HomeMy WebLinkAbout10-187JUNE 8, 2010 10 -187 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 09 -07 FOR CARL BOWERS & SON
CONSTRUCTION CO. FOR CONCRETE PAVING — UTILITIES /
NORTH SIDE (- $45,071.35)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
CARL BOWERS & SONS CONSTRUCTION CO.
N1844 Maloney Rd.
Kaukauna, WI 54130
Decrease to contract: - $45,071.35
PURPOSE: See attached Change Order.
( 0
HKO H
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: June 2, 2010
RE: Change Order #1 for Public Works Contract No. 09 -07; for Carl Bowers & Sons
Construction Co. for Concrete Paving - Utilities /North Side (- $45,071.35)
BACKGROUND
Change Order #1 for Contract 09 -07 is scheduled for consideration by the Common Council at the June
8, 2010 meeting. The contract was originally awarded to Carl Bowers & Sons Construction Co. Inc. in
June of 2009. This change order balances all items to the actual installed quantities and adds additional
work needed to complete the project.
ANALYSIS
Following is a summary of the significant additional work items performed for each section of the CIP.
- Paving - Deleted the paving of the cul -de -sac bulb on Fernau Ct.
-Storm Sewer - Additional pipe length was installed
- Sanitary Sewer - Additional work to resolve utility conflicts and additional pipe /lateral installation
FISCAL IMPACT
The changes are summarized below.
Contract Section
Change Order Amount
CIP Budget Amount
New Contract Total
Concrete Paving
- $78,935.97
$1,585,700
$1,306,269.53
Storm Sewer
$14,120.46
$838,000
$1,070,963.96
- Sanitary Sewer
$22,128.16
$1,430,000
$525,740.16
Water Main
- $2,384.00
$685,000
$586,596.00
Total
- $45,071.35
$4,538,700
$3,489,569.65
Adequate funds are available in the relating sections of the 2009 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of the Change Order #1 to Contact No. 09 -07 in the amount of - $45,071.35 to Carl
Bowers & Sons Construction Co. Inc.
Respectfully Submitted,
/JAA, /+� -L 4_
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
IAEngineering \09 -07 Concrete Paving - North Side\Project_ Information \Correspondence\Memo \CO 41 exp.doc
CHANGE ORDER # 1
DATED: May 27, 2010
TO: Carl Bowers & Sons Construction Co
N1844 Maloney Rd.
Kaukauna, WI 54130
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING
NET INCREASE TO: SECTION II - STORM SEWER
NET INCREASE TO: SECTION III - SANITARY SEWER
NET DECREASE TO: SECTION IV - WATER MAIN
NET DECREASE TO CONTRACT:
Recommended:
Director of Public Works
F
09 -07 , is hereby amended
($78,935.97)
$14,120.46
$22,128.16
($2,384.00)
($45,071.35)
CITY OF OSHKOSH
City Manager
City Clerk
Approved a accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 09 -07 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE !N
DECREASE 1N
NUMBER
complete asspecified
Yards
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
101
Sidewalk and driveway
PRICE
PRICE
100
Pavement removal,
Square
complete asspecified
Yards
6,785
6290.30
- 494.70
$2.00
$989.40
101
Sidewalk and driveway
removal, complete as
Square
specified
Feet
42,255
45285.60
3,030.60
$0.65
$1,969.89
102
Excavation, complete as
Cubic
specified
Yards
9,530
1 9012.90
- 517.10
$8.25
$4,266.08
103
7" non - reinforced concrete
pavement, including
integral curb, 5" base
material and grading,
Square
complete as specified
Yards
13,195
13189.30
-5.70
$30.30
$172,71
104
8" doweled concrete
pavement, including
integral curb and grading
(base in place), complete
Square
asspecified
Yards
2,885
1 1974.60
- 910.40
$30.00
$27,312.00
105
8" non - reinforced concrete
pavement, including
integral curb and grading,
base in place, complete as
Square
, specified
Yards
6,245
6253.10
8.10
$29.50
$238.95
106
8" non - reinforced concrete
pavement, including
integral curb, 6" base
material and grading,
Square
complete as specified
Yards
3,500
3507.80
7.80
$32.50
$253.50
107
8" non - reinforced H.E.S.
