HomeMy WebLinkAboutfluor bros fir dep renovation # 5CHANGE ORDER
PROJECT. Fire Department Renovation CHANGE ORDER NUMBER:
100 Court Street
Oshkosh, WI 54901 INITIATIONDATE.
ARCHITECTS PROJECT NUMBER:
CONTRACT FOR:
The Contract is changed as follows:
5
4 -27 -09
08018
Construction Services
26. Remove shower bases (owner agreed to'/ cost) per change order dated 9 -15 -08
$523.60
31. Relocate urinals install to close per change order dated 12 -1 -08
$1,322.95
47. Replaced entry door transom (owner agreed to'h cost) per change order dated 11 -13 -08
$466.45
49. Add some 2x2 ceramic tile to upper bathroom per change order dated 11 -10 -08
$117.85
52. Add concrete housekeeping pad per change order dated 10 -20 -08
$677.72
53. Add to fill -in reception door and redo trim per change order dated 10 -14 -08
385.25
55. Replace five locksets with passage sets per change order dated 1 -15 -09
$894.30
56. Add outlets in sleeping room per change order dated 10 -17 -09
$1,298.00
57. Add it disconnect and reconnect cad wiring in chief's sleeping room per change order dated 9 -15 -08
$1,016.50
58. Add controls for condensing unit shut down per change order dated 2 -16 -09
$588.00
59. New closer & kick plates per change order dated 1 -5 -09
$427.90
60. Add pull station per change order dated 1 -14 -09
$2,924.24
The original Contract Sum was ................................................................ ............................... $ 607,450.00
Net change by previously authorized Change Orders ................................. ............................... $1'18,571.80
The Contract Sum prior to this Change Order was ..................................... ............................... $726,021.80
The Contract Sum will be Increased by this Change Order .......................... ............................... $10,642.76
The new Contract Sum including this Change Order will be ........................ ............................... $736,664.56
The Contract Time will be (increased) (decreased) (unchanged) by # days. Unchanged
The Date of Substantial Completion as of the date of this Change order therefore is .................. Unchanged
This Change Order is not valid until signed by the Owner, Contractor and Architect.
Signature indicates agreement herewith, including any adjustment in the Contract Sum or Contract Time.
ARCHITECT.
AEC Arch itects/E ng i neers/Const.
Mgrs, LLC
P.O. Box 40
Winp(ebago, WI
PRINTED NAME:
William A. Aubrey
DATE: 4-1 Z1 --�
OWNER:
City of Oshkosh
215 Church Ave.
Oshkosh, WI 54901
BY: z "/mss ���
PRINTED NAME:
DATE:
CONTRACTOR:
Fluor Bros. Construction
203 Otter Avenue
Oshkosh WI 54903
BY:
P TED NAME:
DATE: —�� Co
September 15, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.Q. 26
Bill
This is the cost to remove shower stall bases that were billed in to the existing
floor. We had to demo out concrete and fill in with bags of concrete. This is the
breakdown. If you have any questions, please give me a call
Material
Buster—Electric -------- – - – ----- $25-00
Pea stone concrete ------------- -- $82.00
Labor to demo out ----- -- --- -- -- $520.00
Supt------------ – --------------- --- $65.00
Labor to pour and finish- - - - - -- $260.00
Sub total ------ -------- ---- ---- -- $952.00
Mark up ----------- –...._ ----------- $95.20
Total ---------------------------- $1,047.20
Sincerely
Richard Paulsen
President
December 1, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 31
Bill
This is the proposal for changing the urinal to give a 16" clear between the two in
the upper bathroom. If you have any questions, please give me a call.
Jims Plumbing -------------------------------------------- $579.00
Maccos to patch floor and base tile -------------------- $185.00
Kommorowski drywall ---------------------------------- $300.00
Fluor------------------------------------------------- - - - - -- $130.00
Best Ever Painting ----------------------------------------- $65.00
Sub total -------------------------------------------------- $1259.00
Markup------------------------------------------------------ $63.95
Total ------------------------------------------------ ------ $1,322.95
Sincerely
Richard Paulsen
President
777 - 4
November 13, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O 47
Bill
This is the change order to furnish and install new transom panel above door
#133A. This price also includes new insulated glass, caulking and insulation of
the complete frame. If you have any questions, please give me a call.
