HomeMy WebLinkAbout10-186JUNE 8, 2010 10 -186 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT NO. 09 -04 FOR CARL BOWERS & SON
CONSTRUCTION CO. FOR CONCRETE PAVING — UTILITIES /
SOUTH SIDE ( +$28,492.10)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
CARL BOWERS & SONS CONSTRUCTION CO.
N1844 Maloney Rd.
Kaukauna, WI 54130
Net Increase to contract: $28,492.10
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 315 - 0410 - 7480 -00000 Street Improvement Fund Expenditures
Acct. No. 317 - 0410 - 7480 -03301 Special Assessments Fund - Streets
Acct. No. 317 - 0410 - 7480 -03302 Special Assessments Fund - Sewer
Acct. No. 317 - 0410 - 7480 -03303 Special Assessments Fund - Water
Acct. No. 317 - 0410 - 7480 -03305 Special Assessments Fund - Storm Water
Acct. No. 541 - 1810 - 1799 -00000 Water Utility Construction Work in Progress
Acct. No. 551 - 1910 - 1799 -00000 Sewer Utility Construction Work in Progress
Acct. No. 561 - 2010 - 1799 -00000 Storm Water Utility Constr. Work in Progress
( 0
O HKO H
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: June 2, 2010
RE: Change Order #2 for Public Works Contract No. 09 -04; for Carl Bowers & Sons
Construction Co. for Concrete Paving — Utilities /South Side ( +$28,492.10)
BACKGROUND
Change Order #2 for Contract 09 -04 is scheduled for consideration by the Common Council at the June
8, 2010 meeting. The contract was originally awarded to Carl Bowers & Sons Construction Co. Inc. in
April of 2009. This change order balances all items to the actual installed quantities and adds additional
work needed to complete the project.
ANALYSIS
Following is a summary of the significant additional work items performed for each section of the CIP.
- Sanitary Sewer included additional labor and materials to adjust existing and new utilities to
avoid conflicts.
-Water Main included additional parts and fittings to adjust mains to avoid conflicts with other
utilities and adjust to existing underground conditions.
FISCAL IMPACT
Contract Section
Change Order Amount
CIP Budget Amount
New Contract Total
Concrete Paving
- $7,018.87
$1,634,500
$1,371,639.38
Storm Sewer
- $7,501.26
$1,320,000
$771,165.64
Sanitary Sewer
$8,870.63
$975,000
$603,061.45
Water Main
$34,141.60
$1,095,000
$642,785.60
Total
$28,492.10
$5,024,500
$3,388,652.07
Adequate funds are available in the relating sections of the 2009 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of the Change Order #2 to Contact No. 09 -04 in the amount of $28,492.10 to Carl
Bowers & Sons Construction Co. Inc.
Respectfully Submitted,
Approved:
Steven M. Gohde
Asst. Director of Public Works City Manager
I: \Engineering \09 -04 Concrete Paving - South Side\ Project_ Information \Correspondence\Memo \CO #2 exp.doc
CHANGE ORDER # 2
DATED: May 27, 2010
TO: Carl Bowers & Sons Construction Co.
N1844 Maloney Rd
Kaukauna, WI 54130
Your present contract with the City of Oshkosh, Contract No. 09 -04 is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING ($7,018.87)
NET DECREASE TO: SECTION II - STORM SEWER ($7,501.26)
NET INCREASE TO: SECTION III - SANITARY SEWER $8,870.63
NET INCREASE TO: SECTION IV- WATER MAIN $34,141.60
NET INCREASE TO CONTRACT: $28,492.10
CITY OF OSHKOSH
M
Recommended:
Director of Public Works
City Manager
City Clerk
Approved and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 09 -04 CHANGE ORDER # 2
SECTION I - CONCRETE PAVING
ITEM
DESCRIPTION
UNIT
CONTRACT
I INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE 1N
NUMBER
complete as specified
Yards
QUANTITIES
QUANTITIES
I INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
I
101.
