HomeMy WebLinkAbout09-425NOVEMBER 10, 2009 09 -425 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT NO. 09 -20 WITH FOUR -WAY CONSTRUCTION
OF WI, INC. FOR MINI STORM SEWER /STORM LATERALS
(- $754.04)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
FOUR -WAY CONSTRUCTION OF WI, INC.
PO BOX 133
BERLIN, WI 54923
Net decrease to contract: (- $754.04)
PURPOSE: See attached Change Order.
( 0
Oil-NO Oil-NOf H
ON THE WATER
MEMORANDUM
TO:
FROM
DATE:
RE:
BACKGROUND
Honorable Mayor and Members of the Common Council
Steven M. Gohde, Assistant Director of Public Works
November 5, 2009
Change Order #1 for Public Works Contract No. 09 -20/ Four -Way Construction of WI, Inc./
Mini Storm Sewer /Storm Laterals (- $754.04)
Change Order #3 for Contract 09 -20 is scheduled for consideration by the Common Council at the November
10, 2009 meeting. The contract was originally awarded to Four -Way Construction of WI, Inc. in September of
2009. This is the final change order for the contract.
ANALYSIS
Upon completion of the work final quantities were measured. The final quantities increase and decrease for
various bid items. The changes are a result of matching field conditions.
FISCAL IMPACT
Funding is in the 2009 Capital Improvement Budget under the Storm Sewer Section. The total change is a
decrease of $754.04.
RECOMMENDATIONS
recommend approval of the Change Order # 1 to Contact No. 09 -20 in the amount of ($754.04) to Four -Way
Construction of WI, Inc.
Respectfully Submitted,
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
IAEngineering109 -20 Mini Storm SewerTroject_ Information lCorrespondence\Memo\CO #I exp.doc
CHANGE ORDER # 1
DATED: October 30, 2009
TO: Four -Way Construction Co. of WI, Inc.
P. O. Box 133
Berlin, WI 54923
Your present contract with the City of Oshkosh, Contract No. 09 -20 , is hereby amended
and changed as follows:
NET DECREASE TO: SECTION I - CONCRETE PAVING
NET DECREASE TO: SECTION II - STORM SEWER
($353.04)
($401.00)
NET DECREASE TO CONTRACT:
($754.04)
CITY OF OSHKOSH
Recommended:
BY:
City Manager
Director of Public Works
City Clerk
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT: 09 -20 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
100 Pavement removal,
Square
64
33.70
-30.30
$4.65
INCREASE IN
DECREASE !N
ITEM
Yards
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
NUMBER
100 Pavement removal,
Square
64
33.70
-30.30
$4.65
$140.89
complete asspecified
Yards
101 Sidewalk removal,
Square
Feet
112
404.65
292.65
$1.00
$292.65
complete ass specified
102 Concrete pavement,
including curb and grading,
complete as specified
Square
Feet
438
180.60
- 257.40
$10.00
$2,574.00
103
Asphalt pavement,
including grading, complete
Square
Feet
138
122.00
-16.00
$8.45
$135.20
ass specified
4" concrete sidewalk,
Square
Feet
112
404.65
292.65
$8.00
$2,341.20
104
com fete asspecified
Sawing, complete as
Linear
Feet
215
160.28
-54.72
$2.50
$136.80
105
specified
Terrace work at 1220
106
Greenfield Trail, complete
Lump
1
0.00
-1.00
$200.00
$200.00
asspecified
Terrace work at 1242
Sum
107
Liberty Street, complete as
Lump
$150.00
specified
Terrace work at 1516
Sum
1
1.00
108
Menominee Drive,
Lump
1
1.00
$300.00
complete ass specified
Terrace work at 2205
Sum
109
Allerton Drive, complete as
Lump
$200.00
[ specified
Sum
1
1.00
110
Terrace work at 1906
Doemel Street, complete
Lump
$150.00
ass specified
Sum
1
1.00
111
Terrace work at 1633
through 1719 Doemel
Street, complete as
Lump
1
1.00
$1,020.00
s ecified
Terrace work at 1815 East
Sum
112
Murdock Avenue and 1790
Cliffview Drive, complete
Lump
$850.00
ass specified
Terrace work at 1511
Sum
1
1.00
113
Coolidge Avenue, complete
Lump
$175.00
asspecified
Terrace work and
Sum
1
1.00
114
restoration for storm sewer
easement at 539 West
17th Avenue, complete as
Lump
$300.00
specified
Terrace work at 151 West
Sum
1
1.00
115
Fernau Avenue, complete
Lump
$210.00
ass specified
Sum
1
1.00
SECTION I - (BID ITEMS 100 -115) - SUB - TOTALS $2,633.85 ($3,186.89)
Page 1 of 3
CONTRACT: 09 -20 CHANGE ORDER # 1
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
LINCREA S E
NET
DECREASE
COSTPER
UNIT
INCREASElN
CONTRACT
PRICE
DECREASE IN
CONTRACT
PRICE
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
QUANTITIES
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
COSTPER
UNIT
INCREASE IN
CONTRACT
PRICE
DECREASE 1N
CONTRACT
PRICE
ITEM
NUMBER
DESCRIPTION
200.
