HomeMy WebLinkAbout09-369SEPTEMBER 22, 2009 09 -369 RESOLUTION
(CARRIED 7 -0 LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVAL OF CHANGE ORDER NO. 1 FOR PUBLIC WORKS
CONTRACT 09 -06 WITH FISCHER -ULMAN CONSTRUCTION,
FOR CONCRETE SIDEWALK- CONCRETE PAVING ON 9TH
AVENUE (MAIN TO NEBRASKA) ($107,861.57)
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
FISCHER -ULMAN CONSTRUCTION
1115 S. THEODORE STREET
APPLETON, WI 54915
Net increase to contract: $107,861.57
PURPOSE: See attached Change Order.
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from:
Acct. No. 534 - 1040- 6401 -00000 — TID No. 20, Southshore Redevelopment
CHANGE ORDER # 1
DATED: September 16, 2009
TO: FISCHER -ULMAN CONSTRUCTION
1115 S. THEODORE STREET
APPLETON, WI 54915
Your present contract with the City of Oshkosh, Contract No
and changed as follows:
NET INCREASE TO CONTRACT:
fflu
Recommended:
. Director of Public Works
09 -06 , is hereby amended
$107,861.57
CITY OF OSHKOSH
City Manager
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
City Clerk
I CONTRACT: 09 -06 CHANGE ORDER # 1
ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT
rnK1r0ere owiKira
1
Pavement removal
Square
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COSTPER
CONTRACT
CONTRACT
NUMBER
Sidewalk & driveway
Square
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
1
Pavement removal
Square
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
Yards
0.00
453.30
453.30
NET
7.00
3,173.10
CONTRACT
2
Sidewalk & driveway
Square
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
removal
Feet
0.00
10,141.00
10,141.00
0.33
3,346.53
3
8" Concrete pavement with
Square
integral curb, 6" base &
Yards
0.00
2.50
2.50
1,375.00
3,437.50
14
wading
Each
0.00
1,034.40
1,034.40
39.00
40,341.60
4
12" Radius curb head
Linear
0.00
4.46
4.46
550.00
2,453.00
15
Abandon inlets or
Feet
0.00
113.40
113.40
3.50
396.90
5
4" Concrete sidewalk
Square
0.00
5.00
5.00
385.00
1,925.00
16
Furnish, install, & maintain
Feet
0.00
5,188.50
5,188.50
2.72
14,112.72
6
6" Concrete sidewalk
Square
Feet
0.00
2,592.00
2,592.00
3.08
7,983.36
7
Adiust manholes & inlets
Each
0.00
13.00
13.00
125.00
1,625.00
1
8
No. 4 reinforcing bars
Linear
0.00
5.00
5.00
165.00
825.00
( epoxy coated
Feet
0.00
240.00
240.00
1.50
360.00
9
Detectable warning field
Square
Feet
0.00
48.00
48.00
28.00
1,344.00
10
Terrace work
Square
Yards
0.00
1 922.40
922.40
3.90
3,597.36
ADDITIONAL ITEMS - CONCRETE PAVING - SUB - TOTALS
ADDITIONAL WORK FOR THE MILES KIMBALL REDEVELOPMENT
cl Anan C /Cn
76,280.57 $0.00
11
12" Storm sewer
Linear
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
Inlets (type 3 with 18"
Each
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
11
12" Storm sewer
Linear
Feet
0.00
159.00
159.00
49.50
7,870.50
12
Inlets (type 3 with 18"
Each
sum with castings
0.00
8.00
8.00
1,650.00
13,200.00
13
Rebuild storm manhole in
Each
one location
0.00
2.50
2.50
1,375.00
3,437.50
14
Std. storm manhole in one
Each
location (V ID)
0.00
4.46
4.46
550.00
2,453.00
15
Abandon inlets or
Each
manholes
0.00
5.00
5.00
385.00
1,925.00
16
Furnish, install, & maintain
Each
type D inlet protection
0.00
17.00
17.00
110.00
1,870.00
17
Connect to ex storm
Each
1
1
manhole
0.00
5.00
5.00
165.00
825.00
ADDITIONAL ITEMS - STORM SEWER - SUB - TOTALS
NET INCREASE TO CONTRACT 09 -06:
31,581.00 $0.00
107,861.57
Page 1 of 1
( 0
OfHKOlH
ON THE WATER
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Steven M. Gohde, Assistant Director of Public Works
DATE: September 17, 2009
RE: Change Order #1 for Public Works Contract No. 09 -06 / Fisher -Ulman Construction Inc./
Concrete Paving on 9 Avenue (Main to Nebraska)
BACKGROUND
Change Order #1 for Contract 09 -06 is scheduled for consideration by the Common Council at the September
22, 2009 meeting. The contract was originally awarded to Fisher -Ulman Construction Inc, of Appleton, WI in
April of 2009.
ANALYSIS
In February of 2008 the Council approved Pay -go TIF funding for the redevelopment of the block between Main
Street and Nebraska Street, 8 Avenue and 91h Avenue, the former Miles Kimball block in the South Shore
Redevelopment Area. In an effort to improve the pedestrian access and provide traffic calming narrowin%of 9
Ave was included in the pro�osal. The proposal is to provide bump outs approximately mid block on 9 Ave.
and at the intersection of 9 Ave and Nebraska Street. 9 Ave. will be narrowed to 38' in the areas where
parking is allowed. This maintains one lane of traffic in each direction and parking on both sides. At the
intersection with Main St., 9 Ave will widen back to its current width of 48' to accommodate turn movements.
Sidewalks will be replaced on 9 Ave, Nebraska Street and 8th Ave. as well.
The work was not included with the original bid. The contractor has agreed to perform the additional work at
the bid prices in the contract. Additional storm sewer items have been added. The prices provided by the
contractor are comparable to other bids of similar work.
FISCAL IMPACT
Funding for this project will come from currently available TID #20 South Shore Redevelopment District
funds that have been earmarked for public improvements in this area.
RECOMMENDATIONS
I recommend approval of the Change Order # 1 to Contact No. 09 -06 in the amount of $107,861.57 to Fisher -
Ulman Construction Inc.
Respectfully Submitted,
Steven M. Gohde
Asst. Director of Public Works
Approved:
City Manager
I: \Engineering \09 -06 Concrete Sidewall Information \Correspondence \Memo \CO 9 1 exp.doc