HomeMy WebLinkAbout10-39FEBRUARY 9, 2010 10 -39 RESOLUTION
(CARRIED 4 -2 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC
WORKS CONTRACT NO. 09 -28 WITH PTS CONTRACTORS,
INC., FOR JACKSON STREET & MURDOCK AVENUE
ROUNDABOUT UTILITY RELOCATION (- $24,927.88)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that
the following Change Order, a copy of which is attached, is hereby approved:
PTS CONTRACTORS, INC.
4075 Eaton Rd
Green Bay, WI 54311 -9340
Net decrease to contract: (- $24,927.88)
PURPOSE: See attached Change Order.
( 0
OHKOH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: February 4, 2010
RE: Change Order #1 for Public Works Contract No. 09 -281 PTS Contractors Inc. /
Jackson St. and Murdock Ave. Roundabout Utility Relocations (- $24,927.88)
BACKGROUND
Change Order #1 for Contract 09 -28 is scheduled for consideration by the Common Council at the
February 9, 2010 meeting. The contract was originally awarded to PTS Contractor Inc. of Green Bay in
November of 2009. This change order is to finalize quantities.
ANALYSIS
The work under this contract is complete and final quantities have been measured. All sections of the
contract are reduced. The significant changes to the paving section are additional costs to haul
contaminated soils to a landfill and reduced pavement removal and replacement. Sanitary sewer laterals
and water lateral quantities were reduced to limit impacts to traffic. These laterals will be replaced when
the intersection is closed during the roundabout construction.
FISCAL IMPACT
All sections of the contract were reduced. The total reduction is $24,927.88. The paving section was
reduced by $2,601.90, storm sewer by $952.00, sanitary sewer by $15,653.34 and water main by
$5,720.64.
RECOMMENDATIONS
I recommend approval of the Change Order # 1 to Contact No. 09 -28 in the amount of - $24,927.88 to
PTS Contractors Inc.
Respectfully Submitted,
Z�� P��
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
1:\Engineering \09 -28 Jackson & Murdock Utility Relocation\ Project_ Inform ationTorrespondenceWemoTO 4 1 exp.doc
CHANGE ORDER # 1
DATED: January 22, 2010
TO: PTS CONTRACTORS, INC.
4075 EATON RD
GREEN BAY, WI 54311 -9340
Your present contract with the City of Oshkosh, Contract No. 09 -28 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING
NET DECREASE TO: SECTION II - STORM SEWER
NET DECREASE TO: SECTION III - SANITARY SEWER
NET DECREASE TO: SECTION IV - WATER MAIN
($2,601.90)
($952.00)
($15,653.34)
($5,720.64)
NET DECREASE TO CONTRACT:
($24,927.88)
CITY OF OSHKOSH
Recommended:
BY:
City Manager
Director of Public Works
City Clerk
Approved and accepted:
- 4 )- 1 AIA-- ( , LAI
Contractor
certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 09 - 28 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
112 Excavation and disposal of
contaminated soil
encountered on ro'ect Ton 0.00 517.02 517.02 $37.15 $19,207.29
ADDITIONAL WORK: C.O.81 - (ITEM 112) - SUB -TOTAL $19,207.29 $0.00
NET DECREASE TO: SECTION 1 ($2,601.90)
