HomeMy WebLinkAboutPW CNT 09-05 CNG# 1 FOUR-WAYCHANGE ORDER # 1
DATED: May 5, 2009
TO: Four -Way Construction of WI, Inc.
P. O. Box 133
Berlin, WI 54923
Your present contract with the City of Oshkosh, Contract No. 09 -05 , is hereby amended
and changed as follows:
NET INCREASE TO: SECTION I - CONCRETE PAVING
NET INCREASE TO: SECTION III - SANITARY SEWER
NET INCREASE TO: SECTION IV - WATER MAIN
$2,800.00
$14,208.00
$45,100.00
NET INCREASE TO CONTRACT: $62,108.00
CITY OF OSHKOSH
BY: ., _
Recommended: - City Manager
J G
Director of Public Works City Clerk J
Approved and accepted:
Contract
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
iV omptroller
�_"
CONTRACT: 09 -05 CHANGE ORDER # 1
SECTION I - CONCRETE PAVING
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION I
121 Preparation of foundation
for Asphalt Paving on
Marine Dr., complete as
specified lump sum 1.00 1.00 $2,800.00 $2,800.00
ADDITIONAL WORK: C.O. # 1 - (ITEM 121) - SUB -TOTAL $2,800.00 $0.00
NET INCREASE TO: SECTION 1 $2,800.00
SECTION III - SANITARY SEWER
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION III
Additional price pre foot to
ITEM
use 10" C -900 Cert -a -lok
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
NUMBER
complete as specified
Foot
QUANTITIES
400.00
400.00
DECREASE
$13.35
PRICE
PRICE
121 Preparation of foundation
for Asphalt Paving on
Marine Dr., complete as
specified lump sum 1.00 1.00 $2,800.00 $2,800.00
ADDITIONAL WORK: C.O. # 1 - (ITEM 121) - SUB -TOTAL $2,800.00 $0.00
NET INCREASE TO: SECTION 1 $2,800.00
SECTION III - SANITARY SEWER
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION III
317
Additional price pre foot to
ITEM
use 10" C -900 Cert -a -lok
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE 1N
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
CONTRACT
CONTRACT
NUMBER
complete as specified
Foot
QUANTITIES
400.00
400.00
DECREASE
$13.35
PRICE
PRICE
317
Additional price pre foot to
ITEM
use 10" C -900 Cert -a -lok
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
Pipe through Casing Pipe,
Linear
CONTRACT
CONTRACT
NUMBER
complete as specified
Foot
QUANTITIES
400.00
400.00
DECREASE
$13.35
$5,340.00
318
Additional price per foot to
Each
250.00
250.00
$104.40
PRICE
PRICE
422
use 12" C -900 Cert-a -lok
Pipe through casing pipes,
complete as specified
Each
400.00
400.00
$17.42
$6,968.00
319
Furnish & install 10" solid
sleeves with Megalugs,
complete asspecified
Each
2.00
2.00
$450.00
$900.00
320
Furnish & install 12" solid
sleeves with Megalugs,
complete as specified
Each
2.00 1
2.00
1
1 $500.00
1 $1,000.00
ADDITIONAL WORK: C. O. # 1 - (ITEMS 317 - 320) - SUB -TOTAL $14,208.00 $0.00
NET INCREASE TO: SECTION 111 $14,208.00
SECTION IV - WATER MAIN
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
421
Furnish and install 16"
ITEM
Ductile Iron Watermain
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
DECREASE IN
DESCRIPTION
UNIT
CONTRACT
CONTRACT
NUMBER
as specified (fittings not
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
included)
Each
250.00
250.00
$104.40
PRICE
PRICE
421
Furnish and install 16"
Ductile Iron Watermain
with Poly Warp, complete
as specified (fittings not
included)
Each
250.00
250.00
$104.40
$26,100.00
422
Furnish and install 16"
45 degree bends, complete
as specified
Each
3.00
3.00
$860.00
$2,580.00
Page 1
CONTRACT: 09 -05 CHANGE ORDER # 1
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
423
Furnish and install 16"
22.5 degree bends,
. complete asspecified
Each
1.00
1.00
$860.00
$860.00
424
Furnish and install 16"
11.25 degree bends,
complete asspecified
Each
1.00
1.00
1 $850.00
$850.00
425
Furnish & install 16" x 6"
reducer, complete as
sped ied
Each
1.00
1.00
$650.00
$650.00
426
Furnish and install 16"
valve, complete as
s ecified
Each
1.00
1.00
$6,460.00
$6,460.00
427
Furnish and install 6"
45 degree bends, complete
asspecified
Each 1
8.00
8.00
$175.00
$1,400.00
428
Relocate existing Hydrants,
complete as specified
Each
1.00
1.00
$1,500.00
$1,500.00
429
Abandon water valve
manhole, complete as
specified
Each
1.00 1
1.00
$4,700.00
$4,700.00
ADDITIONAL WORK: C.O. # 1 (ITEMS 421-429) -SUB-TOTAL $45,100.00 $0.00
NET INCREASE TO: SECTION IV - $45,100.00
NET INCREASE TO SECTIONS I, II, III, IV $62,108.00
NET DECREASE TO SECTIONS I, II, III, IV $0.00
NET INCREASE TO CONTRACT: $62,108.00
Page 2