Sidewalk and driveway
PRICE
PRICE
100.
Pavement removal,
Square
complete as specified
Yards
17,585
17425.80
- 159.20
$1.80
($286.56
101.
Sidewalk and driveway
removal, complete as
Square
specified
Feet
34,200
33301.50
- 898.50
$0.45
$404.33
102.
Excavation, complete as
Cubic
. specified
Yards
1 12,025
12854.10
829.10
$4.95
$4,104.05
103.
7" non - reinforced concrete
pavement, including
integral curb, 5" base
material and grading,
Square
complete as specified
Yards
29,305
27802.10
- 1,502.90
$28.94
$43,493.93
104.
8" non - reinforced H.E.S.
concrete pavement,
including integral curb, 6"
base material and grading,
Square
complete as specified
Yards
2,100
2149.70
49.70
$41.62
$2,068.51
105.
12" wide radius curb head,
Linear
complete as specified
Feet
1,630
1637.20
7.20
$5.50
$39.60
106.
Standard 30" curb & gutter,
7" (tie -in), complete as
Linear
specified
Feet
25
30.40
5.40
$24.00
$129.60
107.
Sidewalk curb, complete as
Linear
specified
Feet
200
0.00
- 200.00
$16.00
($3,200.00
108.
4" concrete sidewalk,
Square
complete asspecified
Feet
12,215
14337.00
2,122.00
$2.97
$6,302.34
109.
6" concrete sidewalk &
driveway, complete as
Square
specified
Feet
31,005
27716.20
- 3,288.80
$3.25
$10,688.60
110.
3 %" asphaltic concrete
transition, with base,
Square
complete ass ecified
Yards
640
842.50
202.50
$28.10
$5,690.25
111.
Furnish and install crushed
stone base course,
complete as specified
Tons
4,590
2803.40
- 1,786.60
$7.80
$13,935.48)
112.
Profile sawing, complete as
Linear
specified
Feet
10
8.80
-1.20
$40.00
$48.00)
113.
Sawing, complete as
Linear
specified
Feet
3,750
3875.80
125.80
$1.50
$188.70
114.
Furnish and install
pavement ties (epoxy
coated), complete as
specified
Each
1,270
1399.00
129.00
$6.00
$774.00
115.
Adjust manholes and inlets,
complete as specified
Each
169
169.00
$240.00
116.
Furnish and install No. 4
reinforcing bars (epoxy
coated), complete as
Linear
specified
Feet
120
120.00
$1.00
117.
Remove trees and stumps,
complete as specified
Inch
Diameter
2
4.00
2.00
$12.00
$24.00
Page 1 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
p avement w /base
Yard
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
118.
Remove stumps, complete
Square
1,703
1754.70
51.70
$37.00
PRICE
PRICE
201.
as specified
Inch
HES )
Diameter
15
12.00
101.50
-3.00
$10.00
$4,518.78
$30.00
119.
Furnish and install trees,
Linear
corn lete as s ecified
Each
1
0.00
-1.00
$250.00
$250.00
120.
Provide and install metal
detectable warning plates,
Square
complete as specified
Feet
816
736.00
-80.00
$28.00
($2,240.00
121.
Terrace work on Adams
Avenue, complete as
Lump
specified
Sum
1
1.00
$9,135.00
122.
Terrace work on Dove
Street, complete as
Lump
specified
Sum
1
1.00
$6,875.00
123.
Terrace work on N. Eagle
Street, complete as
Lump
specified
Sum
1
1.00
$5,850.00
124.
Terrace work on Hawk
Street, complete as
Lump
specified
Sum
1
1.00
$11,125.00
125.
Terrace work on Sullivan
Street, complete as
Lump
specified
Sum
1
1.00
$2,425.00
126.