concrete pavement,
including integral curb, 6"
base material and grading,
Square
complete as specified
Yards
420
430.90
10.90
$38.50
$419.65
108
12" wide radius curb head,
Linear
complete as specified
Feet
1,440
1364.50
-75.50
$6.50
$490.75
109
Standard 24" curb & gutter,
7" (tie -in), complete as
Linear
specified
Feet
55
102.80
47.80
$19.00
$908.20
110
Standard 30" curb & gutter,
7" (tie -in), complete as
Linear
specified
Feet
605
682.90
77.90
$19.00
$1,480.10
111
Sidewalk curb, complete
Linear
asspecified
Feet
450
62.80
- 387.20
$18.00
$6,969.60
112
4" concrete sidewalk,
Square
complete asspecified
Feet
21,455
28922.50
7,467.50
$2.81
$20,983.68
113
6" concrete sidewalk &
driveway, complete as
Square
specified
Feet
24,950
21311.80
1
- 3,638.20 1
$3.00
($10,914.60)
114
8" concrete sidewalk &
driveway, complete as
Square
s ecified
Feet 1
2,895
2180.20
- 714.80
$3.42
($2,444.62)
Page 1 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
115
6" concrete steps,
Square
complete asspecified
Feet
95
32.30
-62.70
$32.00
($2,006.40
116
3 %2' asphaltic concrete
driveway, complete as
Square
specified
Feet
175
1367.80
1,192.80
$5.00
$5,964.00
117
3'Y2" asphaltic concrete
transition, with base,
Square
complete asspecified
Yards
1,255
1253.80
-1.20
$22.00
$26.40
118
5" asphaltic concrete
transition, with base,
Square
complete asspecified
Yards
745
1 747.10
2.10
$25.00
$52.50
119
Furnish and install crushed
stone base course,
complete as specified
Tons
3,640
180.00
- 3,460.00
$7.00
$24,220.00
120
Sawing, complete as
Linear
specified
Feet
2,345
2749.50
404.50
$2.00
$809.00
121
Furnish and install
pavement ties (epoxy
coated), complete as
specified
Each
385
427.00
42.00
$7.00
$294.00
122
Adjust manholes and
inlets, complete as
specified
Each
228
239.00
11.00
$225.00
$2,475.00
123
Furnish and install No. 4
reinforcing bars (epoxy
coated), complete as
Linear
specified
Feet
2,160
1480.50
- 679.50
$1.05
($713.48
124
Remove trees and stumps,
complete as specified
Inch
Diameter
400
317.00
-83.00
$10.00
$830.00
125
Remove stumps, complete
Inch
asspecified
Diameter
40
67.00
27.00
$10.00
$270.00
126
Furnish and install trees,
complete asspecified
Each
10
0.00
-10.00
$250.00
$2,500.00)
127
Provide and install metal
detectable warning plates,
Square
complete as specified
Feet
736
692.00
-44.00
$28.30
$1,245.20
128
Terrace work on Babbitz
Avenue (including storm
sewer outfall restoration to
Lake Winnebago),
Lump
complete asspecified
Sum
1
1.00 1
$8,000.00
129
Terrace work on Fernau
Court, complete as
Lump
specified
Sum
1 1
1.00
$9,000.00
Terrace work on Gehres
Court, complete as
Lump
130
specified
Sum
1
1.00
1
$2,100.00
131
Terrace work on Grand
Street, complete as
Lump
s ecified
Sum
1
1.00
$5,500.00
132
Terrace work on Lane
I specified
Street, complete as
Lump
Sum
1
1.00
1
$2,100.00
Page 2 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE !N
INCREASE IN
DECREASE IN
Lump
QUANTITIES
QUANTITIES
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
133
Terrace work on Mt.
1.00
1.00
$127.50
PRICE
PRICE
PRICE
PRICE
Vernon Street, complete as
Lump
CURB & GUTTER ON
Linear
s ecified
Sum
1
1.00
$10,000.00
BABBITZ
134
Terrace work on E. New
658.00
658.00
$3.75
$2,467.50
145
EXTRA - PROFILE
Linear
York Avenue (Jefferson St.
