Loading...
HomeMy WebLinkAbout10-08JANUARY 12, 2010 10 -08 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDER NO. 2 FOR PUBLIC WORKS CONTRACT NO. 09 -06 WITH FISCHER -ULMAN CONSTRUCTION, INC., FOR VARIOUS CONCRETE SIDEWALK- CONCRETE PAVING ($73,360.74) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: FISCHER -ULMAN CONSTRUCTION 1115 S. THEODORE ST. APPLETON WI 54915 Net Increase to contract: $73,360.74 PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Acct. No. 311- 0410- 7480 -00000 Sidewalk Construction Fund Expenditures Acct. No. 311- 0410- 7480 -03304 Special Assessments - Sidewalks Acct. No. 541 - 1867 - 6401 -08673 Water Utility - Maintenance of Mains Acct. No. 541 - 1867 - 6401 -08675 Water Utility - Maintenance of Services Acct. No. 561 - 2010 - 1799 -00000 Storm Water Utility Construction CONTRACT: 09 -06 CHANGE ORDER # 2 CONCRETE SIDEWALK (New and Reconstruction) 1 Sidewalk removal & INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER complete asspecified Feet QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 1 Sidewalk removal & driveway removal, Square complete asspecified Feet 95,520.00 106,019.38 10,499.38 0.33 3,464.80 2 Concrete /asphalt sawing, Linear complete asspecified Feet 4,750.00 4,826.20 76.20 2.00 152.40 3 Construct 4" thick concrete sidewalk in various locations in the City of Oshkosh, complete as Square s ecified Feet 1 92,500.00 97,452.64 4,952.64 2.72 13,471.18 4 Construct 6" thick concrete sidewalk in various locations in the City of Oshkosh, complete as Square specified Feet 18,000.00 17,890.10 - 109.90 3.08 $338.49 5 Construct 7" thick crosswalk areas, complete Square asspecified Feet 5,000.00 3,006.77 - 1,993.23 3.28 $6,537.79 6 Provide and install metal detectable warning plates, complete as specified Square Feet 272.00 248.00 -24.00 28.00 $672.00 7 Three (3 ") inch asphalt replacement, complete as Square specified Feet 2,000.00 2,313.35 313.35 3.70 1,159.40 8 Curb and gutter removal, Linear complete asspecified Feet 425.001 442.60 17.60 3.50 61.60 9 Construct 30" curb and gutter, complete as Linear specified Feet 425.00 442.60 17.60 16.80 295.68 10 Terrace restoration, including seed, fertilizer, and mulch, complete as Square specified Yards 1,000.00 3,618.66 2,618.66 3.90 10,212.77 11 Furnish and install pavement ties, complete as specified Each 125.00 51.00 -74.00 7.00 $518.00 12 Construct 4" thick concrete sidewalk in Water Dept. repair locations as approx. 60 sites, complete as Square specified Feet 1 2,500.00 2,141.85 - 358.15 4.10 $1,468.42 13 Construct 6" thick concrete sidewalk in Water Dept. repair locations at approx. 20 sites, complete as Square specified Feet 1,500.00 630.93 1 - 869.07 4.26 $3,702.24 14 7" non - reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, Square complete asspecified Yards 100.00 126.01 26.01 39.00 1,014.39 Page 1 of 5 CONTRACT: 09 -06 CHANGE ORDER # 2 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN CONTRACT DECREASE IN CONTRACT NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 15 8" non - reinforced concrete Feet QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 3 pavement removal and replacement, including Square sawing, pavement ties, Yards 1,034.401 881.90 - 152.50 39.00 $5,947.50 integral curb & grading, terrace & traffic control, complete as specified Square Yards 1,500.00 311.37 - 1,188.63 39.00 $46,356.57 16 8" special High Early Strength, non - reinforced concrete pavement removal and replacement, including sawing, pavement ties, integral curb and grading, terracing and traffic control, Square complete asspecified Yards 175.00 8.00 - 167.00 46.50 $7,765.50 17 Extra crushed stone base, complete as specified Tons 250.00 79.20 - 170.80 14.00 $2,391.20 18 No. 4 epoxy- coated reinforced rods, installed Linear asspecified Feet 300.00 260.00 - 40.00 1.50 $60.00 19 Furnish, install, and