Terrace work on W. 11th
Avenue, complete as
Lump
specified
Sum
1
1.00
$20,000.00
SECTION I - (BID ITEMS 100 - 126) - SUB - TOTALS $19,321.05 ($74,576.90)
ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION I
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE !N
DECREASE IN
NUMBER
p avement w /base
Yard
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
128
Extra work - 8" concrete
Square
1,703
1754.70
51.70
$37.00
PRICE
PRICE
127
Extra work - 8" concrete
Square
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
p avement w /base
Yard
QUANTITIES
1,162.10
1,162.10
DECREASE
$37.62
$43,718.20
CONTRACT
128
Extra work - 8" concrete
Square
1,703
1754.70
51.70
$37.00
PRICE
PRICE
201.
pavement w /base (9 bag
Yard
HES )
101.50
101.50
$44.52
$4,518.78
ADDITIONAL WORK: C.O. # 2 -(ITEMS 127 -128) -SUB-TOTAL $48,236.98 $0.00
NET DECREASE TO: SECTION 1 ($7,018.87)
SECTION II - STORM SEWER
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
storm sewer, complete as
Linear
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
specified
Feet
1,703
1754.70
51.70
$37.00
PRICE
PRICE
200.
Furnish and install 12"
storm sewer, complete as
Linear
specified
Feet
1,703
1754.70
51.70
$37.00
$1,912.90
201.
Furnish and install 12" RCP
Class III storm sewer,
complete as specified
Linear
Feet
117
112.54
-4.46
$41.00
$182.86
Page 2 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
202.
Furnish and install 15"
storm sewer, complete as
Linear
specified
Feet
2,445
2438.30
-6.70
$39.00
($261.30
203.
Furnish and install 18"
storm sewer, complete as
Linear
specified
Feet
669
670.80
1.80
$42.00
$75.60
204.
Furnish and install 21"
storm sewer, complete as
Linear
specified
Feet
1,273
909.28
- 363.72
$47.00
$17,094.84
205.
Furnish and install 24"
storm sewer, complete as
Linear
specified
Feet
1,846
1904.87
58.87
$50.00
$2,943.50
206.
Furnish and install 19" x
30" RCP CL III storm
sewer, complete as
Linear
. specified
Feet
73
77.15
4.15
$75.00
$311.25
207.
Furnish and install 30"
storm sewer, complete as
Linear
specified
Feet
57
51.65
-5.35
$65.00
($347.75)
208.
Furnish and install 30" RCP
Class III storm sewer,
complete as specified
Linear
Feet
62
62.00
$65.00
209.
Furnish and install 30"
storm sewer with clay
bedding and backfill and
joint ties, complete as
Linear
s ecified
Feet
75
75.00
$65.00
210.
Furnish and install 24" x
38" RCP Class III storm
sewer, complete as
Linear
specified
Feet
479
464.24
-14.76
$86.00
$1,269.36)
211.
Furnish and install 29" x
45" RCP Class III storm
sewer, complete as
Linear
. specified
Feet
363
366.45
3.45
$90.00
$310.50
212.
Furnish and install 29" x
45" RCP Class III storm
sewer with clay bedding
and backfill and joint ties,
Linear
complete asspecified
Feet
45
45.00
$90.00
213.
Furnish and install 29" x
45" RCP Class III apron
endwall with joint ties,
complete asspecified
Each
1
1.00
$1,400.00
214.
Furnish and install std.
inlets (Type 3 with 18"
sump) with castings,
complete asspecified
Each
79
81.00
2.00
$1,100.00
$2,200.00
215.
Furnish and install std.
storm manhole (4' inside
diameter) in 37 locations
without casting, complete
Vertical
asspecified
Feet
146.91
143.45
-3.46
$215.00
$743.90)
Page 3 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
216.
Furnish and install std.
PRICE
PRICE
storm manhole (5' inside
diameter) in 6 locations
without casting, complete
Vertical
asspecified
Feet
20.07
25.47
5.40
$375.00
$2,025.00
217.
Furnish and install std.
storm manhole (6' inside
diameter) in 3 locations
without casting, complete
Vertical
ass ecified
Feet
13.38
15.29
1.91
$500.00
$955.00
218.