SAWING ON PARKWAY 1
Foot
to Broad St.), complete as
Lump
13.00
$50.00
$650.00
specified
Sum
1
1.00
$10,000.00
135
Terrace work on E.
Parkway Avenue (includes
storm sewer restoration
through park), complete as
Lump
specified
Sum
1
1 1.00
$10,000.00
136
Terrace work on Lawndale
Street storm sewer,
Lump
complete as specified
Sum
1
1.00
$1,350.00
137
Terrace work on E. New
York Avenue storm sewer,
Lump
complete as specified
Sum
1
1.00
$4,000.00
138
Restoration for storm
sewer easement from
Doemel Street to channel
east of White Swan Drive,
Lump
com lete asspecified
Sum
1
1.00
$5,500.00
139
Furnish and install cold
weather covering, 1 -layer
visquine, complete as
Square
F-4,6510.00
specified
Yards
4,650
0.00
$2.00
$9,300.00
140
Furnish and install cold
weather covering, 2 -layer
visquine, complete as
Square
141
s ecified
Furnish and install cold
Yards
4,650
0.00
- 4,650.00
$3.00
($13,950.00
weather covering, 2 -layer
visquine and 6" hay,
Square
complete asspecified
Yards
4,650
0.00
- 4,650.00
$4.00
$18,600.00
142
2" Asphaltic concrete
transition with base,
Square
com fete ass ecified I
Yards
905
1292.60
387.60
1
$18.00
$6,976.80
SECTION I - (BID ITEMS 100 - 142) - SUB - TOTALS $43,095.27 ($126,951.24)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE !N
SUBGRADE, INVOICE
Lump
QUANTITIES
QUANTITIES
IN
DECREASE
UNIT
CONTRACT
CONTRACT
#9367
Sum
1.00
1.00
$127.50
PRICE
PRICE
143
EXTRA - CUT INLET TO
SUBGRADE, INVOICE
Lump
#9367
Sum
1.00
1.00
$127.50
$127.50
144
EXTRA - SEPARATE
CURB & GUTTER ON
Linear
BABBITZ
Foot
658.00
658.00
$3.75
$2,467.50
145
EXTRA - PROFILE
Linear
SAWING ON PARKWAY 1
Foot
1
13.00
13.00
$50.00
$650.00
Page 3 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
storm sewer, complete as
Linear
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
146
EXTRA - RELOCATE
Feet
1,300
1,402.92
102.92
$39.50
PRICE
PRICE
201
EXISTING INLET @ SE
CORNER OF GRAND &
Lump
NEVADA
SUM
1
1.00
1.00
$1,675.00
$1,675.00
ADDITIONAL WORK: C.O. # 1 - (ITEMS 143 -146) - SUB -TOTAL $4,920.00 $0.00
NET DECREASE TO: SECTION 1 ($78,935.97)
SECTION II - STORM SEWER
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
NUMBER
storm sewer, complete as
Linear
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
specified
Feet
1,300
1,402.92
102.92
$39.50
PRICE
PRICE
200
Furnish and install 12"
storm sewer, complete as
Linear
specified
Feet
1,300
1,402.92
102.92
$39.50
$4,065.34
201
Furnish and install 12"
RCP Class III storm sewer,
complete as specified
Linear
Feet
65
1 66.00
1.00
$41.50
$41.50
202
Furnish and install 15"
storm sewer, complete as
Linear
specified
Feet
982
977.69
-4.31
$42.00
$181.02)
203
Furnish and install 15"
RCP Class III storm sewer,
complete as specified
Linear
Feet
395
1 396.20
1.20
$44.00
$52.80
204
Furnish and install 18"
storm sewer, complete as
Linear
specified
Feet
693
737.84
44.84
$45.00
$2,017.80
205
Furnish and install 18"
RCP Class III storm sewer
with joint ties and clay
bedding and backfill,
Linear
complete asspecified
Feet
71 1
71.99
0.99
$46.00
$45.54
206
Furnish and install 21"
storm sewer, complete as
Linear
specified
Feet
36
36.80
0.80
$49.00
$39.20
207
Furnish and install 21"
RCP Class III storm sewer,
complete as specified
Linear
Feet
168 1
167.30
-0.70
$49.00
$34.30
208
Furnish and install 21"
