HomeMy WebLinkAboutfluor bros fire dep renovation #1RiTI PT-
PROJECT: Fire Department Renovation
100 Court Street
Oshkosh, WI 54901
The Contract is changed as follows:
CHANGE ORDER NUMBER:
INITIATION DATE:
ARCHITECT
CONTRACT
1. New exterior soffit lighting per change order dated 7 -29 -08
2. Replace wall paper in existing first floor corridors per change order dated 8 -13 -08
3. Fill in door in office 123 per change order dated 8 -26 -08
4. New suspended ceilings per change order dated 8 -13 -08
5. Repaint existing rooms per change order dated 8 -20 -08
6. Replace existing kitchen cabinets per change order dated 8 -13 -08
7. Replace existing ceiling fans in apparatus bay per change order dated 8 -13 -08
The original Contract Sum was ................................................................ ...............................
Net change by previously authorized Change Orders ................................. ...............................
The Contract Sum prior to this Change Order was ..................................... ...............................
The Contract Sum will be Increased by this Change Order .......................... ...............................
The new Contract Sum including this Change Order will be ........................ ...............................
The Contract Time will be (increased) (decreased) (unchanged) by # days.
The Date of Substantial Completion as of the date of this Change order therefore is ..................
1 - Revised
3 -19 -09
08018
)n Services
$11,854.00
$9,043.65
$332.75
$14,712.90
$4,107.50
$15,573.14
$4,546.50
$ 607,450.00
$ 0.00
$ 607,450.00
$ 60,170.44
$ 667,620.44
Unchanged
Unchanged
This Change Order is not valid until signed by the Owner, Contractor and Architect.
Signature indicates agreement herewith, including any adjustment in the Contract Sum or Contract Time.
ARCHITECT:
AEC
Architects /Engineers /Construction
Managers, LLC
5703 County Road A
Oshkosh, WI 54,901_
PRINTED NAM
William A. Aubre
DATE: 1"'m -C6
OWNER: CONTRACTOR:
City of Oshkosh Fluor Bros. Construction
215 Church Ave. 203 Otter Avenue
Oshkosh, WI 54901 Oshkosh WI 54903
BY: BY:
�� �.�
�,!��.-
i
PRINTED NAME PRLt4TED NAME:
O R l
DATE: q Ix 10 1
DATE: 3 .- - 2- 3 — 0 -
July 29, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. #1
Bill
This is the proposal for new 16 recessed incandescent down lights and two
fluorescents light under canopies. Fluor will have to cut in new squares in
overhangs for new lights. If you have any questions, please give me a call
Materials------- - - - - -- $6300.00
Solar labor ----------- $3900.00 ,
Fluor labor ----------- $1040.00
Sub total --------- - -- $11,240.00
Mark up ---------------- $614.00
Total ------------ --- -- $11,854.00
Sincerely
U
Richard Paulsen
President
5 .
August 13, 2008
Bill Aubrey
AEC
Oshkosh, WI, 54901
Re; quotes for extra work Oshkosh Fire Department C. 0. #2
Bill
He is the break down for changing out the existing wallpaper in the main corridor.
We have a $35.00 per yard included in this bid. If you have any questions, please
give me a call.
Best Ever Painting ----------- -- ---- -- $8,613.00
Mark up -------------------------- M ----- $430.65
Total ------- -- -------------------------- $9,043.65
Sincerely
Richard Paulsen
President
August 26, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 3
Bill
This is the proposal to fill in one door in room 123 Office. This is the cost to stud
up and drywall. We will assume that the office and corridor is getting changed to
with paint and wallpaper. If not, we will have to add to this price for the
difference.
Komoroski-- .. ----- — ------- $275.00
Demo out door -------------- $40.00
Mark up ----------- - ., --------- $ 17.75
Total-------------- ---- - - - - -- $332.75
Sincerely
Richard Paulsen
President
July 29, 2008
Bill Aubrey
AEC
Oshkosh, WI, 54901
Re; quotes for extra work Oshkosh Fire Department C.O. 4
Bill
This is the proposal for adding new ceilings in the lower offices, stairwells and
lounge on second floor. If you have any questions, please give me a call
Great Lakes Ceilings --------------- - $10,718.00
Fluor demo ----------------------------- $1,980.00
Solar ---------------- _ ------------------- $1,220.00
Sub total ------------------------------- $13,918.00
Mark up----------------------------------- $794.90
Total ----------------------------------- $14,712.90
Sincerely
Richard Paulsen
President
October 2, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra. work Oshkosh Fire Department C.O. 5
Bill
This is the break down for room 206. We will remove and replace carpet, remove
paneling, add drywall to north and east wall, tape walls, paint all walls and add
oak trim around doorway.
Fluor— ------------------ ---- ------- -- ---- $650.00
Komorowski------ _--------------------- $725.00
Best Ever Painting ----------------- -- $1,019.00
Solar Electric ----------------- ---------- $100.00
Maccos Flooring ---------------- - - - - -- $1;356.00
Sub total- --------------- w - - - -- __ - - -- $ 3,850.00
Mark up ----------- -- --------------------- $257.50
Total- ---------- ------- -- ,.--- - - - - -_ - $ 4,107.50
Sincerely
Richard Paulsen
President
August 13, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re; quotes for extra work Oshkosh Fire Department C,O. 6
Bill
This is the cost break down for changing out the existing kitchen cabinets with
laminate finishes and heavy-duty hardware. If you have any questions, please give
me a call
CLS Cabinetry ---- — --- — ---- — ---- — -- $ 12,647,34
Fluor to install- -- — ------ --------------- $2085-00
Subtotal--------------------------- ---- - -$14, 732.34
Mark up ------- -- - - — --------- ----- - - - - -- -$840
Total---- ------------------------------- - -$15, 573.14
Sincerely
Richard Paulsen
President
August 13, 2008
Bill Aubrey
AEC
Oshkosh, WI. 54901
Re, quotes for extra work Oshkosh Fire Department C. 0. #7
Bill
This is the proposal as requested to furnish and install 10 new ceiling fans and to
add new conduits with 3- speed controls. These fans will have a five- year
warranty
Solar Elecrtric ------------------------ $4,330.00
Mark up ------------ --- ---------------- $216.50
Total-------------------------------- - - -$4
Sincerely
Richard Paulsen
President