Furnish and install 6" storm
116
Terrace work at 1285
sewer, complete as
Linear
Feet
380
399.00
Heritage Trail, complete as
s ecified
Lump
Sum
1.00
1.00
$200.00
$200.00
ADDITIONAL WORK: C.O.
# 1 - (ITEM 116) - SUB -TOTAL
$200.00
$0.00
201.
Furnish and install 12"
NET DECREASE TO:
SECTION 1
($353.04)
SECTION II - STORM SEWER
Page 2 of 3
CONTRACT
INSTALLED
NET
NET
COSTPER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
ITEM
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
200.
Furnish and install 6" storm
sewer, complete as
Linear
Feet
380
399.00
19.00
$ 26.95
$512.05
s ecified
201.
Furnish and install 12"
storm sewer, complete as
Linear
56
42.00
- 14.00
$46.60
$652.40
specified
Feet
202.
Furnish and install std.
inlets (Type 1 with no
sump) with castings,
1
1.00
$985.00
com lete ass pacified
Each
203.
Furnish and install std.
storm manhole (4' inside
diameter) in 1 (one)
location without casting,
Vertical
Feet
3.53
3.96
0.43
$354.00 $152.22
complete ass ecified
204.
Furnish and install 6" storm
lateral, complete as
Linear
Feet
208
195.50
-12.50
$52.95
$661.87}
s ecified
205.
Fumish and install storm
lateral marker balls,
complete asspecified
Each
28
29.00
1.00
$20.00 $20.00
206.
Furnish, install, and
maintain Type "D" inlet
protection std., complete
26
24.00
.2 00
$85.00
$170.00
ass ecified
Each
207.
Connection to existing
5
3.00
-2.00
$85.00
$170.00
storm sewer
Each
208.
Tap existing storm inlet,
5
7.00
2.00
$85.00 $170.00
complete ass specified
Each
SECTION 11
- (BID ITEMS 200-208)
- SUB - TOTALS
$854.27
($1,654.27)
ADDITIONAL WORK REQUIRED:
C.O. # 1 -
SECTION II
Page 2 of 3
CONTRACT: 09 -20 CHANGE ORDER # 1
209 Frost sleeves for
clean -outs Each 7.00 7.00 $57.00 $399.00
ADDITIONAL WORK: C.O. # 1 - (ITEM 209) - SUB -TOTAL $399.00 $0.00
NET DECREASE TO: SECTION II ($401.00)
NET INCREASE TO SECTIONS I, it $4,087.12
NET DECREASE TO SECTIONS I, II ($4,841.16)
NET DECREASE TO CONTRACT: ($754.04)
Page 3 of 3
INCREASEIN
DECREASEIN
ITEM
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
INCREASE IN
DECREASE IN
ITEM
CONTRACT
INSTALLED
NET
NET
COSTPER
CONTRACT
CONTRACT
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
209 Frost sleeves for
clean -outs Each 7.00 7.00 $57.00 $399.00
ADDITIONAL WORK: C.O. # 1 - (ITEM 209) - SUB -TOTAL $399.00 $0.00
NET DECREASE TO: SECTION II ($401.00)
NET INCREASE TO SECTIONS I, it $4,087.12
NET DECREASE TO SECTIONS I, II ($4,841.16)
NET DECREASE TO CONTRACT: ($754.04)
Page 3 of 3