Page 1 of 6
INCREASE IN
DECREASE IN
CONTRACT
INSTALLE
COSTPER
UNIT
CONTRACT
CONTRACT
ITEM
DESCRIPTION
UNIT
QUANTITIES
QUANTIT
PRICE
PRICE
NUMBER
100 Pavement removal,
Square
Yards
3450
1840.93
- 1,609.07
$0.26
$418.36
com late ass ecified
101 Sidewalk and driveway
removal, complete as
Square
1000
200.00
-800
$0.16
$128.00
s cified
Feet
102
Excavation, complete as
Lump
1.00
$2,100.00
s ecified
Sum
1
103
Furnish and install
temporary pavement and
driveways, complete as
Square
4150
1840.83
- 2,309.17
$10.64
$24,569.57
s ecified
Yards
104
Sawing, complete as
Linear
Feet
500
3931.61 3,431.61
$1.70
$5,833.74
s ecified
105
Adjust manholes and inlets,
complete as specified
7.00
-13.00
$132.00
$1,716.00
Each
20
106
Terrace work on West
Murdock Avenue, complete
Lump
0.00
- 1.00
$660.00
$660.00
ass specified
Sum
1
107
Terrace work on Jackson
Street, complete as
Lump
1
0.00
-1.00
$150.00
$150.00
s ecified
Sum
108
Eliminated
teml;Gklpji; t
from
s
2809
__.__
Contract
Eliminated
109
1 RAt.
from
senErete- pavemePt-
squafe-
Contract
110
Furnish and install traffic
control, complete as
Lump
$13,000.00
Sum
1
1.00
specified
111
Furnish and install traffic
delineator replacement,
100
0.00
- 100.00
$0.01
$1.00
complete asspecified
Each
SECTION I
-(BID ITEMS 100 -111) - SUB - TOTALS
$5,833.74
($27,642.93)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
INCREASE IN DECREASE IN
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTRACT
NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
112 Excavation and disposal of
contaminated soil
encountered on ro'ect Ton 0.00 517.02 517.02 $37.15 $19,207.29
ADDITIONAL WORK: C.O.81 - (ITEM 112) - SUB -TOTAL $19,207.29 $0.00
NET DECREASE TO: SECTION 1 ($2,601.90)
Page 1 of 6
CONTRACT: 09 - 28 CHANGE ORDER # 1
ITEM DESCRIPTION
NUMBER
SECTION II - STORM SEWER
ITEM DESCRIPTION
NUMBER
INCREASEIN DECREASEIN
CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTRACT
UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
=COSTPER CREASEIN DECREASEIN
UNIT CONTRACT INSTALLED NET NET ONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE PRICE PRICE
$0.00 ($952.00)
($952.00)
200
Fumish and install
sanitary sewer relay,
reconnecting of existing
com lete asspecified
Feet
storm sewer or inlet leads,
Furnish and install 15"
complete as specified
Each
10
201
Furnish, install, and
302
Furnish and install 24'
maintain Type "D' inlet
sanitary sewer relay,
Linear
protection, complete as
Feet
303
Furnish and install std.
s ecified
Each
10
SECTION II - (BID ITEMS 201 .202) - SUB - TOTALS
NET DECREASE TO: SECTION II
SECTION III - SANITARY SEWER
ITEM DESCRIPTION
NUMBER
INCREASEIN DECREASEIN
UNIT CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
300
Furnish and install 10"
sanitary sewer relay,
Linear
com lete asspecified
Feet
301
Furnish and install 15"
sanitary sewer relay,
Linear
complete ass ecified
Feet
302
Furnish and install 24'
sanitary sewer relay,
Linear
complete asspecified
Feet
303
Furnish and install std.
sanitary manhole (4' inside
diameter) in various
locations, complete as
Vertical
specified
Feet
304
Furnish and install 15" x 6"
factory wyes, complete as
s ecified
Each
305
Furnish and install 4 "/6"
sanitary lateral relay,
Linear
complete ass specified
Feet
306
Furnish and install sanitary
lateral marker balls,
complete as specified
Each
307
Furnish and install
connections of new
sanitary main to existing
main (various locations and
sizes), complete as
.specified
Each
Page 2 of 6
CONTRACT: 09 - 28 CHANGE ORDER # 1
SECTION IV - WATER MAIN
ITEM CONTRACT INSTALLED
DESCRIPTION UNIT QUANTITIES QUANTITIES
NUMBER
400 Furnish and install 4"
INCREASE IN