RCP Class III storm sewer
with joint ties and clay
bedding and backfill,
Linear
com lete asspecified
Feet
49
51.70
2.70 1
1
$49.00
$132.30
209
Furnish and install 24°
1
storm sewer, complete as
Linear
specified
Feet
291 1
286.30
-4.70
$50.00
$235.00)
Page 4 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
210
Furnish and install 24" x
38" RCP Class III storm
sewer, complete as
Linear
. specified
Feet
668
649.50
-18.50
$85.00
$1,572.50
211
Furnish and install 29° x
45" RCP Class III storm
sewer, complete as
Linear
specified
Feet
894
871.30
-22.70
$100.00
$2,270.00
212
Furnish and install 34" x
53" RCP Class III storm
sewer, complete as
Linear
specified
Feet
452
435.00
1 -17.00
$107.00
$1,819.00
213
Furnish and install 34" x
53" RCP Class III storm
sewer with joint ties and
clay bedding and backfill,
Linear
complete asspecified
Feet
107
104.70
-2.30
$107.00
$246.10)
214
Furnish and install 38" x
60" RCP Class III storm
sewer, complete as
Linear
specified
Feet
325
304.70
-20.30
$144.00
$2,923.20
215
Furnish and install 43" x
68" RCP Class III storm
sewer, complete as
Linear
specified
Feet
1,532
1,585.20
53.20
$163.00
$8,671.60
216
Furnish and install 43" x
68" RCP Class III storm
sewer with joint ties and
clay bedding and backfill,
Linear
complete asspecified
Feet
42 1
42.00
$163.00
217
Furnish and install 18"
RCP Class III apron
endwall with joint ties,
complete asspecified
Each
1
1.00
$1,000.00
218
Furnish and install 21"
RCP Class III apron
endwall with joint ties,
complete asspecified
Each
1 1
1.00
$1,050.00
219
Furnish and install 34" x
53" RCP Class III apron
endwall with joint ties,
complete asspecified
Each
1
1.00
$2,000.00
220
Furnish and install 43° x
68" RCP Class III apron
endwall with joint ties,
complete asspecified
Each
1
1.00
$3,000.00
221
Furnish and install std.
inlets (Type 1 with 18"
sump) with castings,
complete asspecified
Each
2
2.00
$1,100.00
222
Furnish and install std.
inlets (Type 1 with no
sump) with castings,
complete asspecified
Each
2 1
2.00
$1,100.00
Page 5 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE 1N
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
223
Furnish and install std.
inlets (Type 3 with 18"
sump) with castings,
com lete asspecified
Each
85
1 89.00
4.00
$1,150.00
$4,600.00
224
Furnish and install std.
storm manhole (4' inside
diameter) in 25 locations
without casting, complete
Vertical
asspecified
Feet
104.1
102.53
-1.57
$300.00
$471.00
225
Furnish and install std.
storm manhole (5' inside
diameter) in 3 locations
without casting, complete
Vertical
asspecified
Feet
11.16
1 11.14
-0.02
$400.00
$8.00)
226
Furnish and install std.
storm manhole (6' inside
diameter) in 7 locations
without casting, complete
Vertical
asspecified
Feet
34.1
33.03
1 -1.07
$500.00
($535.00
227
Furnish and install std.
storm manhole (7'x 7') in
15 locations without
casting, complete as
Vertical
, specified
Feet
92.47
1 92.85
0.38
$900.00
$342.00
228
Furnish and install std.
storm inlet manhole (4'
inside diameter) in 1 (one)
location with casting,
complete as specified
Vertical
Feet
3.95
3.79
-0.16
$350.00
$56.00
229
Furnish and install std.
storm inlet manhole (5'
inside diameter) in 1 (one)
location with casting,
complete as specified
Vertical
Feet
3.38
3.29
-0.09
$500.00
$45.00)
230
Furnish and install std.
