HomeMy WebLinkAboutMiron Construction contract 08-05 # 1 water filtration planttr . .i E of E..0 S TS September 16, 2008 Change Order No. 1 Project: Water Filtration Plant Modifications and Demolition Project Owner: City of Oshkosh Contract: 08 -05 Contractor: Miron Construction Description of Change Request for Quote No. is Phase 1 Demolition subgrade improvement, excavation and backfill Sr& taota add $100,905 1 b Elimination of starter walls /water stop on interior baffle walls CT Basin RF OL 6a, deduct ($9,337) 1 c Security shrouded vents P P CQ. 03 add $3,248 1 d Access hatches, ladders and sumps R t= Q o6 add $6,402 le Reroute 4 inch sanitary sewer lateral P-P a 0 add $6,581 1 f Additional reinforcing steel in CT Basin Exterior Walls R r Ca Oct A add $10,449 1g Xypex Concrete Waterproofing Additive 'krq 70 add $69,168 1h Replace 1880 Water main 2;' a Ii add $176,829 ii Relocate Electrical Ductbank near Clearwells R P 61 i,1 deduct ($5,061) 1 j Reduce project work allowance from $200,000 to $0.00 deduct ($200,000) TOTAL VALUE OF THIS CHANGE ORDER ADD $159,184 Contract Price Adjustment Original Contract Price $6,070,273 Previous Change Orders $0 Adjustments in Contract Price this Change Order $159,184 Current Contract Price including this Change Order $6,229,457 This document shall become a supplement to the Contract and all provisions will apply hereto. RECOMMENDED Enginebr - CH2MHill or RPR - STS /v_r Date d Date RECOMME BY OWNER !): kw d G. -iQ, zl� Director of Public Works 10-17 -2,oc Date ('o o & Date Date I certify that provision has been made to pay the liability that will accrue to the City of Osh sh, Wisconsin under this Change Order. City CoApVoeer Date 4 . "I W1 , c Date STS i z EC M APPROVED BY OWNER