maintain Type "C" inlet protection, complete as specified Each 15.00 0.00 -15.00 40.00 $600.00 20 Furnish, install, and maintain Type "D" inlet protection, complete as specified Each 5.00 41.00 36.00 40.001 1,440.00 21 Construct 12" wide radius curb head, complete as Linear specified Feet 175.00 113.50 -61.50 3.50 $215.25 22 Furnish, install, and maintain erosion mat, Square complete asspecified 1 Yards 600.00 70.60 - 529.40 1 1.75 $926.45 23 Profile sawcut concrete Linear 1 curb, complete as specified Feet 60.00 37.40 -22.60 40.00 $904.00 SUB -TOTAL CONCRETE SIDEWALK (NEW & RECONSTRUCTION) 31,272.22 ($72,455.91) CHANGES TO CHANGE ORDER #1 ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT CONCRETE PAVING 1 Pavement removal Square Yards 453.30 442.80 -10.50 7.00 INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT C/O #1 INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER removal Feet QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 1 Pavement removal Square Yards 453.30 442.80 -10.50 7.00 $73.50 2 Sidewalk & driveway Square removal Feet 10,141.00 11,565.20 1,424.20 0.33 469.99 3 8" Concrete pavement with integral curb, 6" base & Square g rading Yards 1,034.401 881.90 - 152.50 39.00 $5,947.50 Page 2 of 5 CONTRACT: 09 -06 CHANGE ORDER # 2 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN CONTRACT DECREASE IN CONTRACT NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 4 12" Radius curb head Linear QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 19 sum with castings Feet 113.40 123.20 9.80 3.50 34.30 5 4" Concrete sidewalk Square 0.00 49.10 49.10 2.00 98.20 one location Feet 5,188.50 7,542.20 2,353.70 2.72 6,402.06 6 6" Concrete sidewalk Square location 5' ID Feet 2,592.00 1,364.90 - 1,227.10 3.08 $3,779.47 7 Adjust manholes & inlets Each 13.00 15.00 2.00 125.00 250.00 8 No. 4 reinforcing bars Linear 5.00 5.00 385.00 16 ( epoxy coated Feet .240.00 540.00 300.00 1.50 450.00 9 Detectable warning field Square 17.00 6.00 -11.00 1 110.00 $1,210.00 17 Connect to ex storm Feet 48.00 56.00 8.00 28.00 224.00 10 Terrace work Square 5.00 5.00 1 165.00 Yards 922.40 744.60 - 177.80 3.90 $693.42 CHANGE TO ADDITIONAL ITEMS - CONCRETE PAVING - SUB - TOTALS 7,830.35 ($10,493.89) CHANGES TO CHANGE ORDER #1 ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT STORM SEWER 11 12" Storm sewer Linear INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT C/O #1 INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER Inlets (type 3 with 18" Sum QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 11 12" Storm sewer Linear INCREASE IN DECREASE IN ITEM DESCRIPTION Feet 159.00 157.80 NET -1.20 49.50 CONTRACT $59.40 12 Inlets (type 3 with 18" Sum QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 19 sum with castings Each 8.00 8.00 1,650.00 13 Rebuild storm manhole in Feet 0.00 49.10 49.10 2.00 98.20 one location Each 2.50 6.86 4.36 1,375.00 5,995.00 14 Std. storm manhole in one location 5' ID Each 4.46 3.47 -0.99 550.00 ($544.50) 15 Abandon inlets or manholes Each 5.00 5.00 385.00 16 Furnish, install, & maintain type D inlet protection Each 17.00 6.00 -11.00 1 110.00 $1,210.00 17 Connect to ex storm 1 manhole Each 5.00 5.00 1 165.00 CHANGE TO ADDITIONAL ITEMS - STORM SEWER - SUB - TOTALS 5,995.00 ($1,813.90) ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT - C/O #2 CONCRETE PAVING 18 Abandon two concrete INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED I NET NET COST PER CONTRACT CONTRACT NUMBER complete asspecified Sum QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 18 Abandon two concrete vaults on W. 8th Avenue, Lump complete asspecified Sum 0.00 1.00 1.00 1,845.00 1,845.00 19 Concrete sawing, complete Linear ass ecified Feet 0.00 49.10 49.10 2.00 98.20 Page 3 of 5 CONTRACT: 09 -06 CHANGE ORDER # 2 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN CONTRACT DECREASE