HomeMy WebLinkAbout09-420OCTOBER 27, 2009 09 -420 RESOLUTION (CARRIED 7 -0 LOST LAID OVER WITHDRAWN ) PURPOSE: APPROVE RECOMMENDATIONS FOR STORMWATER MANAGEMENT IN THE CAMPBELL CREEK AND SAWYER CREEK DRAINAGE BASINS INITIATED BY: DEPARTMENT OF PUBLIC WORKS WHEREAS, the City of Oshkosh has recently experienced severe flooding during rain events in 2004 and 2008; and WHEREAS, the City entered into contracts with Strand Associates for the exploration of various alternatives for storm water management in the Campbell Creek Drainage Basin and the Sawyer Creek Drainage Basin; and WHEREAS, these plans were presented to the Council in November 2006, February 2008, and in September 2009; and WHEREAS, the Common Council approved recommendations for stormwater management facilities including related drainage system improvements in the Campbell Creek Drainage Basin at Tipler Middle School and at the National Guard Armory in August 2008 per Resolution 08 -326; and WHEREAS, the Common Council has decided not to pursue the proposal for development of stormwater management facilities which would have required the purchase of the entire Westhaven Golf Course. NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Oshkosh that the staff is hereby authorized and directed to implement recommendations for the Campbell Creek Drainage Basin and Sawyer Creek Drainage Basin including related drainage system improvements as follows: Campbell Creek: Wet Detention Basin in the 9th Avenue/Washburn Street area Wet Detention Basin on the vacant land (approximately 5 acres) south of 1400 Westhaven Drive (Golf Course Clubhouse) Sawyer Creek: Dry Detention Basin in James Road /State Trunk Hwy. 91 Area ( 0 OfHKO1H ON THE WATER MEMORANDUM TO: Honorable Mayor and Members of the Common Council FROM: Steven M. Gohde, Assistant Director of Public Works DATE: October 23, 2009 RE: Approve Recommendations for Stormwater Management in the Campbell Creek and Sawyer Creek Drainage Basins BACKGROUND The Department of Public Works hired Strand and Associates to perform stormwater management studies for the Campbell Creek and Sawyer Creek drainage basins. The reports consisted of several options to provide flood control and pollution control basins. The Department of Public Works is seeking approval to implement the non - Westhaven options. Included with this option are the previously approved Tipler Middle School and National Guard Armory sites, a wet detention basin at the vacant property near 9th Ave. and Washburn Street and a detention basin near James Road/ State Hwy. 91. In addition, the Department of Public Works recommends pursuing a wet detention basin on the vacant land south of the existing Westhaven Golf Course Club house. This basin along with other improvements will provide some relief to the residents of Newport Ct. ANALYSIS The implementation of the basins mentioned above will help lessen the flooding experienced by some property owners in the Sawyer Creek and Campbell Creek Drainage Basins. The benefit of each basin will vary based on final design. Most of the basins mentioned above were analyzed on a conceptual basis in the reports that were discussed with Council on September 1, 2009. The Department of Public Works will continue to look for additional locations within the Sawyer Creek and Campbell Creek Drainage Basins to help alleviate flooding and provide pollution control. FISCAL IMPACT These basins will be budgeted in future years Capital Improvement Program Budgets for acquisition and construction. RECOMMENDATIONS I recommend approval of the recommendation to construct detention basins near 9 and Washburn, James Road and State Hwy 91 and south of the Westhaven Club House. Respectfully Submitted, Approved: A 7y � c Steven M. Gohde Asst. Director of Public Works City Manager I:\ Engineering \Correspondence \Steve Gohde \council memos \stormwater rec.doc