Loading...
HomeMy WebLinkAboutfluor bros fire dep renovation # 3CHANGE ORDER PROJECT: Fire Department Renovation CHANGE ORDER NUMBER: 3 - Revised 100 Court Street Oshkosh, WI 54901 INITIATION DATE. 3 -20 -09 ARCHITECT'S PROJECT NUMBER: 08018 CONTRACT FOR: Construction Services The Contract is changed as follows: 8. Add ceramic tile flooring & vinyl base on room 113 per change order dated Sept. 15 2008 $758.20 9. Remove existing data cabling & install conduit per change order dated Sept. 16 2008 $1,462.80 10. Paint remaining vehicle bays walls per change order dated Sept. 17 2008 $3,923.85 11. Paint rooms 124,129 and 133 per change order dated Sept. 17 2008 $563.95 12. Fur out walls in rooms 108, 110 and 112 at east walls per change order dated Oct. 2 "d , 2008 $1,220.90 13. Redo finishes in entry vestibule 100 per change order dated Oct. 2 "d , 2008 $6,942.05 14. Redo finishes in room 206 per change order dated Oct. 2 "d , 2008 $4,075.00 15. Fur out walls in bath room 107 per change order dated Oct. 7 2008 $821.00 16. Redo drywall soffit in existing kitchen per change order dated Oct. 8 2008 $646.25 17. Remove & replace exterior concrete slabs per change order dated Oct. 7 2008 $580.00 18. Extend new wall in room 200 per change order dated Oct. 8 2008 $649.00 19. Fill in existing pole hole at second floor per change order dated Oct. 8 2008 $1,642.00 20. Replace existing wood door at second floor bathroom per change order dated Oct. 13 2008 $1,061.35 22. Replace flooring in rooms 102, 106, 123 and 113 $4,412.30 24. Paint "C" channels at vehicle bay overhead doors per quote dated Oct. 2 "d , 2008 $342.70 27. Run new data cables per change order dated Oct. 15 2008 $7,650.50 Theoriginal Contract Sum was ................................................................ ............................... $ 607,450.00 Net change by previously authorized Change Orders ................................. ............................... $63,708.88 The Contract Sum prior to this Change Order was ..................................... ............................... $ 671,158.88 The Contract Sum will be Increased by this Change Order .......................... ............................... $36,751.85 The new Contract Sum including this Change Order will be ........................ ............................... $707,910.73 The Contract Time will be (increased) (decreased) (unchanged) by # days. Unchanged The Date of Substantial Completion as of the date of this Change order therefore is .................. Unchanged This Change Order is not valid until signed by the Owner, Contractor and Architect. Signature indicates agreement herewith, including any adjustment in the Contract Sum or Contract Time. ARCHITECT: OWNER: CONTRACTOR: AEC Arch itects/E ng ineers/Const. City of Oshkosh Fluor Bros. Construction Mgrs, LLC f +o 215 Church Ave. 203 Otter Avenue - fr499.1 �y Oshkosh, WI 54901 Oshkosh WI 54903 B BY:.- BY: PRINTED NAME. PRINT D M ( P D NAME. William A. Aubrey -0 DATE: DATE: T � (� DATE: T �°s e7 September 15, 2008 Bill Aubrey .ABC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 8 Bill This is the quote to furnish and install new ceramic floor and vinyl base in 113. This is the break down. Marcos ------ -- ------- - ,. -------- $ 920.00 Credit on carpet ------------- ($266.00) Sub total ------ --- .. ---- — ------ $654.00 Fluor supt-- ------- _ ------------ $65.00 Sub total ------ — --------------- $719.00 Mark up ------------------------- $39.20 Total ------------------------ -- $758.20 Sincerely Richard Paulsen President 4 September 16, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O.9 Bill This is the quote to remove data cables and then reinstall in conduit to meet code. Jeff requested to put a 4 -0' wall from the block wall to the east. This is the price for this work. We will also have to patch all the holes in the floor to receive new flooring Van Ert Electric ------------ $900.00 Komorowski Drywall - - - -- $220.00 Fluor labor ------------- -- -- $248.00 Sub total ------------ - - ----- $ 1,348.00 Mark u p--- .. --------- — ---- - ..$125.80 Total------------------ -. - -- $ 1,462.80 Sincerely Richard Paulsen President September 17, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 10 Bill This is the proposal to paint the masonry walls in Vehicle bay. Only the east was required to have paint. This is the breakdown. If you have any questions, please give me a call Best Ever Painting----------------- $3607.00 Fluor Time- - - -- ------------- - - - - -- $130.00 Sub total --------- -- ------ -- --------- $3,'737.00 Mark up-- ----------- - ---------------- $186.85 Total--------------------------------- $3923.85 Sincerely Richard Paulsen President September 17, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 11 Bill This is the proposal for painting Rooms 124,129and 133, Owner is to move everything so painting can get done. Best Ever Painting ------------------- $469.00 Fluor time- ----------------------- - - - - -- $65.00 Sub Mark up ---- — ---------------------- — -- $29-95 Total ------------------------------ — - — $563.95 Sincerely Richard Paulsen President October 2, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 12 Bill This is the proposal to fir out the walls in 108,110 and 112 and drywall over east walls. If you have any questions, please give me a call. Komorowski ---------- ---- - - - - -- $460.00 Fluor to fur out -- --- ----- ------- - - ----- $679.00 Sub total ------ _------ ..