HomeMy WebLinkAboutMiron 08-05 # 3AECOM 558 N. Main Street, Oshkosh, Wisconsin 54901 T 920.235.0270 F 920.235.0321 www.aecom.com June 3, 2009 Change Order No. 3 Project: Water Filtration Plant Modifications and Demolition Project Owner: City of Oshkosh Contract: 08 -05 Contractor: Miron Construction Description of Change 1 AE:COM cc[1Ma ri JUN 112999 1 P IVI RON GONKRUCTION COMPANY INC. Change Order No.: Request for Quotation No. (Project Modification No.) 3a: RFQ 03A (PM 029 -1) — Additional Hatch Changes add $1,683.00 3b: RFQ 08A (PM 011 -4) — 42" to 30" Pipe Connection add $71,792.00 3c: RFQ 16 (PM 018 -1) — 24" RW Valves L.L.P.S. add $37,968.00 3d: RFQ 17A (PM 019 -2) — Small Diameter Piping add $57,237.00 3e: RFQ 22 (PM 027 -1) — Gate Access System Change add $0.00 3f: PM 028 — LP Gas Credit Cold Weather Concrete deduct ($3,025.00) 3g: PM 030 — Temporary Wiring at Center Clearwell add $651.00 3h: Submittal 088 -2 Pump Testing Credit deduct ($6,720.00) 3i: RFQ 23 (PM 03 1) — High Lift Pump Station Foundation add $5,319.00 3j: RFQ 24A (PM 032) — Re -route Ozone Cooling Water add $2,892.00 3k: RFQ 25 (PM 033) —Comb. Starter & Disconnect add $414.00 31: RFQ 26 (PM 034 -1) — CT /BWS & Clearwell Level Elements add $2,383.00 3m: RFQ 27 (PM 035 -2) — Elect. HH & Duckbank Changes deduct ($13,713.00) 3n: RFQ 28 (PM 036 -2) — PVC Coated Conduit add $8,993.00 30: RFQ 29 (PM 037) — Deletion of Mow Strip deduct ($574.00) 3p: RFQ 30 (PM 038) — Installation of a 24" Valve add $1,759.00 3q: RFQ 31 (PM 039 -2) — Change from 4" Conduit to 3" deduct ($378.00) 3r: RFQ 32 (PM 040 -2) — Delete Wireway at GAC deduct ($1,970.00) 3s: RFQ 33 (PM 042) — Clearwell Hatches deduct ($3,428.00) TOTAL VALUE OF THIS CHANGE ORDER ADD $161,283.00 Contract Price Adjustment 91 days Original Contract Price $6,070,273.00 Previous Change Orders $454,308.52 Adjustments in Contract Price this Change Order $161,283.00 Current Contract Price including this Change Order $6,685,864.52 Contract Duration Adjustment Original Contract Duration (Substantial Completion) 365 days Previous Change Orders 91 days Adjustment to Contract Duration this Change Order 0 days Current Contract Duration including this Change Order 456 days Revised Contract Substantial Completion Date Sept. 26, 2009 This document shall become a supplement to the Contract and all provisions will apply hereto. AECOM RECOMMEND i �. ngin er - CH2M Hill d RPR - XECOM INC r - Miron C Ua4d CL Vet RECOMMENDED BY OWNER Director of Public Works G 3 6 Date Date (0 260 Date Date — ;,, L/- 2c u l 6 C7 Date I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh., Wis nsm under this Change Order. - P City Cofilf Woller Date APPIR0,VED AS TO FO S pity orney _ Date AECOM APPROVED BY OWNER