NET NET COSTPER CONTRACT
INCREASE DECREASE UNIT PRICE
DECREASE IN
CONTRACT
PRICE
INCREASE IN DECREASE IN
ductile iron water main
CONTRACT
INSTALLED
NET NET
COST PER
UNIT
CONTRACT
CONTRACT
ITEM
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE DECREASE
-36.00
PRICE
PRICE
NUMBER
included ) Feet 45
401 Furnish and install 6"
308
Furnish and install concrete
ductile iron water main
collars, complete as
1
200
1 00
$530.00
$530.00
-37.00
s ecified
Each
$2,220.00
included Feet
309
Remove or abandon
ductile iron water main
existing sanitary manholes,
w /poly wrap, complete as
complete as specified
2.00
7
6.00
-1.00
$340.00
included Feet
$
Each
403 Furnish and install 10"
310
Abandon 8" sanitary sewer
w /poly wrap, complete as
at various locations,
specified (fittings not Linear
1700 1668.00
-32.00
$70.60
$2,259.20
complete as specified
Linear
55.00
$5.30
Feet
55
311
Abandon 10" sanitary
sewer at various locations,
complete as specified
Linear
35.00
$5.30
Feet
35
312
Abandon 15" sanitary
sewer at various locations,
complete as specified
Linear
20.00
$17.00
Feet
20
313
Abandon 24" sanitary
sewer at various locations,
complete as specified
Linear
670
670.00
$7.50
Feet
314
Fumish and install
reconnections of sanitary
laterals, complete as
7
8.00
1.00
$238.00
$238.00
s cified
Each
SECTION
III - (BID ITEMS 300 - 314) - SUB - TOTALS
$1,229.80
($16,883.14)
NET DECREASE TO:
SECTION III
($15,653.34)
SECTION IV - WATER MAIN
ITEM CONTRACT INSTALLED
DESCRIPTION UNIT QUANTITIES QUANTITIES
NUMBER
400 Furnish and install 4"
INCREASE IN
NET NET COSTPER CONTRACT
INCREASE DECREASE UNIT PRICE
DECREASE IN
CONTRACT
PRICE
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
9.00
-36.00
$57.50
$2,070.00
included ) Feet 45
401 Furnish and install 6"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
100 63.00
-37.00
$60.00
$2,220.00
included Feet
402 Furnish and install 8"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
25 27.00
2.00
$62.80
$125.60
included Feet
403 Furnish and install 10"
ductile iron water main
w /poly wrap, complete as
specified (fittings not Linear
1700 1668.00
-32.00
$70.60
$2,259.20
included Feet
Page 3 of 6
CONTRACT: 09 - 28 CHANGE ORDER # 1
Page 4 of 6
INCREASEIN
DECREASEIN
ITEM
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COSTPER
UNIT
CONTRACT
PRICE
CONTRACT
PRICE
NUMBER
Furnish and install 1' water
404
service
relay, complete as
specified,
not including
corporation and stop box
Linear
30.00
- 70.00
$40.60
$2,842.00
Furnish and install 1
Feet
100
405
water service relay,
complete as specified, not
including
corporation and
Linear
34.00
-16.00
$54.30
$868.80
sto box
Feet
50
406
Furnish and install 2" water
service relay, complete as
specified, not including
corporation and stop box
Linear
4.00
-11.00
$64.35
$707.85
Feet
15
407
Fumish and install 1°
corporation and stop box
with rod, complete as
3.00
$227.30
specified
Furnish and install 1 'h"
Each
3
408
corporation and stop box
with rod, complete as
3.00
$480.00
s ecified
Each
3
409
Furnish and install 2'
corporation and stop box
with rod, complete as
2.00
- 1.00
$630.00
$630.00
s ecified Each 3
Furnish and install 8' x 6"
410
tee, complete as specified
1.00
$302.00
Each 1
Fumish and install 10" x 4"
411
tee, complete as specified
$312.00
Each 1
Furnish and install 10"x 6"
1.00
412
tees, complete as specified
$348.00
Each 2
Furnish and install 10' x 8"
2.00
413
tees, complete as specified
$376.50
Each 2
Furnish and install 10" x
2.00
414
10" cross, complete as
1.00
$525.00
s ecified Each 1
Furnish and install 4" valve,
415
complete as specified
1.00
$740.00
Each 1
Furnish and install 6"
416