LaForce----------------------------- --------- $548.00
Fluor to install- ---------------- - - -_ -- $325.00
Sub total ------------ -- --- -- ------------------ $873.00
Markup --- -- ---- — ---------- _.. ------------- $ 59.90
Total----------------------------------------- $9
Sincerely
Richard Paulsen
President
-- 2-
I =�-
r .
pf
November 10, 2005�
Bill Aubrey
AEC
f
z f'
Oshkosh, WI..54901
Re, quotes for extra work Oshkosh Fire .Department
Bill
These are a couple of tile extras that we have talked over with Tim and 3eff One
is to change add bull nose to the masonry return at the top of the stairs by
bathroom,' The second is to add some 2x2 file at the slop sink in the upper bath l
room,
Sink backsplash ---- _- -------- -_ — $94.00
Sub total - - - - -- -- - - - - -- - - --- - $159.00
Markup --------------- -__ - $23.85
Total------------------ - - - - -- ----- -- -- $182.85 .. 1
Sincerely
Richard Paulsen
President
October 20, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 52
Bill
This is the cost for forming and pouring the house keeping pads under make up
air units in the basement. The cost for this work is $677.62.
I
Sincerely
Richard Paulsen
President
( , . Y-y
Q
October 14, 2008
Bill Aubrey
AEC
Oshkosh, WE 54901
Re; quotes for extra worm Oshkosh Fire Department
Bill
The cost to fill in reception area door is $385.25. If you have any questions,
please give me a call.
Sincerely .
Richard Paulsen
President
January 15, 200X
Tim Franz
Oshkosh Fire Department
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 55
Tim
This is the price to remove and replace five lockset to passage sets. If you have
any questions, please give me a call.
La Force ------ — --- - ,. ------- — ------ $588.00
Fluor-------------------------- - - - - -- $225.00
Sub total ----------------- — --------- $ 813.00
Mark up ------------------------------ $81.30
Total ------ ---------- - ,. --------------- $ 894.30
Sincerely
Richard Paulsen
President
BUILDING THE FUTURE
OF COMMUNITIES & BUSINESS
October 17, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 56
Bill
This is the break down for adding outlets in sleepy room, data line, conduits and
wire. If you have any questions, please give me a call.
Solar ----------------------------- $1,100.00
Fluor ------------------------------- $130.00
Sub total ------------------------- $1230.00
Mark up ----------------------------- $68.00
Total ----------------------------- $1,298.00
Sincerely
Richard Paulsen
President
4 .
Sept 15, 200)( V
Tim Franz
Oshkosh Fire Department
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.Q. 57
Tim
This is the cost to disconnect and retermination of cad wiring that is in the
existing wall in chiefs sleepy wall.
Van Ert- _—__. ----- .___ --- $900.00
Fluor ------------------------- $65.00
Sub total------------ --- ----- $965.00
Mark up ---------------- _ --- $51.50
Total ---- -- ---------- ------- $1016.50
Sincerely
Richard Paulsen
President
February 16, 2009
Tim Franz
Oshkosh Fire Department
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 58
Tim
This is the price for add additional controls to shut down the condensing units.
You gave Tower a go ahead to get this work completed. if you have any
questions, please give me a call.
Tower ---------- _. ---- $495.00
Fluor ---- ----- m --- - -- $ 65.00
Sub total ------------- $560.00
Mark up ----------- -- $28.00
Total ----------------- $588.00
Sincerely
Richard Paulsen
President
January 5, 200
Tim Franz
Oshkosh Fire Department
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O 59
Tim
We missed on the new closer and kick plates for bathroom door. If you have any
Questions, please give me a call.
La Force Hardware --------------------- $244.00
Fluor to install ---------- — --------------- $ 145.00
Sub Total ----- -- ----- -- ----- ---- -- ------ -- $389.00
Mark up ------------------------------------ $38.90
Total -------- ------- — -------------------- $427.90
Sincerely
Richard Paulsen
President
ry
January 14, 200k I
Tim Franz
Oshkosh Fire Department
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 60
Tim
This is the change orange to add pull station, strobe and switches that are required
by the fire inspector. If you have any questions, please give me a call.
Solar -------- -- ---- - - -_ - -- $2,785.00
Sub t --------------- — ---- $2,785.00
Mark up-------------- - -- - -- $139.25
Total -------------------------- $2,924.25
Sincerely
Richard Paulsen
President