storm inlet manhole (6'
inside diameter) in 7
locations with casting,
Vertical
complete asspecified
Feet
34.18 1
33.16
-1.02
$575.00
$586.50)
231
Furnish and install 6" storm
lateral, complete as
Linear
, specified
Feet
2,056
1,988.00
-68.00
$27.00
($1,836.00
232
Furnish and install storm
lateral marker balls,
complete asspecified
Each
175
167.00
1
-8.00
$18.00
$144.00
233
Abandon lineal feet of 8" -
12" storm sewer, complete
Linear
asspecified
Feet
1,396
1,396.00
$10.00
234
Abandon lineal feet of 15"
and larger storm sewer,
Linear
complete asspecified
Feet
769
769.00
$10.00
Page 6 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE 1N
NUMBER
#0002046 -IN
Sum
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
242
EXTRA PER INVOICE
Lump
PRICE
PRICE
235
Abandon inlets or
Sum
1.00
1.00
$550.00
$550.00
243
manholes, complete as
Lump
specified
Each
36
36.00
1.00
$250.00
$300.00
236
Furnish, install, and
Lump
maintain Type "D" inlet
Sum
1.00
1.00
$4,650.00
$4,650.00
245
protection std., complete
Lump
asspecified
Each
159
159.00
1.00
$90.00
$675.00
237
Furnish, install, and
maintain silt fence,
Linear
complete asspecified
Feet
278
1 278.00
$3.00
238
Furnish, install, and
maintain stone bags,
complete asspecified
Each
34
34.00
$5.00
239
Clear inch - diameter of
existing trees, complete as
inch
, specified
Diameter
225
225.00
1
1
$2.001
1
240
Grub inch - diameter of
existing stumps, complete
inch
asspecified I
Diameter
225
225.00
$2.00
SECTION II - (BID ITEMS 200 - 240) - SUB - TOTALS
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION II
$20,008.08 ($12,962.62)
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
#0002046 -IN
Sum
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
242
EXTRA PER INVOICE
Lump
PRICE
PRICE
241
EXTRA PER INVOICE
Lump
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
NUMBER
#0002046 -IN
Sum
QUANTITIES
1.00
1.00
DECREASE
$900.00
$900.00
CONTRACT
242
EXTRA PER INVOICE
Lump
PRICE
PRICE
#0002072 -IN
Sum
1.00
1.00
$550.00
$550.00
243
EXTRA PER INVOICE
Lump
#0002074 -IN
Sum
1.00
1.00
$300.00
$300.00
244
EXTRA PER INVOICE
Lump
#0002075 -IN
Sum
1.00
1.00
$4,650.00
$4,650.00
245
EXTRA PER INVOICE
Lump
#0002076 -IN
Sum
1.00
1.00
$675.00
$675.00
ADDITIONAL WORK: C.O. # 1 - (ITEMS 241 - 245) - SUB -TOTAL
NET INCREASE TO: SECTION II
SECTION III - SANITARY SEWER
$7,075.00 $0.00
$14,120.46
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
300 Furnish and install 8"
sanitary sewer (relay), Linear
complete ass ecified I Feet 3,115 3094.68 -20.32 1 $57.00 $1,158.24
Page 7 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
301
Furnish and install 8"
sanitary sewer drop,
Vertical
complete asspecified
Feet
15
15.83
0.83
$450.00
$373.50
302
Furnish and install 10"
sanitary sewer (relay),
Linear
complete asspecified
Feet
145
139.80
-5.20
$77.00
$400.40)
303
Furnish and install 10"
sanitary sewer drop,
Vertical
com fete asspecified
Feet
5
1 4.54
-0.46
$500.00
$230.00
304
Furnish and install 12"
sanitary sewer (relay),
Linear
complete asspecified
Feet
1,485
1529.40
44.40
$83.00
$3,685.20
305
Furnish and install 12"
sanitary sewer drop,
Vertical
complete asspecified
Feet
15
11.72
-3.28
$550.00
$1,804.00
306
Furnish and install 15"
sanitary sewer relay,
Vertical
complete asspecified
Feet
5
7.90
2.90
$130.00
$377.00
307
Furnish and install std.