Furnish and install 6" storm
lateral, complete as
Linear
specified
Feet
4,670
4735.00
65.00
$27.00
$1,755.00
219.
Furnish and install storm
lateral marker balls,
complete asspecified
Each
308
302.00
-6.00
$15.00
($90.00)
220.
Abandon 8" - 12" storm
sewer, complete as
Linear
specified
Feet
1,634
1634.00
$10.00
221.
Abandon lineal feet of 15"
and larger storm sewer,
Linear
complete asspecified
Feet
2,918
2918.00
$10.00
222.
Abandon inlets or
manholes, complete as
s ecified
Each
55
55.00
$250.00
223.
Furnish, install, and
maintain Type "D" inlet
protection std., complete
asspecified
Each
167
167.00
$90.00
224.
Furnish, install, and
maintain silt fence,
Linear
complete asspecified
Feet
88
88.00
$3.00
225.
Utility line opening,
complete ass ecified
Each 1
2 1
2.00
$300.00
SECTION II - (BID ITEMS 200 - 225) - SUB - TOTALS
NO ADDITIONAL WORK REQUIRED: SECTION If
NET DECREASE TO: SECTION II
SECTION III - SANITARY SEWER
$12,488.75 ($19,990.01)
($7,501.26)
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
PRICE
PRICE
300. Furnish and install 8"
sanitary sewer (relay /new),
complete as specified Linear
Feet
301. Furnish and install 8"
sanitary sewer drop, Vertical
complete as specified Feet
335 1 4318.26
25 1 25.311 0.31
-16.74
7.
$450.001 $139.50
Page 4 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
302.
Furnish and install 10"
sanitary sewer (relay /new),
complete as specified
Linear
Feet
1 25
17.29
-7.71
$60.00
($462.60)
303.
-
ELIMINATED
Ve#isal
Feet
304.
Furnish and install 12"
sanitary sewer (relay /new),
complete as specified
Linear
Feet
1,280
1276.54
-3.46
$57.00
($197.22
305.
Furnish and install std.
sanitary manhole (4' inside
diameter) in various
locations, complete as
specified, without casing
Vertical
Feet
215
194.01
-20.99
$185.00
($3,883.15
306.
Furnish and install 6" insert -
a-tees, complete as
specified
Each
6
5.00
-1.00
$170.00
($170.00
307.
Furnish and install 8" x 4"
factory wyes or tees,
complete asspecified
Each
5
3.00
1 -2.00
$70.00
($140.00
308.
Furnish and install 8" x 6"
factory wyes or tees,
complete asspecified
Each
101
96.00
-5.00
$90.00
($450.00)
309.
Furnish and install 10" x 6"
factory wyes or tees,
complete asspecified
Each
4
0.00
-4.00
$150.00
$600.00)
310.
Furnish and install 12" x 4"
factory wyes or tees,
complete asspecified
Each
1
0.00
-1.00
$180.00
$180.00
311.
Furnish and install 12" x 6"
factory wyes or tees,
complete asspecified
Each
38
40.00
2.00
$190.00
$380.00
312.
Furnish and install new 4"
sanitary laterals, complete
Linear
asspecified
Feet
150
89.00
-61.00
$43.00
$2,623.00
313.
Furnish and install 4 " /6"
sanitary lateral relay,
Linear
complete asspecified
Feet
3,640
3664.50
24.50
$43.00
$1,053.50
314.
Furnish and install sanitary
lateral marker balls,
complete as specified
Each
302
291.00
-11.00
$15.00
$165.00
315.
Furnish and install
connections of new
sanitary main to existing
main (various locations and
sizes), complete as
specified
Each
10
11.00
1.00
$300.00
$300.00
316.
Abandon sanitary
manholes, complete as
specified
Each
15
15.00
$400.00
Page 5 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
Sum
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
325
Extra - Invoice @2033
Lump
PRICE
PRICE
317.
Abandon 8' sanitary sewer
Sum
1.00
1.00
$4,187.50
$4,187.50
326
on Adams Avenue and W.