----- ---------- $1,130.00 Mark up ------------------------------- _$90.90 Total ------- - ,. -------------------------- $1220.90 Sincerely Richard Paulsen President October 2, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 13 This quote is for the removal and replacement of floor tile in Vestibule 100, Passage 120 and on south wall in Reception room 106, We also include furring the metal window panels and drywall to match. We will install oak trim around window and doorframes as requested. - Wallpaper is also included in 101 and 100, If you have any questions, please give me a call Komorowski -------------- - .. ------------------------ - --- ------ $1,175.00 Best Ever Painting -- -wall paper and staining -------------- $1,730.00 Floor removal ---------------------- _ --- -- ----- - ..- -------------- $1,040.00 Fir out walls, Oak Trim- ------------------------------- - - - - -- $2,498.00 Sub total- ----------------- — --- --------------------- .. -_ ---- .$6,443.00 Markup----------------------------------------------------------- $499.05 Total - ---- -------------------------------- — --- - ,. ------- - - - - -- $6,942.05 Bill Sincerely Richard Paulsen President October 2, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C. O. 14 Bill This is the break down for room 206. We will remove and replace carpet, remove paneling, add drywall to north and east wall, tape walls, paint all walls and add oak trim around doorway. Fluor ---- — -------------------------------- $650.00 Komorowski ----------------------------- $725.00 Best Ever Painting ----------------- --- $1,019.00 Solar Electric ----- -- --- ----------------- $100.00 Maccos Flooring ---------------------- $1,356.00 Sub total --------- - .. ---- - ------- — ------ $3,850.00 Mark up ---------------------------------- $225.00 Total- -------------- - - - - -- — --------- $4,075.00 Sincerely Richard Paulsen President October 7, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 15 Bill This is the change order for room 107 bath room. We will fur out existing walls and drywall. Painting was included in base bid. Fluor ------ ---------------- $250.00 Komorowski --------- -- -- $520.00 Sub total --------- - ------- $770.00 Mark up ---------------- --- $51.00 Total- -- ------------ -.. - -- $821.00 Sincerely Richard Paulsen President U October 8, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 16 Bill This is the breakdown for dry walling above soffit area in the kitchen. We will also add blocking and bracing to the existing drywall wall. Fl - - -- -- - $260.00 Komorowski --------- -- --- -- --- $275.00 Supt------------------------------ $65.00 Sub total------------------------ $600.00 Mark u p_ - .. ---- -- ---------------- $46.25 Total---------- - - - - -- ---- - - - - -- $646.25 Sincerely Richard Paulsen President October 7, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 17 Bill This is the quote to remove the front entrance slab and replace with wire mesh and dowel into the existing. The cost for this work is $580.00. Sincerely Richard Paulsen President October 8, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 18 Bill This is the quote to add onto the wall in room 200. If you have any questions, please give me a call. Komorowski ------------------------ $550.00 Supt----------------------------- - - - - -- $65.00 Sub total ----------------------------- $615.00 Markup ------------------------------- $34.00 Total---------------------------------- $649.00 Sincerely Richard Paulsen President October 8, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O. 19 Bill This is the proposal to fill in the other piece of structural floor in the closet on second floor. We will shore, drill in rebar , put one layer of rebar #5s and fill with 4000# concrete. The revised price is $1,642.00. We worked this in with the other pours. It help save on the costs. Sincerely Richard Paulsen President October 13, 2008 Bill Aubrey AEC Oshkosh, WE 54901 Re; quotes for extra work Oshkosh Fire Department C.O.20 Bill This is the change order requested to furnish a new 2- 8 "x6 -8" oak door in the second floor bathroom. We will remove all the existing hardware a router out the hinges and reinstall old hardware. If you have any questions, please give me a call. La Force ------------------------- $386.00 Fluor ------------------ w ---- — --- $ 356.00 Best Ever painting ---------- - -- $175.00 Sub total ------------------------- $917.00 Supt- -- --------- -- ---- ----- - - ---- $65.00 Sub total ------------------------ $991.20 Markup ------ - ., --- - .. ----- - --- -- -- $70.15 Total- ------------------- - - - - -- $1,061.3 5 Sincerely Richard Paulsen President October 13, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O.22 Bill This is a break down for changing the floor in rooms 102, 106,123,113. If you have any questions, please give me a call. Maccos flooring ----- ---------- $4066.00 Supt----------------------- - - - - -- - $130.00 Sub total ------------ --- -- - - - - -- -$4196.00 Mark up ------------- _. ----------- $216.30 Total --- _----- ..---------- - - - --- $4,412.30 Sincerely Richard Paulsen President October 2, 2008 Bill Aubrey AEC Oshkosh, WI. 54301 Re; quotes for extra work Oshkosh Fire Department C o - ?, `i Bill CIO , '�- -3 This is the price for painting the c- channels around garage door in vehicle garage. The cost for this work is $342.70. Sincerely Richard Paulsen President October 15, 2008 Bill Aubrey AEC Oshkosh, WI. 54901 Re; quotes for extra work Oshkosh Fire Department C.O.27 Bill This is the cost breakdown to run all new data cables, phone lines and all other materials for the project. If you have any questions, please give me a call. Van Ert -------- --------- .--- --« --- $7,150.00 Fluor-------------------------------- - - -$ 0.00 Sub t ------ - ,. ------- _-- . -------- $7,280.00 Mark up --------------------------- - - - -$ 57.50 T $7650.50 Sincerely Richard Paulsen President