IN CONTRACT NUMBER DESCRIPTION UNIT QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 20 8" Special High Early QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE Strength non - reinforced concrete pavement removal & replacement, Square including sawing, Yards 0.00 72.51 72.51 44.55 3,230.32 pavement ties, integral curb and grading, terracing and traffic control, Square complete as specified Yards 0.00 40.50 40.50 46.50 1,883.25 21 Extra crushed stone base, complete as specified Tons 0.00 250.00 250.00 14.00 3,500.00 22 8"/7-bag non - reinforced concrete removal and replacement, including sawing, pavement ties, integral curb & grading, terracing and traffic control, Square . complete asspecified Yards 0.00 250.70 250.70 45.12 11,311.58 23 8" Concrete sidewalk, Square complete asspecified Feet 0.00 56.00 56.00 4.771 267.12 ADDITIONAL ITEMS - CONCRETE PAVING - SUB - TOTALS 18,905.15 $0.00 ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT - C/O #2 QTnMeA 001AIC0 24 6 Hours to relocate inlets on W. 9th Avenue and Nebraska Street Each 0.00 6.00 6.00 300.00 1,800.00 ADDITIONAL ITEMS - STORM SEWER - SUB - TOTALS 1,800.00 $0.00 CONCRETE SIDEWALK (New and Reconstruction) Ar1r11T1AAl AI ITCIIAC 7 "/7 -Bag non - reinforced INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER I CONTRACT CONTRACT NUMBER replacement, including QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 24 6 Hours to relocate inlets on W. 9th Avenue and Nebraska Street Each 0.00 6.00 6.00 300.00 1,800.00 ADDITIONAL ITEMS - STORM SEWER - SUB - TOTALS 1,800.00 $0.00 CONCRETE SIDEWALK (New and Reconstruction) Ar1r11T1AAl AI ITCIIAC 25 7 "/7 -Bag non - reinforced INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER replacement, including QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 25 7 "/7 -Bag non - reinforced concrete removal & replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, Square complete as specified Yards 0.00 72.51 72.51 44.55 3,230.32 Page 4 of 5 CONTRACT: 09 -06 CHANGE ORDER # 2 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER INCREASE IN CONTRACT DECREASE IN CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 26 8 "/7 -bag non - reinforced concrete removal & replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, Square complete asspecified Yards 0.00 1,146.08 1,146.08 45.12 51,711.13 27 8 "/8 -bag non - reinforced concrete removal & replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, Square complete asspecified Yards 0.00 276.17 276.17 45.92 12,681.73 28 9 "/7 -bag non - reinforced concrete removal & replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, Square complete as specified Yards 0.00 164.52 164.52 54.75 9,007.47 29 9 " /8-bag non - reinforced concrete removal & replacement, including sawing, pavement ties, integral curb & grading, terracing & traffic control, Square complete ass ecified Yards 0.00 92.25 92.25 59.85 5,521.16 30 8" curb, complete as Linear specified Feet 0.00 63.00 63.00 5.17 325.71 31 8" sidewalk, complete as Square specified Feet 0.00 1,560.00 1,560.00 4.77 7,441.20 32 Move shed at 3098 Jackson Street, complete Lump asspecified Sum 0.00 1.00 1.00 80.00 80.00 33 Remove trees, brush, and stumps at 3098 Jackson Street, complete as Lump specified Sum 0.00 1.00 1.00 875.00 875.00 34 Remove two trees at 51 Fernau Avenue, complete Lump asspecified Sum 0.00 1.00 1.001 120.00 120.00 35 Remove 56 ft. of .5' curb at 2920 N. Main Street, Linear complete ass ecified Feet 0.00 56.00 56.00 3.50 196.00 36 Replace 21 ft. of .5' curb at 2920 N. Main Street, Linear com lete asspecified Feet 0.00 21.00 21.00 12.00 252.00 37 Grade fill under sidewalk at miscellaneous locations, Lump complete ass ecified Sum 0.00 1.00 1.00 880.00 880.00 ADDITIONAL ITEMS - CONCRETE SIDEWALK 92,321.72 $0.00 158,124.44 ($84,763.70) NET INCREASE TO CONTRACT 09 -06: 73,360.74 Page 5 of 5