Lump
11th Avenue, complete as
Linear
1.00
1.00
$1,050.00
$1,050.00
327
specified
Feet
690
690.00
$3.00
318.
Abandon 12' sanitary
Sum
1.00
1.00
$1,260.00
$1,260.00
328
sewer on Dove Street and
Lump
W. 11th Avenue, complete
Linear
1.00
1.00
$6,973.32
$6,973.32
asspecified
Feet
505
505.00
$3.00
319.
Abandon 18' sanitary
sewer on W. 11th Avenue,
complete as specified
Linear
Feet
1,220
1220.00
$15.00
320.
Furnish and install
excavation and C.A.B.C.
backfilling for tunnel
crossing at N. Eagle Street
and Adams Avenue,
complete as specified
Lump
Sum
1
1.00
$1,450.00
321.
Furnish and install
excavation and C.A.B.C.
backfilling for tunnel
crossing at Hawk Street
and Adams Avenue,
Lump
complete asspecified
Sum
1
1.00
$1,450.00
322.
Furnish and install
excavation and C.A.B.C.
backfilling for tunnel
crossing at Dove Street
and Adams Avenue,
Lump
complete ass ecified
Sum
1
1.00
$1,450.00
Furnish and install blown
: 1specified
sand backfill to fill tunnel
sections, complete as
Cubic
Yards
50
50.00
$20.00
SECTION III - (BID ITEMS 300 - 323 ) - SUB - TOTALS $1,873.00 ($9,768.19)
ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION III
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
NUMBER
Sum
QUANTITIES
QUANTITIES
IN
DECREASE
UNIT
CONTRACT
CONTRACT
325
Extra - Invoice @2033
Lump
PRICE
PRICE
324
Extra - Invoice @2031
Lump
Sum
1.00
1.00
$3,285.00
$3,285.00
325
Extra - Invoice @2033
Lump
Sum
1.00
1.00
$4,187.50
$4,187.50
326
Extra - Invoice @2035
Lump
Sum
1.00
1.00
$1,050.00
$1,050.00
327
Extra - Invoice @2036
Lump
Sum
1.00
1.00
$1,260.00
$1,260.00
328
Extra - Invoice @2045
Lump
Sum
1.00
1.00
$6,973.32
$6,973.32
ADDITIONAL WORK: C. O. # 2 - (ITEMS 324 - 328) - SUB -TOTAL $16,755.82 $0.00
NET INCREASE TO: SECTION III $8,870.63
Page 6 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
ductile iron water main
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
w /poly wrap, complete as
PRICE
PRICE
SECTION IV - WATER MAIN
ITEM
DESCRIPTION
UNIT
CONTRACT
F Q NSTALLED
NET
NET
COST PER
INCRE
DECREASE IN
NUMBER
ductile iron water main
QUANTITIES
UAN TITIES
IN
DECREASE
UNIT
CONTRAASE CIN
T
CONTRACT
w /poly wrap, complete as
PRICE
PRICE
400.
Furnish and install 6"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
590
458.00
- 132.00
$43.00
($5,676.00
401.
Furnish and install 8"
ductile iron water main
w /poly wrap, complete as
specified (fittings not
Linear
included )
Feet
1 5,400
5417.00
17.00
$47.00
$799.00
402.
Furnish and install 1" water
service relay, complete as
specified, not including
corporation and stop box
Linear
Feet
3,245
3355.10
110.10
$36.00
$3,963.60
403.
Furnish and install new 1"
water service, complete as
specified, not including
corporation and stop box
Linear
Feet
155
0.00
- 155.00
$36.00
($5,580.00
404.
Furnish and install 1 '/"
water service relay,
complete as specified, not
including corporation and
Linear
stop box
Feet
16
16.50
0.50
$50.00
$25.00
405.
Furnish and install 1"
corporation and stop box
with rod, complete as
specified
Each
132
144.00
12.00
$200.00
$2,400.00
406.
