HomeMy WebLinkAbout09-444NOVEMBER 24, 2009 09 -444 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS CONTRACT NO. 09 -13 WITH BUTEYN- PETERSON CONSTRUCTION CO. FOR TIPLER STORM WATER IMPROVEMENTS ( +$16,005.30) INITIATED BY: DEPARTMENT OF PUBLIC WORKS BE IT RESOLVED by the Common Council of the City of Oshkosh that the following Change Order, a copy of which is attached, is hereby approved: BUTEYN- PETERSON CONSTRUCTION CO. N7337 DAIRYLAND DR SHEBOYGAN, WI 54083 Net Increase to contract: $16,005.30 PURPOSE: See attached Change Order. BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated from: Acct. No. 561 - 2010 - 1799 -00000 -- Storm Water Utility Construction Work In Progress ( 0 OfHKOIH ON THE WATER MEMORANDUM TO: Honorable Mayor and Members of the Common Council FROM: Steven M. Gohde, Assistant Director of Public Works DATE: November 19, 2009 RE: Change Order #1 for Public Works Contract No. 09 -13/ Buteyn- Peterson Construction Co./ Tipler Storm Water Improvements ( +$16,005.30) BACKGROUND Change Order #1 for Contract 09 -13 is scheduled for consideration by the Common Council at the November 24, 2009 meeting. The contract was originally awarded to Buteyn- Peterson Construction Co. in September of 2009. This change order is for installing high early strength concrete adjacent to the school to allow for better access and replacing a storm sewer line. ANALYSIS During the construction the School District became concerned with access to the School with half of the concrete pavement removed. Due to the time of year and school schedule there was not adequate time for standard concrete to cure and maintain access to the school drop off areas. It was decided to use high early strength concrete to maintain better access. The additional cost of the high early strength concrete is $1,106.10. A storm sewer line was discovered during the construction that was in conflict with the detention basin. The storm line was rerouted to connect to the system outside of the basin limits. The total cost to reroute the storm sewer line is $14,899.20. FISCAL IMPACT The total increase in cost is $16,005.30. Adequate funding is available in the Storm Water Section of the Capital Improvement Program. RECOMMENDATIONS I recommend approval of the Change Order #1 to Contact No. 09 -13 in the amount of $16,005.30 to Buteyn- Peterson Construction Co. Respectfully Submitted, Approved: Steven M. Gohde Asst. Director of Public Works City Manager I:\Engineering109 -13 Tipter Detention Basin\Project_ Information \Correspondence\Memo\CO # 1 exp.doc 4 TO: Buteyn- Peterson Construction Co N7337 Dairyland Drive Sheboygan, WI 54083 CHANGE ORDER # 1 DATED: November 13, 2009 Your present contract with the City of Oshkosh, Contract No. 09 -13 , is hereby amended and changed as follows: NET INCREASE TO: SECTION I - PAVING NET INCREASE TO: SECTION II - STORM SEWER NET INCREASE TO CONTRACT: M Recommended: Director of Public Works $1,106.10 $14,899.20 $16,005.30 CITY OF OSHKOSH City Manager City Clerk I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Comptroller Approved, as to form: City Attorney SECTION I - PAVING CONTRACT: 09 -13 CHANGE ORDER # 1 103 7 -IN non - reinforced concrete INCREASEIN DECREASE IN F TEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COSTPER CONTRACT CONTRACT MBER curb and grading, pavement QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 103 7 -IN non - reinforced concrete INCREASEIN DECREASEIN ITEM pavement, including integral UNIT CONTRACT I INSTALLED NET NET COSTPER CONTRACT CONTRACT I NUMBER curb and grading, pavement QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE ties, base in place, complete Square as specified Yards 400 0.00 - 400.00 $58.80 $23,520.00 SECTION 1- (BID ITEM 103) - SUB - TOTALS ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I $0.00 ($23,520.00) 112 7 -IN non - reinforced concrete INCREASEIN DECREASEIN ITEM DESCRIPTION UNIT CONTRACT I INSTALLED NET NET COSTPER CONTRACT CONTRACT I NUMBER curb and grading, pavement QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 112 7 -IN non - reinforced concrete pavement, including integral curb and grading, pavement ties, base in place, using High Early Contrete (7 -bag), this item replaces Bid Item 103, complete as specified Square Yards 390.00 390.00 $61.43 1 $23,957.70 113 7 -1N non - reinforced concrete pavement, including integral curb and grading, pavement ties, base in place, using Super High Early Contrete (9 -bag), this item replaces Bid Item 103, complete as Square specified Yards 10.00 10.00 $66.84 $668.40 ADDITIONAL WORK: C.O. # 1 - (ITEMS 112 -113) - SUB -TOTAL NET INCREASE TO: SECTION I $24,626.10 $0.00 $1,106.10 Page 1 of 2 SECTION II - STORM SEWER 200. Temporary Construction NET DECREASE TO SECTIONS 1,11 ($23,520.00) NET INCREASE TO CONTRACT: $16,005.30 INCREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER CONTRACT CONTRACT NUMBER specified Feet QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE 200. Temporary Construction NET DECREASE TO SECTIONS 1,11 ($23,520.00) NET INCREASE TO CONTRACT: $16,005.30 INCREASEIN DECREASE IN ITEM Fence, complete as Linear CONTRACT INSTALLED NET NET COST PER I CONTRACT CONTRACT NUMBER specified Feet 1,700 1,900.00 200.00 DECREASE $1.31 $262.00 PRICE 225. Furnish, install, maintain, and remove Inlet Sediment Control Protection, Type D, complete as specified Each 6 20.00 14.00 1 $85.001 $1,190.00 SECTION II - (BID ITEMS 200 & 225) - SUB - TOTALS $1,452.00 $0.00 ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION 11 2:]specified Furnish and install 15 inch PVC, complete as Linear I Foot 312.00 1 312.00 $43.10 $13,447.20 CONTRACT: 09 -13 CHANGE ORDER # 1 $39,525.30 NET DECREASE TO SECTIONS 1,11 ($23,520.00) NET INCREASE TO CONTRACT: $16,005.30 INCREASEIN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET COST PER I CONTRACT CONTRACT NUMBER QUANTITIES QUANTITIES INCREASE DECREASE . UNIT PRICE PRICE 2:]specified Furnish and install 15 inch PVC, complete as Linear I Foot 312.00 1 312.00 $43.10 $13,447.20 CONTRACT: 09 -13 CHANGE ORDER # 1 ADDITIONAL WORK: C.O. # 1 - (ITEMS 242) - SUB -TOTAL $13,447.20 $0.00 NET INCREASE TO: SECTION 11 $14,899.20 NET INCREASE TO. SECTIONS I, II $39,525.30 NET DECREASE TO SECTIONS 1,11 ($23,520.00) NET INCREASE TO CONTRACT: $16,005.30 N C CREASE IN DECREASE IN ITEM DESCRIPTION UNIT CONTRACT I INSTALLED NET NET COST PER CONTRACT CONTRACT . 1 I NUMBER QUANTITIES QUANTITIES INCREASE DECREASE UNIT PRICE PRICE ADDITIONAL WORK: C.O. # 1 - (ITEMS 242) - SUB -TOTAL $13,447.20 $0.00 NET INCREASE TO: SECTION 11 $14,899.20 NET INCREASE TO. SECTIONS I, II $39,525.30 NET DECREASE TO SECTIONS 1,11 ($23,520.00) NET INCREASE TO CONTRACT: $16,005.30 Page 2 of 2