sanitary manhole (4' inside
diameter) in various
locations, complete as
Vertical
specified, without casing
Feet
210
222.30
12.30
$185.00
$2,275.50
308
Furnish and install 8" x 4"
factory wyes or tees,
complete asspecified
Each
3
0.00
-3.00
$70.00
$210.00
309
Furnish and install 8" x 6"
factory wyes or tees,
complete asspecified
Each
79
62.00
-17.00
$90.00
$1,530.00
310
Furnish and install 10" x 6"
factory wyes or tees,
complete asspecified
Each
1
1.00
$150.00
311
Furnish and install 12" x 6"
factory wyes or tees,
complete asspecified
Each
4
23.00
19.00
$190.00
$3,610.00
312
Furnish and install new 4"
sanitary laterals, complete
Linear
asspecified
Feet
50
0.00
-50.00
$46.00
$2,300.00
313
Furnish and install 4 "/6"
sanitary lateral relay,
Linear
complete asspecified
Feet
1,630
1776.10
146.10 1
$46.00
$6,720.60
314
Furnish and install sanitary
lateral marker balls,
complete as specified
Each
174 1
169.00
-5.00
$18.00
($90.00
315
Furnish and install
connections of new
sanitary main to existing
main (various locations
and sizes), complete as
specified
Each
14
14.00 1
1
1
$300.001
1
316
Core into existing sanitary
manhole, complete as
specified
Each
1
1.00
$600.00
Page 8 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASEIN
CONTRACT
DECREASEIN
CONTRACT
NUMBER
DESCRIPTION
UNIT
I
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
I CONTRACT
CONTRACT
I
#0002077 -IN
Sum
1.00
1.00
$4,595.00
PRICE
PRICE
317
Abandon sanitary
Linear
manholes, complete as
Lump
20
43.00
23.00
$51.00
$1,173.00
specified
Each
21
21.00
1 1.00
$400.00
$2,680.00
318
Abandon 8" sanitary sewer
at various locations,
complete as specified
Linear
Feet
1,890
1890.00
$3.00
319
Abandon 10" sanitary
sewer at various locations
Linear
, complete asspecified
Feet
430
430.00
$3.00
320
Abandon 15" sanitary
sewer at various locations,
Linear
complete as specified
Feet
350
350.00
$12.00
321
Abandon 18" sanitary
sewer at various locations,
Linear
complete as specified
Feet
955
955.00
$15.00
322
Abandon 24" sanitary
sewer at various locations,
Linear
complete as specified
Feet
430
430.00
$17.00
SECTION III - (BID ITEMS 300 - 322) - SUB - TOTALS $17,041.80 ($7,722.64)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION III
ITEM
EXTRA PER INVOICE
#0002071 -IN
Lump
Sum
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASEIN
DECREASEIN
NUMBER
DESCRIPTION
UNIT
I
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
I CONTRACT
CONTRACT
I
#0002077 -IN
Sum
1.00
1.00
$4,595.00
PRICE
PRICE
323
EXTRA PER INVOICE
#0002071 -IN
Lump
Sum
CONTRACT
1.00
1.00
NET
$5,534.00
$5,534.00
DECREASEIN
324
EXTRA PER INVOICE
Lump
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
#0002077 -IN
Sum
1.00
1.00
$4,595.00
$4,595.00
PRICE
325
EXTRA - MOVE &
Linear
REPLACE SAN. MH BASE
Lump
20
43.00
23.00
$51.00
$1,173.00
Sum
1.00
1 1.00
$2,680.00 1
$2,680.00
ADDITIONAL WORK: C. O. # 1 - (ITEMS 323 - 325) - SUB -TOTAL $12,809.00 $0.00
NET INCREASE TO: SECTION III $22,128.16
SECTION IV - WATER MAIN
ITEM
Furnish and install 4"
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASEIN
DECREASEIN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
w /poly wrap, complete as
PRICE
PRICE
400.
Furnish and install 4"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
20
43.00
23.00
$51.00
$1,173.00
Page 9 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
401.
Furnish and install 6"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
455
390.00
-65.00
$52.00
$3,380.00)
402.
