence \Memo\CO #1 exp.doc CHANGE ORDER # 1 DATED: May 24, 2010 TO: FISCHER -ULMAN CONSTRUCTION 1115 S. THEODORE STREET APPLETON, WI 54915 Your present contract with the City of Oshkosh, Contract No. 10 -06 , is hereby amended . and changed as follows: NET INCREASE TO CONTRACT: $35,163.85 CITY OF OSHKOSH BY: Recommended: City Manager Director of Public Works City Clerk Approved and accepted: �'G"ontractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Comptroller Approved as to form: City Attorney CONTRACT: 10 -06 CHANGE ORDER # 1 ADDITIONAL WORK PER QUOTE FOR W. MURDOCK AVENUE PAVEMENT rn wlr0CTC nAVILif_` 100 Sidewalk & driveway Square INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER specified QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 100 Sidewalk & driveway Square removal, complete as Feet specified 0.00 585.00 585.00 0.50 292.50 101 8" Concrete pavement Square including integral curb, Yards pavement removal, sawcut, pavement ties, and landscaping, complete as specified 0.00 625.00 625.001 42.75 26,718.75 102 12" Radius curb head, Linear com lete asspecified Feet 0.00 48.00 48.00 4.00 192.00 103 Standard 30" curb & gutter, Linear T' (tie -in), complete as Feet specified 0.00 15.00 15.00 22.50 337.50 104 4" Concrete sidewalk, Square complete asspecified Feet 0.00 300.00 300.00 2.90 870.00 105 6" Concrete sidewalk & Square driveway, complete as Feet specified 0.00 286.00 286.00 3.35 958.10 106 3 1/2" Asphaltic concrete Square transition, with base, Yards complete asspecified 0.00 105.00 105.00 41.40 4,347.00 107 Adjust manholes and inlets, Each complete as specified 0.00 4.00 4.00 250.00 1,000.00 108 Provide and install metal Square detectable warning plates, Feet complete as specified 0.00 16.00 16.00 28.00 448.00 ADDITIONAL ITEMS - CONCRETE PAVING - SUB - TOTALS 35,163.85 $0.00 NET INCREASE TO CONTRACT 10 -06: 35,163.85 Page 1 of 1