HomeMy WebLinkAboutpw cnt 09-03 cng # 1 pts contractorsCHANGE ORDER # 1
DATED: May 1, 2009
TO: PTS Contractors Inc.
4075 Eaton Road
Green Bay, WI 54311
Your present contract with the City of Oshkosh, Contract No.
and changed as follows:
NET INCREASE TO: SECTION I - CONCRETE PAVING
NET INCREASE TO: SECTION IV - WATER MAIN
NET INCREASE TO CONTRACT:
M
Recommended:
i"*
Director of Publ c Works
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
09 -03 , is hereby amended
$7,100.00
$18,888.15
$25,988.15
CITY OF OSHKOSH
pp - . as l
1 �
Approved and accepted:
4 �) X9-� - PA -C-X I,�
ont
SECTION I - CONCRETE PAVING
CONTRACT: 09 -03 CHANGE ORDER # 1
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION 1
125
Furnish, install, maintain
and remove Inlet
Linear
INCREASE IN
DECFEASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
I
INSTALLED
NET
NET
COST PER
CONTRACT
CONTRACT
NUMBER
Additional days required for
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
PRICE
125
Furnish, install, maintain
and remove Inlet
Linear
INCREASE IN
DECREASE IN
ITEM
Protection, Type D
each
CONTRACT
25.00
25.00
NET
$140.00
$3,500.00
COIJTRACT
126
Additional days required for
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
F'RICE
Message Boards due to
Linear
D.O.T. delays on Utility
Foot
1
1 225.00
1 225.00
$14.50
$3,262.50
445
, Agreements
each
36.00
36.00
$100.00
$3,600.00
ADDITIONAL WORK: C.O. #1 -(ITEMS 125-126)-SUB-TOTAL $7,100.00 $0.00
NET INCREASE TO: SECTION I -
SECTION IV - WATER MAIN
ADDITIONAL WORK REQUIRED: C.O. # 1 - SECTION IV
$7,100.00
443
Additional price per foot for
16" Snap Lok Watermain
Linear
INCREASE IN
DECREASE IN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
COST PER
CONTRACT
COIJTRACT
NUMBER
Additional price per foot for
QUANTITIES
QUANTITIES
INCREASE
DECREASE
UNIT
PRICE
F'RICE
443
Additional price per foot for
16" Snap Lok Watermain
Linear
Pipe through casing pipes
Foot
715.00
715.00
$19.35
$13,835.25
444
Additional price per foot for
12" Snap Lok Watermain
Linear
Pipe through casing pipes
Foot
1
1 225.00
1 225.00
$14.50
$3,262.50
445
Furnish and install 6" - 45
degree bends, complete as
specified
each
12.00
12.00
$149.20
$1,790.40
ADDITIONAL WORK: C.O. # 1 (ITEMS 443 -445) -SUB-TOTAL $18,888.15 $0.00
NET INCREASE TO: SECTION IV - $18,888.15
NET INCREASE TO SECTIONS I & IV
NET DECREASE TO SECTIONS I & IV
NET INCREASE TO CONTRACT:
$25,988.15
$0.00
$25,988.15
Page 1