Furnish and install 8"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
3,300
3,201.00
-99.00
1 $52.00
($5,148.00
403.
Furnish and install 10"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
20
0.00
-20.00
$62.00
($1,240.00)
404.
Furnish and install 12"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
660
692.00
32.00
1
$68.00
$2,176.00
405.
Furnish and install 18"
ductile iron water main,
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
695
723.00
28.00
1 $106.00
$2,968.00
406.
Furnish and install 1" water
service relay, complete as
specified, not including
corporation and stop box
Linear
Feet
1,505
1,556.00
51.00
1
$42.00
$2,142.00
407.
Furnish and install new 1"
water service, complete as
specified, not including
Linear
corporation and stop box
Feet
110
0.00
- 110.00
$42.00
$4,620.00
408.
Furnish and install 1"
corporation and stop box
with rod, complete as
specified
Each
83
81.00
1
-2.00
$220.00
($440.00
409.
Furnish and install 8" x 6"
tees, complete as specified
Each
12
8.00
-4.00
$230.00
$920.00)
410.
Furnish and install 8" x 8"
tees, complete as specified
Each
8
8.00
1
$240.00
411.
Furnish and install 18" x 8"
tee, complete as specified
Each
2
1.00
-1.00
$1,200.00
$1,200.00)
412.
Furnish and install 6" x 6"
cut -in tee, complete as
specified
Each
2
0.00
-2.00
$1,500.00
($3,000.00
413.
Furnish and install 8" x 8"
cross, complete as
i s
ecified
Each
3
0.00
-3.00
$250.00
$750.00)
Page 10 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
414.
Furnish and install 12" X 8"
PRICE
PRICE
cross, complete as
specified
Each
1
1 3.00
2.00
$330.00
$660.00
415.
Furnish and install 6"
valves, complete as
specified
Each
14
16.00
2.00
$1,000.00
$2,000.00
416.
Furnish and install 6" cut -in
valve, complete as
specified
Each
2
0.00
-2.00
$1,100.00
$2,200.00
417.
Furnish and install 8"
valves, complete as
specified
Each
26
23.00
-3.00
$1,250.00
$3,750.00)
418.
Furnish and install 12"
valves, complete as
specified
Each
2
L 3.00
1.00
$2,500.00
$2,500.00
419.
Furnish and install 18"
valve, complete as
specified
Each
1
1.00
$9,800.00
420.
Furnish and install 6" x 6"
tapping valve and sleeve,
complete asspecified
Each
3
1 3.00
$2,100.00
421.
Furnish and install 12" x 8"
tapping valve and sleeve,
complete as specified
Each
1
1.00
$2,500.00
422.
Furnish and install 8" - 22
'/ degree bends, complete
ass ecified
Each 1
1
0.00
-1.00
$210.00
$210.00
423.
Furnish and install 4" - 45
degree bends, complete as
specified
Each
4
6.00
2.00
$150.00
$300.00
424.
Furnish and install 6" - 45
degree bends, complete as
specified
Each
34
42.00
8.00
$160.00
$1,280.00
425.
Furnish and install 8" - 45
degree bends, complete as
specified
Each
11
11.00
$210.00
426.
Furnish and install 12" - 45
degree bends, complete as
specified
Each
2
3.00
1.00
$350.00
$350.00
427.
Furnish and install 18" - 45
degree bends, complete as
specified
Each
4
4.00
$1,250.00
428.
Furnish and install 8" x 4"
reducer, complete as
specified
Each
2
3.00
1.00
$160.00
$160.00
429.
Furnish and install 8" x 6"
reducers, complete as
specified
Each
15
15.00
$170.00
430.
Relocate hydrant,
com fete asspecified
Each
2
0.00
-2.00
$700.00
$1,400.00
431.
Furnish and install
hydrants, complete as
specified
Each
14
14.00
$2,400.00
Page 11 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
432.
Furnish and install
gradeloks for hydrant
branches, complete as
s ecified
Each
6
1 0.00
-6.00
$350.00
$2,100.00
433.
Furnish and install
connections of new water
main to existing water main
(various sizes and
locations), complete as
specified
Each
30
1 23.00
-7.00
$1,000.00
$7,000.00
434.