valves, complete as
3.00
$875.00
s ecified Each 3
Furnish and install 8"
417
valves, complete as
2.00
$1,204.00
s ecified Each 2
Furnish and install 10°
418
valves, complete as
8.00
2.00
$ 1,670.00
$3,340.00
s ecified Each 6
Furnish and install 10" cut -
419
in valve, complete as
1
0.00
-1
$2,277.00
$2,277.00
s ecified Each
Page 4 of 6
CONTRACT: 09 - 28 CHANGE ORDER # 1
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
INCREASE
COST PER
UNIT
IN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
420
Furnish and install 10" -11
s
% bends, complete as
ecified
Each
3
0.00
-3.00
$289.00
$867.00
421
Fumish and install 4' - 45°
bends, complete as
s cified
Each
2
1.00
-1.00
$138.00
$138.00
422
Furnish and install 6' - 45°
bends, complete as
s ecified
Each
4
14.00
10.00
$182.00
$1,820.00
423
and install 10' - 45°
bends, complete as
s ecified
Each
17
9.00
_g Op
$310.00
$2,480.00
424
Furnish and install 8' x 6'
reducers, complete as
s ecified
Each
2
2.00
$200.00
425
Furnish and install 10" x 6"
reducers, complete as
s ecified
Each
1
1.00
$220.00
426
Fumish and install
hydrants, complete as
s ecified
Each
3
3.00
$2460.00
,
427
Furnish and install
gradeloks, complete as
s ecified
Each
3
0.00
-3.00
$74.00
$222.00
428
Furnish and install
connections of new water
main to existing water main
(various sizes and
locations), complete as
s cified
Each
5
7.00
2.00
$1,488.00
$2,976.00
429
Abandon water main on W.
Murdock Avenue
(Wisconsin St. to Burdick
St.), complete as specified
Lump
Sum
1
1.00
$1,060.00
430
Abandon water main on
Jackson Street (Sta 19 +00
to Sta 25 +00), including
crossing streets, complete
as specified
Lump
Sum
1
1.00
$1,060.00
431
Furnish and stall
reconnections of existing
water services, complete
ass specified
Each
7
4.00
-3.00
$300.00
$900.00
SECTION IV
- (BID ITEMS
400 - 431)
- SUB - TOTALS $8,261.60
($18,481.85)
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
ITEM I DESCRIPTION
NUMBER
432 Furnish and install 10"
sleeves, complete as
INCREASE IN DECREASE IN
UNIT CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTRACT
QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE
Each 0.00 3.00 1 3.00
Page 5 of 6
901 $773.70
CONTRACT: 09 - 28 CHANGE ORDER # 1
ADDITIONAL WORK: C.O. # 1 (ITEMS 432-438) - SUB -TOTAL $4,499.61
NET DECREASE TO: SECTION IV
NET INCREASE TO SECTIONS I, II, III, IV
NET DECREASE TO SECTIONS I, II, III, IV
NET DECREASE TO CONTRACT:
($5,720.64)
$39,032.04
($63,959.92)
($24,927.88)
$0.00
Page 6 of 6
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
ITEM
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
Furnish and install 6"
433
sleeves, complete as
Each
0.00
3.00
3.00
$175.20
$525.60
specified
Furnish and install 6" cap,
complete as specified
Furnish and install low
Each
0.00
1.00
1.00
$111.15
$111.15
434
435
permeable plugs, complete
Each
0.00
4.00
4.00
$65.00
$260.00
ass ecified
Furnish and install 12"
436
sleeve, complete as
Each
0.00
1.00
1.00
$387.60
$387.60
s ecified
Furnish excavation, labor,
437
and equipment to cut and
plug existing watermain in
the intersection of Jackson
and Murdock, per Invocie
Lump
0.00
1.00
1.00
$1,296.23
$1,296.23
#09- 558 -01
Furnish labor and
Sum
438
equipment to remove
existing water valve
manhole that was in
clonflcit with propsoed
water main work at Station
56 +75, per Invocie #09 -558
Lump
Sum
0.00
1.00
1 1.00
1
$1,145.33
1 $1,145.33
02
ADDITIONAL WORK: C.O. # 1 (ITEMS 432-438) - SUB -TOTAL $4,499.61
NET DECREASE TO: SECTION IV
NET INCREASE TO SECTIONS I, II, III, IV
NET DECREASE TO SECTIONS I, II, III, IV
NET DECREASE TO CONTRACT:
($5,720.64)
$39,032.04
($63,959.92)
($24,927.88)
$0.00
Page 6 of 6