Furnish and install 1 '/"
corporation and stop box
with rod, complete as
. specified
Each
1
1.00
$500.00
407.
Furnish and install 6" x 6"
cut -in tee, complete as
specified
Each
1
0.00
-1.00
$525.00
$525.00
408.
Furnish and install 8" x 6"
tees, complete as specified
Each
16
13.00
-3.00
$240.00
($720.00)
409.
Furnish and install 8" x 8"
tees, complete as specified
Each
2
2.00
$230.00
410.
Furnish and install 8" x 8"
cross, complete as
specified
Each
3
3.00
$300.00
411.
Furnish and install 6" cut -in
valve, complete as
specified
Each
1
0.00
-1.00
$1,100.00
($1,100.00
412.
Furnish and install 6"
valves, complete as
specified
Each
14
17.00
3.00
$1,000.00
$3,000.00
Page 7 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
QUANTITIES QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
413.
Furnish and install 8"
PRICE
PRICE
valves, complete as
specified
Each
21 28.00
7.00
$1,250.00
$8,750.00
414.
Furnish and install 6" x 6"
tapping valve and sleeve,
complete asspecified
Each
4 3.00
-1.00
$1,650.00
$1,650.00
415.
Furnish and install 8" x 8"
tapping valve and sleeve,
complete asspecified
Each
1 0.00
-1.00
$2,000.00
($2,000.00
415 A.
Furnish and install 10" x 6"
tapping valve and sleeves,
complete as specified
416.
Furnish and install 10" x 8"
Each
2 4.00
2.00
$1,700.00
$3,400.00
tapping valve and sleeve,
complete as specified
41 7.
Furnish and install 12" x 6"
Each
4 0.00
4.00
$2,000.00
($8,000.00)
tapping valve and sleeve,
complete as specified
Each
2 3.00
1.00
$1,750.00
$1,750.00
41 8.
tapp va
and s
ELIMINATED
€ash
419.
Furnish and install 6" - 45
1
degree bends, complete as
specified
Each
12
40.001
28.00
$160.00
$4,480.00
420.
Furnish and install 8" - 45
degree bends, complete as
specified
Each
22
21.00
-1.00
$210.00
$210.00)
421.
Furnish and install 6"
sleeve, complete as
specified
Each
2
12.00
10.00
$140.00
$1,400.00
422.
Furnish and install 6" x 8"
enlarger, complete as
specified
Each
2
1.00
-1.00
$150.00
($150.00
423.
Furnish and install 8" x 6"
reducers, complete as
--
specified
Each
10
13.00
3.00
$150.00
$450.00
424.
Relocate hydrant, complete
asspecified
Each
1
0.00
-1.00
$600.00
$600.00)
425.
Furnish and install
hydrants, complete as
specified
Each
17
17.00
$2,400.00
426.
Furnish and install
gradeloks for hydrant
branches, complete as
specified
Each
18
0.00
-18.00
$350.00
($6,300.00
427.
Cut and cap existing tee,
complete asspecified
Each 1
3
1.00
-2.00
$800.00
$1,600.00)
428.
Furnish and install
connections
of new water
main to existing water main
(various
sizes and
locations),
complete as
specified
Each
11
17.00
6.00 1
1
$800-001
$4,800.00
Page 8 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
429.
Abandon water main on
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
Adams Avenue (Eagle St.
Each
3.00
3.00
$275.00
PRICE
PRICE
441
to N. Sawyer St.) complete
Lump
1.00
1.00
$325.00
$325.00
442
ass ecified
Sum
1 1
1.00
1.00
$800.00
$300.00
430.
Abandon water main on
Each
1.00
1.00
$350.00
$350.00
444
Dove Street (Taft Ave. to
Each
8.001
8.00
$300.00
$2,400.00
445
Coolidge Ave.), including
Each
8.00
8.00
$300.00
$2,400.00
446
crossing streets, complete
Lump
2.00
2.00
$225.00
$450.00
447
ass ecified
Sum
1
1.00
4.00
$1,300.00
$1,200.00
431.