Furnish and install 4" cap,
complete as specified
Each
1
0.00
-1.00
$900.00
$900.00
435.
Furnish and install 6" cap,
complete as specified
Each
1
0.00
-1.00
$900.00
$900.00
436.
Furnish and install 8" cap,
complete as specified
Each
1
0.00
-1.00
$900.00
($900.00)
437.
Cut and cap existing 12"
water main, complete as
s ecified
Each
1
0.00
-1.00
$1,100.00
$1,100.00
438.
Furnish and install 18" cap,
complete as specified
Each
1
1.00
$2,000.00
439.
Abandon water main on
Babbitz Avenue (Lane St.
to Sweet St.) complete as
Lump
, specified
Sum
1
1.00
$1,400.00
440.
Abandon water main on
Gehres Court (Broad St. to
a point east), complete as
Lump
specified
Sum
1
1.00
$1,000.00
441.
Abandon water main on
Grand Avenue (New York
Ave. to E. Nevada St.),
Lump
, complete asspecified
Sum
1
1.00
$2,000.00
442.
Abandon water main on
Lane Street (Rahr Ave. to
Babbitz Ave.), complete as
Lump
specified
Sum
1
1.00
1 $600.00
443.
Abandon water main on
Mt. Vernon Street (New
York Ave. to Custer Ave.),
Lump
complete as specified
Sum
1
1.00
$2,200.00
444.
Abandon water main on E.
Parkway Avenue (Bowen
St. to Hazel St.), complete
Lump
asspecified
Sum
1
1.00
$4,800.00
445.
Furnish and install 4"
sleeve, complete as
specified
Each
2
3.00
1.00
$110.00
$110.00
446.
Furnish and install 6"
sleeve, complete as
specified
Each 1
2 1
7.00
5.00 1
$140.001
$700.00
Page 12 of 13
CONTRACT: 09 -07 CHANGE ORDER # 1
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
447.
Furnish and install 8"
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
451
sleeve, complete as
Each
2.00
2.00
$750.00
PRICE
PRICE
452
, specified
Each
2
2.00
1.00
$180.00
$265.00
448.
Furnish and install 12"
Each
1 1.00
1.00
$1,225.00
$1,225.00
454
sleeve, complete as
Each
1.00
1.00
$475.00
$475.00
455
specified
Each
2
1.00
3.00
-1.00
$235.00
$825.00
($235.00
SECTION IV - (BID ITEMS 400 - 448) - SUB - TOTALS
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
$16,519.00 ($41,393.00)
ITEM
RECONNECT WATER
SERVICE
Each
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE 1N
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
451
ULO'S
Each
2.00
2.00
$750.00
PRICE
PRICE
449
RECONNECT WATER
SERVICE
Each
3.00
3.00
$825.00
$2,475.00
450
BOX & ROD ONLY
Each
13.00
13.00
$800.00
$10,400.00
451
ULO'S
Each
2.00
2.00
$750.00
$1,500.00
452
4" TEE
Each
1.00
1.00
$265.00
$265.00
453
18" SLEEVE
Each
1 1.00
1.00
$1,225.00
$1,225.00
454
12" X 6" ANCHORING TEE
Each
1.00
1.00
$475.00
$475.00
455
6" X 6" TEE
Each
3.00
3.00
$275.00
$825.00
456
12" X 18" TEE
Each
1.00
1.00
$2,485.00
$2,485.00
457
EXTRA PER INVOICE
#0002042 -IN
Lump
Sum
1.00
1.00
$1,560.00
$1,560.00
458
EXTRA PER INVOICE
#0002073 -IN
Lump
Sum
1.00
1.00
$1,280.00
$1,280.00
ADDITIONAL WORK: C.O.01 (ITEMS 449 - 458) - SUB -TOTAL $22,490.00 $0.00
NET DECREASE TO: SECTION IV
($2,384.00)
NET INCREASE TO SECTIONS I, II, III, IV $143,958.15
NET DECREASE TO SECTIONS I, II, III, IV ($189,029.50)
NET DECREASE TO CONTRACT: ($45,071.35)
Page 13 of 13