Abandon water main on N.
Each
2.00
2.00
1
$2,200.00 1
$4,400.00
Eagle Street (Taft Ave. to
Adams St.), complete as
Lump
specified
Sum
1
1.00
$1,000.00
432.
Abandon water main on W.
11th Avenue (Ohio St. to
Knapp St.), complete as
Lump
specified
Sum
1
1.00
$3,000.00
433.
Abandon water main on
Hawk Street (Southland
Ave. to Taft Ave.),
Lump
complete asspecified
Sum
1
1.00
$1,400.00
434.
Abandon water main on
Sullivan Street (Southland
Ave. to Lombard St.),
Lump
complete asspecified
Sum
1
1.00
$700.00
435.
Furnish and install 12" x 8"
tapping valve and sleeve,
complete as specified
Each
1
2.00
1.00
$2,100.00
$2,100.00
436.
Furnish and install 12" cut -
in valve, complete as
specified
Each
1
0.00
-1.00
$2,600.00
($2,600.00
437.
Furnish and install 8" x 12"
enlarger, complete as
specified
Each
1
0.00
-1.00
$200.00
$200.00
438.
Abandon water valve
manhole, complete as
s ecified
Each
1
0.00
-1.00
$500.00
$500.00)
SECTION IV - (BID ITEMS 400 - 438) - SUB - TOTALS $37,317.60 ($37,411.00)
ADDITIONAL WORK REQUIRED: C.O. # 2 - SECTION IV
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
8" 22 1/2 DEGREE BEND
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
Each
3.00
3.00
$275.00
PRICE
PRICE
439
8" SOLID SLEEVE
Each
4.00
4.00
$275.00
$1,100.00
440
8" 22 1/2 DEGREE BEND
Each
3.00
3.00
$275.00
$825.00
441
6" x 6" LOCKING TEE
Each
1.00
1.00
$325.00
$325.00
442
6" X 12" SSI SLEEVE
Each
1.00
1.00
$300.00
$300.00
443
8" X 12" SSI SLEEVE
Each
1.00
1.00
$350.00
$350.00
444
10" X 8" TEE
Each
8.001
8.00
$300.00
$2,400.00
445
10" SOLID SLEEVE
Each
8.00
8.00
$300.00
$2,400.00
446
6" SOLID SLEEVE
Each
2.00
2.00
$225.00
$450.00
447
10" 45 DEGREE BEND
Each
4.00
4.00
$300.00
$1,200.00
448
10" VALVE
Each
2.00
2.00
1
$2,200.00 1
$4,400.00
Page 9 of 10
CONTRACT: 09 -04 CHANGE ORDER # 2
1
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COST PER
UNIT
INCREASE IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
449
10 "X10 "X6" TEE
Each
1.00
1.00
$475.00
$475.00
450
10" D.I. WATERMAIN
Each
81.00
81.00
$80.00
$6,480.00
451
EXTRA - INVOICE #2034
LS
1.00
1.00
$2,010.00
$2,010.00
452
EXTRA - INVOICE #2037
LS
1.00
1.00
$955.00
$955.00
453
EXTRA - INVOICE #2038
LS
1.00
1.00
$930.00
$930.00
454
EXTRA - INVOCIE #2039
LS
1.00
1.00
$3,975.00
$3,975.00
455
EXTRA - INVOICE #2040
LS
1.00
1.00
$670.00
$670.00
456
EXTRA - INVOICE #2041
LS
1.00
1.00
$4,990.00
$4,990.00
ADDITIONAL WORK: C.O. # 2 (ITEMS 439 - 456) - SUB -TOTAL $34,235.00 $0.00
NET INCREASE TO: SECTION IV $34,141.60
NET INCREASE TO SECTIONS I, II, III, IV $170,228.20
NET DECREASE TO SECTIONS I, II, III, IV ($141,736.10)
NET INCREASE TO CONTRACT: $28,492.10
Page 10 of 10